Posted to dev@pig.apache.org by Jonathan Coveney <jc...@gmail.com> on 2012/03/27 07:29:23 UTC

What outstanding patches are must haves for 0.10? (path to a RC theater)

It's time to get serious about rolling an RC. 0.10 seems pretty strong...
are there any pressing JIRAs that people want to try and get in? Looking at
the open JIRAs with a fix labeled of 0.10 (which is admittedly possibly
incomplete), it looks like there isn't anything terribly seriously left...
I'd love to get the ball rolling on an RC so we can test it and identify
any bugs.

Thoughts?

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Jonathan Coveney <jc...@gmail.com>.
RE the CI/e2e, we should see if we can't get the e2e tests running on a CI
server.

2012/3/27 Jonathan Coveney <jc...@gmail.com>

> Bill,
>
> Thanks for going through those tickets. I marked them all as 0.10/0.11...
> 2616 seems like the only critical one, and the others are nice to haves (I
> imagine 2587and 2574 won't be super critical until we build out the systems
> that rely on them). All of them look pretty close so I'd have no problem
> with that.
>
> Hopefully tomorrow others can weigh in on their priorities. Then we can
> label things, work to finish them, and roll the RC.
>
> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>
>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>> by ourselves.
>>
>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>> wrote:
>> > Perhaps a big initiative for 0.11 could be to get the builds to the
>> point
>> > where flaky tests don't essentially gut the usefulness of the CI server
>> > (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>> that
>> > would be though, and what the benefit would be. But it's pretty
>> annoying to
>> > be able to wrap up a release when there are a bunch of "known useless"
>> > tests.
>> >
>> > 2012/3/26 Daniel Dai <da...@hortonworks.com>
>> >
>> >> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>> >> Russell's patches left. Before roll up RC, we need to make sure all
>> >> unit tests and e2e tests pass, I can help with this.
>> >>
>> >> Daniel
>> >>
>> >> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jcoveney@gmail.com
>> >
>> >> wrote:
>> >> > It's time to get serious about rolling an RC. 0.10 seems pretty
>> strong...
>> >> > are there any pressing JIRAs that people want to try and get in?
>> Looking
>> >> at
>> >> > the open JIRAs with a fix labeled of 0.10 (which is admittedly
>> possibly
>> >> > incomplete), it looks like there isn't anything terribly seriously
>> >> left...
>> >> > I'd love to get the ball rolling on an RC so we can test it and
>> identify
>> >> > any bugs.
>> >> >
>> >> > Thoughts?
>> >>
>>
>
>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Dmitriy Ryaboy <dv...@gmail.com>.
WOOT.

