Posted to common-dev@hadoop.apache.org by "Vivek Ratan (JIRA)" <ji...@apache.org> on 2008/10/06 19:31:44 UTC

[jira] Commented: (HADOOP-4211) Capacity Scheduler does not divide queue resources properly among users, when jobs are submitted one after other.

    [ https://issues.apache.org/jira/browse/HADOOP-4211?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=12637146#action_12637146 ] 

Vivek Ratan commented on HADOOP-4211:
-------------------------------------

Yes, part of this behavior is explained by HADOOP-4053. If none of the first three jobs is removed, and two additional jobs are submitted by two different users, then we have 5 users in the system, and each user gets 25% of the resources. When a slot is free, it is given to Job 4 (since Jobs 1, 2, and 3 don't have any tasks to run as they have completed). Slots are given to job4 till that job/user consumes n/4 slots. Then they're given to job5, up until n/4 slots are consumed by job5 too. With the fix for HADOOP-4053, the limits for job4 and job5 will be n/2, which is right. If either job4 or job5 does not have enough tasks to run at limit, additional slots are given to jobs that do have a need, even though they may be running at limit. 

I agree with you - you should re-evaluate this behavior once HADOOP-4053 is fixed. A lot depends on when jobs are marked complete and removed from the scheduler, as that determines the current user limit. 

> Capacity Scheduler does not divide queue resources properly among users, when jobs are submitted one after other.
> -----------------------------------------------------------------------------------------------------------------
>
>                 Key: HADOOP-4211
>                 URL: https://issues.apache.org/jira/browse/HADOOP-4211
>             Project: Hadoop Core
>          Issue Type: Bug
>          Components: contrib/capacity-sched
>    Affects Versions: 0.19.0
>         Environment: Mapred Cluster capacity with 204 Maps and 204 Reduces. User limit =25% and only one queue.
>            Reporter: Karam Singh
>            Assignee: Hemanth Yamijala
>            Priority: Blocker
>             Fix For: 0.19.0
>
>
> Capacity Scheduler does not divide queue resources  properly among users, when job are submitted one after other. E.g. user limit =25. Say User1's job is running. Then user2 submits a job. Then user1's job uses 75% and user2's job 25%=user limit.

-- 