You are viewing a plain text version of this content. The canonical link for it is here.
Posted to common-dev@hadoop.apache.org by Owen O'Malley <om...@apache.org> on 2009/07/24 22:10:33 UTC

[VOTE] Push back code freeze for 0.21

I'd like to push the date for the code freeze back to 4 September to  
give the file append more time to be finished well. Clearly, I'm +1.

-- Owen

Re: [VOTE] Push back code freeze for 0.21

Posted by Amr Awadallah <aa...@cloudera.com>.
+1 to the 3rd option.

-- amr

Konstantin Boudnik wrote:
> +1
>
> On 7/24/09 4:30 PM, Nigel Daley wrote:
>> There's a 3rd option I'd support.  Feature freeze on Sept 4, except
>> for Append which gets a 2 week extension.  This allows us to start
>> stabilizing the rest of the code base while Append is finished up.
>>
>> Nige
>>
>> On Jul 24, 2009, at 4:25 PM, Konstantin Boudnik wrote:
>>
>>> I second Konstantin's point: FI tests are likely to take a pretty
>>> hefty chunk of overall dev. time. Considering that people'd be
>>> facing a certain learning curve to master this new technology we are
>>> likely to need more time for the completion of the development of
>>> the code&  tests.
>>>
>>> +1 for farther push back, e.g. until 9/18/09
>>>
>>> Konstantin (aka Cos)
>>>
>>> On 7/24/09 4:18 PM, Konstantin Shvachko wrote:
>>>> I would like to clarify the append plans.
>>>> Right now according to our planning schedule we need about
>>>> 8 weeks to complete the implementation of the design.
>>>> This will include all the functionality and unit testing
>>>> according to the test plan.
>>>>
>>>> September 4 deadline gives us about 6 weeks to commit the features.
>>>> Which is 2 weeks short off our schedule.
>>>> This of course if the implementation will not go much faster than
>>>> we predicted :-).
>>>>
>>>> So, we can either move the freeze a couple of weeks further ahead.
>>>> Or we can also use some help from the people familiar with the
>>>> design.
>>>> E.g. there is a lot of hours scheduled to unit test writing using
>>>> fault
>>>> injection, etc.
>>>>
>>>> Thanks,
>>>> --Konstantin
>>>>
>>>> Amr Awadallah wrote:
>>>>> +1 for stable append.
>>>>>
>>>>> -- amr
>>>>>
>>>>> Dhruba Borthakur wrote:
>>>>>> +1
>>>>>>
>>>>>>
>>>>>>
>>>>>>
>>>>>>
>>>>>> On 7/24/09, Jim Kellerman
>>>>>> (POWERSET)<Ji...@microsoft.com>   wrote:
>>>>>>
>>>>>>> +1
>>>>>>>
>>>>>>>
>>>>>>>> -----Original Message-----
>>>>>>>> From: Owen O'Malley [mailto:omalley@apache.org]
>>>>>>>> Sent: Friday, July 24, 2009 1:11 PM
>>>>>>>> To: common-dev@hadoop.apache.org
>>>>>>>> Subject: [VOTE] Push back code freeze for 0.21
>>>>>>>>
>>>>>>>> I'd like to push the date for the code freeze back to 4
>>>>>>>> September to
>>>>>>>> give the file append more time to be finished well. Clearly,
>>>>>>>> I'm +1.
>>>>>>>>
>>>>>>>> -- Owen
>>>>>>>>
>>> -- 
>>> With best regards,
>>>     Konstantin Boudnik (aka Cos)
>>>
>>>         Yahoo! Grid Computing
>>>         +1 (408) 349-4049
>>>
>>> 2CAC 8312 4870 D885 8616  6115 220F 6980 1F27 E622
>>> Attention! Streams of consciousness are disallowed
>>>
>>
>

Re: [VOTE] Push back code freeze for 0.21

Posted by Konstantin Boudnik <co...@yahoo-inc.com>.
+1

On 7/24/09 4:30 PM, Nigel Daley wrote:
> There's a 3rd option I'd support.  Feature freeze on Sept 4, except
> for Append which gets a 2 week extension.  This allows us to start
> stabilizing the rest of the code base while Append is finished up.
>
> Nige
>
> On Jul 24, 2009, at 4:25 PM, Konstantin Boudnik wrote:
>
>> I second Konstantin's point: FI tests are likely to take a pretty
>> hefty chunk of overall dev. time. Considering that people'd be
>> facing a certain learning curve to master this new technology we are
>> likely to need more time for the completion of the development of
>> the code&  tests.
>>
>> +1 for farther push back, e.g. until 9/18/09
>>
>> Konstantin (aka Cos)
>>
>> On 7/24/09 4:18 PM, Konstantin Shvachko wrote:
>>> I would like to clarify the append plans.
>>> Right now according to our planning schedule we need about
>>> 8 weeks to complete the implementation of the design.
>>> This will include all the functionality and unit testing
>>> according to the test plan.
>>>
>>> September 4 deadline gives us about 6 weeks to commit the features.
>>> Which is 2 weeks short off our schedule.
>>> This of course if the implementation will not go much faster than
>>> we predicted :-).
>>>
>>> So, we can either move the freeze a couple of weeks further ahead.
>>> Or we can also use some help from the people familiar with the
>>> design.
>>> E.g. there is a lot of hours scheduled to unit test writing using
>>> fault
>>> injection, etc.
>>>
>>> Thanks,
>>> --Konstantin
>>>
>>> Amr Awadallah wrote:
>>>> +1 for stable append.
>>>>
>>>> -- amr
>>>>
>>>> Dhruba Borthakur wrote:
>>>>> +1
>>>>>
>>>>>
>>>>>
>>>>>
>>>>>
>>>>> On 7/24/09, Jim Kellerman
>>>>> (POWERSET)<Ji...@microsoft.com>   wrote:
>>>>>
>>>>>> +1
>>>>>>
>>>>>>
>>>>>>> -----Original Message-----
>>>>>>> From: Owen O'Malley [mailto:omalley@apache.org]
>>>>>>> Sent: Friday, July 24, 2009 1:11 PM
>>>>>>> To: common-dev@hadoop.apache.org
>>>>>>> Subject: [VOTE] Push back code freeze for 0.21
>>>>>>>
>>>>>>> I'd like to push the date for the code freeze back to 4
>>>>>>> September to
>>>>>>> give the file append more time to be finished well. Clearly,
>>>>>>> I'm +1.
>>>>>>>
>>>>>>> -- Owen
>>>>>>>
>> --
>> With best regards,
>> 	Konstantin Boudnik (aka Cos)
>>
>>         Yahoo! Grid Computing
>>         +1 (408) 349-4049
>>
>> 2CAC 8312 4870 D885 8616  6115 220F 6980 1F27 E622
>> Attention! Streams of consciousness are disallowed
>>
>