On Fri, Apr 6, 2012 at 1:53 PM, Daniel Dai <da...@hortonworks.com> wrote:
> Ok, let's cut off the 0.10.0 release. I will start testing during the weekend.
>
> Daniel
>
> On Wed, Apr 4, 2012 at 11:17 PM, Russell Jurney
> <ru...@gmail.com> wrote:
>> JRuby and a working AvroStorage. Woohoo!
>>
>> Russell Jurney http://datasyndrome.com
>>
>> On Apr 4, 2012, at 10:48 PM, Alan Gates <ga...@hortonworks.com> wrote:
>>
>>> +1.  Let's roll 0.10.
>>>
>>> Alan.
>>>
>>> On Apr 4, 2012, at 9:34 PM, Jon Coveney wrote:
>>>
>>>> I think we got everything important in. Am excited
>>>>
>>>> On Apr 3, 2012, at 4:22 PM, Daniel Dai <da...@hortonworks.com> wrote:
>>>>
>>>>> Is everything ready now? Can we start the release process?
>>>>>
>>>>> Daniel
>>>>>
>>>>> On Tue, Mar 27, 2012 at 11:54 AM, Alan Gates <ga...@hortonworks.com> wrote:
>>>>>> Sure, that's fine.
>>>>>>
>>>>>> Alan.
>>>>>>
>>>>>> On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:
>>>>>>
>>>>>>> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
>>>>>>> testing is going to happen during the week anyway, and I'd like to give
>>>>>>> true believers the weekend to fix up anything that is lacking.
>>>>>>>
>>>>>>> Sound ok?
>>>>>>>
>>>>>>> 2012/3/27 Alan Gates <ga...@hortonworks.com>
>>>>>>>
>>>>>>>> I propose we set a deadline and say patches need to be ready by that day,
>>>>>>>> or they don't go in.  Otherwise this time next week there will be another
>>>>>>>> set of patches people would like to see.  I'd say the deadline should be
>>>>>>>> 3/30 (this Friday).  That would mean we could address any final test
>>>>>>>> failures we see and start rolling the RC next week.
>>>>>>>>
>>>>>>>> Alan.
>>>>>>>>
>>>>>>>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>>>>>>>>
>>>>>>>>> Bill,
>>>>>>>>>
>>>>>>>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>>>>>>>> 2616 seems like the only critical one, and the others are nice to haves
>>>>>>>> (I
>>>>>>>>> imagine 2587and 2574 won't be super critical until we build out the
>>>>>>>> systems
>>>>>>>>> that rely on them). All of them look pretty close so I'd have no problem
>>>>>>>>> with that.
>>>>>>>>>
>>>>>>>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>>>>>>>> label things, work to finish them, and roll the RC.
>>>>>>>>>
>>>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>>>>
>>>>>>>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>>>>>>>> by ourselves.
>>>>>>>>>>
>>>>>>>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>>>>>>>> wrote:
>>>>>>>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>>>>>>>> point
>>>>>>>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>>>>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>>>>>>>> that
>>>>>>>>>>> would be though, and what the benefit would be. But it's pretty
>>>>>>>> annoying
>>>>>>>>>> to
>>>>>>>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>>>>>>>> tests.
>>>>>>>>>>>
>>>>>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>>>>>>
>>>>>>>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>>>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>>>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>>>>>>>>
>>>>>>>>>>>> Daniel
>>>>>>>>>>>>
>>>>>>>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>>>>>>>> jcoveney@gmail.com>
>>>>>>>>>>>> wrote:
>>>>>>>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>>>>>>>> strong...
>>>>>>>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>>>>>>>> Looking
>>>>>>>>>>>> at
>>>>>>>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>>>>>>>> possibly
>>>>>>>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>>>>>>>> left...
>>>>>>>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>>>>>>>> identify
>>>>>>>>>>>>> any bugs.
>>>>>>>>>>>>>
>>>>>>>>>>>>> Thoughts?
>>>>>>>>>>>>
>>>>>>>>>>
>>>>>>>>
>>>>>>>>
>>>>>>
>>>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Daniel Dai <da...@hortonworks.com>.
Ok, let's cut off the 0.10.0 release. I will start testing during the weekend.

Daniel

On Wed, Apr 4, 2012 at 11:17 PM, Russell Jurney
<ru...@gmail.com> wrote:
> JRuby and a working AvroStorage. Woohoo!
>
> Russell Jurney http://datasyndrome.com
>
> On Apr 4, 2012, at 10:48 PM, Alan Gates <ga...@hortonworks.com> wrote:
>
>> +1.  Let's roll 0.10.
>>
>> Alan.
>>
>> On Apr 4, 2012, at 9:34 PM, Jon Coveney wrote:
>>
>>> I think we got everything important in. Am excited
>>>
>>> On Apr 3, 2012, at 4:22 PM, Daniel Dai <da...@hortonworks.com> wrote:
>>>
>>>> Is everything ready now? Can we start the release process?
>>>>
>>>> Daniel
>>>>
>>>> On Tue, Mar 27, 2012 at 11:54 AM, Alan Gates <ga...@hortonworks.com> wrote:
>>>>> Sure, that's fine.
>>>>>
>>>>> Alan.
>>>>>
>>>>> On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:
>>>>>
>>>>>> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
>>>>>> testing is going to happen during the week anyway, and I'd like to give
>>>>>> true believers the weekend to fix up anything that is lacking.
>>>>>>
>>>>>> Sound ok?
>>>>>>
>>>>>> 2012/3/27 Alan Gates <ga...@hortonworks.com>
>>>>>>
>>>>>>> I propose we set a deadline and say patches need to be ready by that day,
>>>>>>> or they don't go in.  Otherwise this time next week there will be another
>>>>>>> set of patches people would like to see.  I'd say the deadline should be
>>>>>>> 3/30 (this Friday).  That would mean we could address any final test
>>>>>>> failures we see and start rolling the RC next week.
>>>>>>>
>>>>>>> Alan.
>>>>>>>
>>>>>>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>>>>>>>
>>>>>>>> Bill,
>>>>>>>>
>>>>>>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>>>>>>> 2616 seems like the only critical one, and the others are nice to haves
>>>>>>> (I
>>>>>>>> imagine 2587and 2574 won't be super critical until we build out the
>>>>>>> systems
>>>>>>>> that rely on them). All of them look pretty close so I'd have no problem
>>>>>>>> with that.
>>>>>>>>
>>>>>>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>>>>>>> label things, work to finish them, and roll the RC.
>>>>>>>>
>>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>>>
>>>>>>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>>>>>>> by ourselves.
>>>>>>>>>
>>>>>>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>>>>>>> wrote:
>>>>>>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>>>>>>> point
>>>>>>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>>>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>>>>>>> that
>>>>>>>>>> would be though, and what the benefit would be. But it's pretty
>>>>>>> annoying
>>>>>>>>> to
>>>>>>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>>>>>>> tests.
>>>>>>>>>>
>>>>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>>>>>
>>>>>>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>>>>>>>
>>>>>>>>>>> Daniel
>>>>>>>>>>>
>>>>>>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>>>>>>> jcoveney@gmail.com>
>>>>>>>>>>> wrote:
>>>>>>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>>>>>>> strong...
>>>>>>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>>>>>>> Looking
>>>>>>>>>>> at
>>>>>>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>>>>>>> possibly
>>>>>>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>>>>>>> left...
>>>>>>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>>>>>>> identify
>>>>>>>>>>>> any bugs.
>>>>>>>>>>>>
>>>>>>>>>>>> Thoughts?
>>>>>>>>>>>
>>>>>>>>>
>>>>>>>
>>>>>>>
>>>>>
>>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Russell Jurney <ru...@gmail.com>.
JRuby and a working AvroStorage. Woohoo!

Russell Jurney http://datasyndrome.com

On Apr 4, 2012, at 10:48 PM, Alan Gates <ga...@hortonworks.com> wrote:

> +1.  Let's roll 0.10.
> 
> Alan.
> 
> On Apr 4, 2012, at 9:34 PM, Jon Coveney wrote:
> 
>> I think we got everything important in. Am excited
>> 
>> On Apr 3, 2012, at 4:22 PM, Daniel Dai <da...@hortonworks.com> wrote:
>> 
>>> Is everything ready now? Can we start the release process?
>>> 
>>> Daniel
>>> 
>>> On Tue, Mar 27, 2012 at 11:54 AM, Alan Gates <ga...@hortonworks.com> wrote:
>>>> Sure, that's fine.
>>>> 
>>>> Alan.
>>>> 
>>>> On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:
>>>> 
>>>>> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
>>>>> testing is going to happen during the week anyway, and I'd like to give
>>>>> true believers the weekend to fix up anything that is lacking.
>>>>> 
>>>>> Sound ok?
>>>>> 
>>>>> 2012/3/27 Alan Gates <ga...@hortonworks.com>
>>>>> 
>>>>>> I propose we set a deadline and say patches need to be ready by that day,
>>>>>> or they don't go in.  Otherwise this time next week there will be another
>>>>>> set of patches people would like to see.  I'd say the deadline should be
>>>>>> 3/30 (this Friday).  That would mean we could address any final test
>>>>>> failures we see and start rolling the RC next week.
>>>>>> 
>>>>>> Alan.
>>>>>> 
>>>>>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>>>>>> 
>>>>>>> Bill,
>>>>>>> 
>>>>>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>>>>>> 2616 seems like the only critical one, and the others are nice to haves
>>>>>> (I
>>>>>>> imagine 2587and 2574 won't be super critical until we build out the
>>>>>> systems
>>>>>>> that rely on them). All of them look pretty close so I'd have no problem
>>>>>>> with that.
>>>>>>> 
>>>>>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>>>>>> label things, work to finish them, and roll the RC.
>>>>>>> 
>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>> 
>>>>>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>>>>>> by ourselves.
>>>>>>>> 
>>>>>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>>>>>> wrote:
>>>>>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>>>>>> point
>>>>>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>>>>>> that
>>>>>>>>> would be though, and what the benefit would be. But it's pretty
>>>>>> annoying
>>>>>>>> to
>>>>>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>>>>>> tests.
>>>>>>>>> 
>>>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>>>> 
>>>>>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>>>>>> 
>>>>>>>>>> Daniel
>>>>>>>>>> 
>>>>>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>>>>>> jcoveney@gmail.com>
>>>>>>>>>> wrote:
>>>>>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>>>>>> strong...
>>>>>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>>>>>> Looking
>>>>>>>>>> at
>>>>>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>>>>>> possibly
>>>>>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>>>>>> left...
>>>>>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>>>>>> identify
>>>>>>>>>>> any bugs.
>>>>>>>>>>> 
>>>>>>>>>>> Thoughts?
>>>>>>>>>> 
>>>>>>>> 
>>>>>> 
>>>>>> 
>>>> 
> 

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Alan Gates <ga...@hortonworks.com>.
+1.  Let's roll 0.10.

Alan.

On Apr 4, 2012, at 9:34 PM, Jon Coveney wrote:

> I think we got everything important in. Am excited
> 
> On Apr 3, 2012, at 4:22 PM, Daniel Dai <da...@hortonworks.com> wrote:
> 
>> Is everything ready now? Can we start the release process?
>> 
>> Daniel
>> 
>> On Tue, Mar 27, 2012 at 11:54 AM, Alan Gates <ga...@hortonworks.com> wrote:
>>> Sure, that's fine.
>>> 
>>> Alan.
>>> 
>>> On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:
>>> 
>>>> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
>>>> testing is going to happen during the week anyway, and I'd like to give
>>>> true believers the weekend to fix up anything that is lacking.
>>>> 
>>>> Sound ok?
>>>> 
>>>> 2012/3/27 Alan Gates <ga...@hortonworks.com>
>>>> 
>>>>> I propose we set a deadline and say patches need to be ready by that day,
>>>>> or they don't go in.  Otherwise this time next week there will be another
>>>>> set of patches people would like to see.  I'd say the deadline should be
>>>>> 3/30 (this Friday).  That would mean we could address any final test
>>>>> failures we see and start rolling the RC next week.
>>>>> 
>>>>> Alan.
>>>>> 
>>>>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>>>>> 
>>>>>> Bill,
>>>>>> 
>>>>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>>>>> 2616 seems like the only critical one, and the others are nice to haves
>>>>> (I
>>>>>> imagine 2587and 2574 won't be super critical until we build out the
>>>>> systems
>>>>>> that rely on them). All of them look pretty close so I'd have no problem
>>>>>> with that.
>>>>>> 
>>>>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>>>>> label things, work to finish them, and roll the RC.
>>>>>> 
>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>> 
>>>>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>>>>> by ourselves.
>>>>>>> 
>>>>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>>>>> wrote:
>>>>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>>>>> point
>>>>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>>>>> that
>>>>>>>> would be though, and what the benefit would be. But it's pretty
>>>>> annoying
>>>>>>> to
>>>>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>>>>> tests.
>>>>>>>> 
>>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>>> 
>>>>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>>>>> 
>>>>>>>>> Daniel
>>>>>>>>> 
>>>>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>>>>> jcoveney@gmail.com>
>>>>>>>>> wrote:
>>>>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>>>>> strong...
>>>>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>>>>> Looking
>>>>>>>>> at
>>>>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>>>>> possibly
>>>>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>>>>> left...
>>>>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>>>>> identify
>>>>>>>>>> any bugs.
>>>>>>>>>> 
>>>>>>>>>> Thoughts?
>>>>>>>>> 
>>>>>>> 
>>>>> 
>>>>> 
>>> 


Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Jon Coveney <jc...@gmail.com>.
I think we got everything important in. Am excited

On Apr 3, 2012, at 4:22 PM, Daniel Dai <da...@hortonworks.com> wrote:

> Is everything ready now? Can we start the release process?
> 
> Daniel
> 
> On Tue, Mar 27, 2012 at 11:54 AM, Alan Gates <ga...@hortonworks.com> wrote:
>> Sure, that's fine.
>> 
>> Alan.
>> 
>> On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:
>> 
>>> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
>>> testing is going to happen during the week anyway, and I'd like to give
>>> true believers the weekend to fix up anything that is lacking.
>>> 
>>> Sound ok?
>>> 
>>> 2012/3/27 Alan Gates <ga...@hortonworks.com>
>>> 
>>>> I propose we set a deadline and say patches need to be ready by that day,
>>>> or they don't go in.  Otherwise this time next week there will be another
>>>> set of patches people would like to see.  I'd say the deadline should be
>>>> 3/30 (this Friday).  That would mean we could address any final test
>>>> failures we see and start rolling the RC next week.
>>>> 
>>>> Alan.
>>>> 
>>>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>>>> 
>>>>> Bill,
>>>>> 
>>>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>>>> 2616 seems like the only critical one, and the others are nice to haves
>>>> (I
>>>>> imagine 2587and 2574 won't be super critical until we build out the
>>>> systems
>>>>> that rely on them). All of them look pretty close so I'd have no problem
>>>>> with that.
>>>>> 
>>>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>>>> label things, work to finish them, and roll the RC.
>>>>> 
>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>> 
>>>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>>>> by ourselves.
>>>>>> 
>>>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>>>> wrote:
>>>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>>>> point
>>>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>>>> that
>>>>>>> would be though, and what the benefit would be. But it's pretty
>>>> annoying
>>>>>> to
>>>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>>>> tests.
>>>>>>> 
>>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>> 
>>>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>>>> 
>>>>>>>> Daniel
>>>>>>>> 
>>>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>>>> jcoveney@gmail.com>
>>>>>>>> wrote:
>>>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>>>> strong...
>>>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>>>> Looking
>>>>>>>> at
>>>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>>>> possibly
>>>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>>>> left...
>>>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>>>> identify
>>>>>>>>> any bugs.
>>>>>>>>> 
>>>>>>>>> Thoughts?
>>>>>>>> 
>>>>>> 
>>>> 
>>>> 
>> 

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Daniel Dai <da...@hortonworks.com>.
Is everything ready now? Can we start the release process?

Daniel

On Tue, Mar 27, 2012 at 11:54 AM, Alan Gates <ga...@hortonworks.com> wrote:
> Sure, that's fine.
>
> Alan.
>
> On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:
>
>> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
>> testing is going to happen during the week anyway, and I'd like to give
>> true believers the weekend to fix up anything that is lacking.
>>
>> Sound ok?
>>
>> 2012/3/27 Alan Gates <ga...@hortonworks.com>
>>
>>> I propose we set a deadline and say patches need to be ready by that day,
>>> or they don't go in.  Otherwise this time next week there will be another
>>> set of patches people would like to see.  I'd say the deadline should be
>>> 3/30 (this Friday).  That would mean we could address any final test
>>> failures we see and start rolling the RC next week.
>>>
>>> Alan.
>>>
>>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>>>
>>>> Bill,
>>>>
>>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>>> 2616 seems like the only critical one, and the others are nice to haves
>>> (I
>>>> imagine 2587and 2574 won't be super critical until we build out the
>>> systems
>>>> that rely on them). All of them look pretty close so I'd have no problem
>>>> with that.
>>>>
>>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>>> label things, work to finish them, and roll the RC.
>>>>
>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>
>>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>>> by ourselves.
>>>>>
>>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>>> wrote:
>>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>>> point
>>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>>> that
>>>>>> would be though, and what the benefit would be. But it's pretty
>>> annoying
>>>>> to
>>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>>> tests.
>>>>>>
>>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>>>
>>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>>>
>>>>>>> Daniel
>>>>>>>
>>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>>> jcoveney@gmail.com>
>>>>>>> wrote:
>>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>>> strong...
>>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>>> Looking
>>>>>>> at
>>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>>> possibly
>>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>>> left...
>>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>>> identify
>>>>>>>> any bugs.
>>>>>>>>
>>>>>>>> Thoughts?
>>>>>>>
>>>>>
>>>
>>>
>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Alan Gates <ga...@hortonworks.com>.
Sure, that's fine.

Alan.

On Mar 27, 2012, at 11:46 AM, Jonathan Coveney wrote:

> I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
> testing is going to happen during the week anyway, and I'd like to give
> true believers the weekend to fix up anything that is lacking.
> 
> Sound ok?
> 
> 2012/3/27 Alan Gates <ga...@hortonworks.com>
> 
>> I propose we set a deadline and say patches need to be ready by that day,
>> or they don't go in.  Otherwise this time next week there will be another
>> set of patches people would like to see.  I'd say the deadline should be
>> 3/30 (this Friday).  That would mean we could address any final test
>> failures we see and start rolling the RC next week.
>> 
>> Alan.
>> 
>> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>> 
>>> Bill,
>>> 
>>> Thanks for going through those tickets. I marked them all as 0.10/0.11...
>>> 2616 seems like the only critical one, and the others are nice to haves
>> (I
>>> imagine 2587and 2574 won't be super critical until we build out the
>> systems
>>> that rely on them). All of them look pretty close so I'd have no problem
>>> with that.
>>> 
>>> Hopefully tomorrow others can weigh in on their priorities. Then we can
>>> label things, work to finish them, and roll the RC.
>>> 
>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>> 
>>>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>>>> by ourselves.
>>>> 
>>>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>>>> wrote:
>>>>> Perhaps a big initiative for 0.11 could be to get the builds to the
>> point
>>>>> where flaky tests don't essentially gut the usefulness of the CI server
>>>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
>> that
>>>>> would be though, and what the benefit would be. But it's pretty
>> annoying
>>>> to
>>>>> be able to wrap up a release when there are a bunch of "known useless"
>>>>> tests.
>>>>> 
>>>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>>>> 
>>>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>>>> unit tests and e2e tests pass, I can help with this.
>>>>>> 
>>>>>> Daniel
>>>>>> 
>>>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
>> jcoveney@gmail.com>
>>>>>> wrote:
>>>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>>>> strong...
>>>>>>> are there any pressing JIRAs that people want to try and get in?
>>>> Looking
>>>>>> at
>>>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>>>> possibly
>>>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>>>> left...
>>>>>>> I'd love to get the ball rolling on an RC so we can test it and
>>>> identify
>>>>>>> any bugs.
>>>>>>> 
>>>>>>> Thoughts?
>>>>>> 
>>>> 
>> 
>> 


Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Jonathan Coveney <jc...@gmail.com>.
I agree, Alan, though I think we should make the deadline Monday, 4/2. Most
testing is going to happen during the week anyway, and I'd like to give
true believers the weekend to fix up anything that is lacking.

Sound ok?

2012/3/27 Alan Gates <ga...@hortonworks.com>

> I propose we set a deadline and say patches need to be ready by that day,
> or they don't go in.  Otherwise this time next week there will be another
> set of patches people would like to see.  I'd say the deadline should be
> 3/30 (this Friday).  That would mean we could address any final test
> failures we see and start rolling the RC next week.
>
> Alan.
>
> On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:
>
> > Bill,
> >
> > Thanks for going through those tickets. I marked them all as 0.10/0.11...
> > 2616 seems like the only critical one, and the others are nice to haves
> (I
> > imagine 2587and 2574 won't be super critical until we build out the
> systems
> > that rely on them). All of them look pretty close so I'd have no problem
> > with that.
> >
> > Hopefully tomorrow others can weigh in on their priorities. Then we can
> > label things, work to finish them, and roll the RC.
> >
> > 2012/3/26 Daniel Dai <da...@hortonworks.com>
> >
> >> Yes, but CI anyway only run unit tests, we will have to run e2e test
> >> by ourselves.
> >>
> >> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
> >> wrote:
> >>> Perhaps a big initiative for 0.11 could be to get the builds to the
> point
> >>> where flaky tests don't essentially gut the usefulness of the CI server
> >>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult
> that
> >>> would be though, and what the benefit would be. But it's pretty
> annoying
> >> to
> >>> be able to wrap up a release when there are a bunch of "known useless"
> >>> tests.
> >>>
> >>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
> >>>
> >>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
> >>>> Russell's patches left. Before roll up RC, we need to make sure all
> >>>> unit tests and e2e tests pass, I can help with this.
> >>>>
> >>>> Daniel
> >>>>
> >>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <
> jcoveney@gmail.com>
> >>>> wrote:
> >>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
> >> strong...
> >>>>> are there any pressing JIRAs that people want to try and get in?
> >> Looking
> >>>> at
> >>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
> >> possibly
> >>>>> incomplete), it looks like there isn't anything terribly seriously
> >>>> left...
> >>>>> I'd love to get the ball rolling on an RC so we can test it and
> >> identify
> >>>>> any bugs.
> >>>>>
> >>>>> Thoughts?
> >>>>
> >>
>
>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Alan Gates <ga...@hortonworks.com>.
I propose we set a deadline and say patches need to be ready by that day, or they don't go in.  Otherwise this time next week there will be another set of patches people would like to see.  I'd say the deadline should be 3/30 (this Friday).  That would mean we could address any final test failures we see and start rolling the RC next week.

Alan.

On Mar 27, 2012, at 12:00 AM, Jonathan Coveney wrote:

> Bill,
> 
> Thanks for going through those tickets. I marked them all as 0.10/0.11...
> 2616 seems like the only critical one, and the others are nice to haves (I
> imagine 2587and 2574 won't be super critical until we build out the systems
> that rely on them). All of them look pretty close so I'd have no problem
> with that.
> 
> Hopefully tomorrow others can weigh in on their priorities. Then we can
> label things, work to finish them, and roll the RC.
> 
> 2012/3/26 Daniel Dai <da...@hortonworks.com>
> 
>> Yes, but CI anyway only run unit tests, we will have to run e2e test
>> by ourselves.
>> 
>> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
>> wrote:
>>> Perhaps a big initiative for 0.11 could be to get the builds to the point
>>> where flaky tests don't essentially gut the usefulness of the CI server
>>> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult that
>>> would be though, and what the benefit would be. But it's pretty annoying
>> to
>>> be able to wrap up a release when there are a bunch of "known useless"
>>> tests.
>>> 
>>> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>>> 
>>>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>>>> Russell's patches left. Before roll up RC, we need to make sure all
>>>> unit tests and e2e tests pass, I can help with this.
>>>> 
>>>> Daniel
>>>> 
>>>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jc...@gmail.com>
>>>> wrote:
>>>>> It's time to get serious about rolling an RC. 0.10 seems pretty
>> strong...
>>>>> are there any pressing JIRAs that people want to try and get in?
>> Looking
>>>> at
>>>>> the open JIRAs with a fix labeled of 0.10 (which is admittedly
>> possibly
>>>>> incomplete), it looks like there isn't anything terribly seriously
>>>> left...
>>>>> I'd love to get the ball rolling on an RC so we can test it and
>> identify
>>>>> any bugs.
>>>>> 
>>>>> Thoughts?
>>>> 
>> 


Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Jonathan Coveney <jc...@gmail.com>.
Bill,

Thanks for going through those tickets. I marked them all as 0.10/0.11...
2616 seems like the only critical one, and the others are nice to haves (I
imagine 2587and 2574 won't be super critical until we build out the systems
that rely on them). All of them look pretty close so I'd have no problem
with that.

Hopefully tomorrow others can weigh in on their priorities. Then we can
label things, work to finish them, and roll the RC.

2012/3/26 Daniel Dai <da...@hortonworks.com>

> Yes, but CI anyway only run unit tests, we will have to run e2e test
> by ourselves.
>
> On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>
> wrote:
> > Perhaps a big initiative for 0.11 could be to get the builds to the point
> > where flaky tests don't essentially gut the usefulness of the CI server
> > (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult that
> > would be though, and what the benefit would be. But it's pretty annoying
> to
> > be able to wrap up a release when there are a bunch of "known useless"
> > tests.
> >
> > 2012/3/26 Daniel Dai <da...@hortonworks.com>
> >
> >> Once PIG-2317 check in, only document patch (PIG-2601) and some of
> >> Russell's patches left. Before roll up RC, we need to make sure all
> >> unit tests and e2e tests pass, I can help with this.
> >>
> >> Daniel
> >>
> >> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jc...@gmail.com>
> >> wrote:
> >> > It's time to get serious about rolling an RC. 0.10 seems pretty
> strong...
> >> > are there any pressing JIRAs that people want to try and get in?
> Looking
> >> at
> >> > the open JIRAs with a fix labeled of 0.10 (which is admittedly
> possibly
> >> > incomplete), it looks like there isn't anything terribly seriously
> >> left...
> >> > I'd love to get the ball rolling on an RC so we can test it and
> identify
> >> > any bugs.
> >> >
> >> > Thoughts?
> >>
>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Daniel Dai <da...@hortonworks.com>.
Yes, but CI anyway only run unit tests, we will have to run e2e test
by ourselves.

On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com> wrote:
> Perhaps a big initiative for 0.11 could be to get the builds to the point
> where flaky tests don't essentially gut the usefulness of the CI server
> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult that
> would be though, and what the benefit would be. But it's pretty annoying to
> be able to wrap up a release when there are a bunch of "known useless"
> tests.
>
> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>
>> Once PIG-2317 check in, only document patch (PIG-2601) and some of
>> Russell's patches left. Before roll up RC, we need to make sure all
>> unit tests and e2e tests pass, I can help with this.
>>
>> Daniel
>>
>> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jc...@gmail.com>
>> wrote:
>> > It's time to get serious about rolling an RC. 0.10 seems pretty strong...
>> > are there any pressing JIRAs that people want to try and get in? Looking
>> at
>> > the open JIRAs with a fix labeled of 0.10 (which is admittedly possibly
>> > incomplete), it looks like there isn't anything terribly seriously
>> left...
>> > I'd love to get the ball rolling on an RC so we can test it and identify
>> > any bugs.
>> >
>> > Thoughts?
>>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Bill Graham <bi...@gmail.com>.
PIG-2616 should be a blocker bug. It's to fix something broken and it's
ready to commit.

PIG-2574 and PIG-2587 are low-risk and are required to implement
functionality to make better estimates for number of reducers. It would be
great to get these in and I should have an updated PIG-2574 in the next day
or two.

PIG-2547 is a nice bit of new functionality that will simplify writing UDFs
that would be nice to ship if possible.

thanks,
Bill


On Mon, Mar 26, 2012 at 10:44 PM, Jonathan Coveney <jc...@gmail.com>wrote:

> Perhaps a big initiative for 0.11 could be to get the builds to the point
> where flaky tests don't essentially gut the usefulness of the CI server
> (Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult that
> would be though, and what the benefit would be. But it's pretty annoying to
> be able to wrap up a release when there are a bunch of "known useless"
> tests.
>
> 2012/3/26 Daniel Dai <da...@hortonworks.com>
>
> > Once PIG-2317 check in, only document patch (PIG-2601) and some of
> > Russell's patches left. Before roll up RC, we need to make sure all
> > unit tests and e2e tests pass, I can help with this.
> >
> > Daniel
> >
> > On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jc...@gmail.com>
> > wrote:
> > > It's time to get serious about rolling an RC. 0.10 seems pretty
> strong...
> > > are there any pressing JIRAs that people want to try and get in?
> Looking
> > at
> > > the open JIRAs with a fix labeled of 0.10 (which is admittedly possibly
> > > incomplete), it looks like there isn't anything terribly seriously
> > left...
> > > I'd love to get the ball rolling on an RC so we can test it and
> identify
> > > any bugs.
> > >
> > > Thoughts?
> >
>



-- 
*Note that I'm no longer using my Yahoo! email address. Please email me at
billgraham@gmail.com going forward.*

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Jonathan Coveney <jc...@gmail.com>.
Perhaps a big initiative for 0.11 could be to get the builds to the point
where flaky tests don't essentially gut the usefulness of the CI server
(Pig 0.9 hasn't passed in 6 months, etc). I'm not sure how difficult that
would be though, and what the benefit would be. But it's pretty annoying to
be able to wrap up a release when there are a bunch of "known useless"
tests.

2012/3/26 Daniel Dai <da...@hortonworks.com>

> Once PIG-2317 check in, only document patch (PIG-2601) and some of
> Russell's patches left. Before roll up RC, we need to make sure all
> unit tests and e2e tests pass, I can help with this.
>
> Daniel
>
> On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jc...@gmail.com>
> wrote:
> > It's time to get serious about rolling an RC. 0.10 seems pretty strong...
> > are there any pressing JIRAs that people want to try and get in? Looking
> at
> > the open JIRAs with a fix labeled of 0.10 (which is admittedly possibly
> > incomplete), it looks like there isn't anything terribly seriously
> left...
> > I'd love to get the ball rolling on an RC so we can test it and identify
> > any bugs.
> >
> > Thoughts?
>

Re: What outstanding patches are must haves for 0.10? (path to a RC theater)

Posted by Daniel Dai <da...@hortonworks.com>.
Once PIG-2317 check in, only document patch (PIG-2601) and some of
Russell's patches left. Before roll up RC, we need to make sure all
unit tests and e2e tests pass, I can help with this.

Daniel

On Mon, Mar 26, 2012 at 10:29 PM, Jonathan Coveney <jc...@gmail.com> wrote:
> It's time to get serious about rolling an RC. 0.10 seems pretty strong...
> are there any pressing JIRAs that people want to try and get in? Looking at
> the open JIRAs with a fix labeled of 0.10 (which is admittedly possibly
> incomplete), it looks like there isn't anything terribly seriously left...
> I'd love to get the ball rolling on an RC so we can test it and identify
> any bugs.
>
> Thoughts?