-- 
With best regards,
	Konstantin Boudnik (aka Cos)

         Yahoo! Grid Computing
         +1 (408) 349-4049

2CAC 8312 4870 D885 8616  6115 220F 6980 1F27 E622
Attention! Streams of consciousness are disallowed


Re: [VOTE] Push back code freeze for 0.21

Posted by Mathias Herberts <ma...@gmail.com>.
+1

On Jul 25, 2009 1:31 AM, "Nigel Daley" <nd...@yahoo-inc.com> wrote:

There's a 3rd option I'd support.  Feature freeze on Sept 4, except for
Append which gets a 2 week extension.  This allows us to start stabilizing
the rest of the code base while Append is finished up.

Nige

On Jul 24, 2009, at 4:25 PM, Konstantin Boudnik wrote: > I second
Konstantin's point: FI tests ar...

RE: [VOTE] Push back code freeze for 0.21

Posted by "Jim Kellerman (POWERSET)" <Ji...@microsoft.com>.
+1

---
Jim Kellerman, Powerset (Live Search, Microsoft Corporation)


> -----Original Message-----
> From: Nigel Daley [mailto:ndaley@yahoo-inc.com]
> Sent: Friday, July 24, 2009 4:31 PM
> To: common-dev@hadoop.apache.org
> Subject: Re: [VOTE] Push back code freeze for 0.21
>
> There's a 3rd option I'd support.  Feature freeze on Sept 4, except
> for Append which gets a 2 week extension.  This allows us to start
> stabilizing the rest of the code base while Append is finished up.
>
> Nige
>
> On Jul 24, 2009, at 4:25 PM, Konstantin Boudnik wrote:
>
> > I second Konstantin's point: FI tests are likely to take a pretty
> > hefty chunk of overall dev. time. Considering that people'd be
> > facing a certain learning curve to master this new technology we
> are
> > likely to need more time for the completion of the development of
> > the code & tests.
> >
> > +1 for farther push back, e.g. until 9/18/09
> >
> > Konstantin (aka Cos)
> >
> > On 7/24/09 4:18 PM, Konstantin Shvachko wrote:
> >> I would like to clarify the append plans.
> >> Right now according to our planning schedule we need about
> >> 8 weeks to complete the implementation of the design.
> >> This will include all the functionality and unit testing
> >> according to the test plan.
> >>
> >> September 4 deadline gives us about 6 weeks to commit the
> features.
> >> Which is 2 weeks short off our schedule.
> >> This of course if the implementation will not go much faster than
> >> we predicted :-).
> >>
> >> So, we can either move the freeze a couple of weeks further
> ahead.
> >> Or we can also use some help from the people familiar with the
> >> design.
> >> E.g. there is a lot of hours scheduled to unit test writing using
> >> fault
> >> injection, etc.
> >>
> >> Thanks,
> >> --Konstantin
> >>
> >> Amr Awadallah wrote:
> >>> +1 for stable append.
> >>>
> >>> -- amr
> >>>
> >>> Dhruba Borthakur wrote:
> >>>> +1
> >>>>
> >>>>
> >>>>
> >>>>
> >>>>
> >>>> On 7/24/09, Jim Kellerman
> >>>> (POWERSET)<Ji...@microsoft.com>  wrote:
> >>>>
> >>>>> +1
> >>>>>
> >>>>>
> >>>>>> -----Original Message-----
> >>>>>> From: Owen O'Malley [mailto:omalley@apache.org]
> >>>>>> Sent: Friday, July 24, 2009 1:11 PM
> >>>>>> To: common-dev@hadoop.apache.org
> >>>>>> Subject: [VOTE] Push back code freeze for 0.21
> >>>>>>
> >>>>>> I'd like to push the date for the code freeze back to 4
> >>>>>> September to
> >>>>>> give the file append more time to be finished well. Clearly,
> >>>>>> I'm +1.
> >>>>>>
> >>>>>> -- Owen
> >>>>>>
> >>>>>
> >>>>
> >
> > --
> > With best regards,
> >       Konstantin Boudnik (aka Cos)
> >
> >        Yahoo! Grid Computing
> >        +1 (408) 349-4049
> >
> > 2CAC 8312 4870 D885 8616  6115 220F 6980 1F27 E622
> > Attention! Streams of consciousness are disallowed
> >
>


Re: [VOTE] Push back code freeze for 0.21

Posted by Nigel Daley <nd...@yahoo-inc.com>.
There's a 3rd option I'd support.  Feature freeze on Sept 4, except  
for Append which gets a 2 week extension.  This allows us to start  
stabilizing the rest of the code base while Append is finished up.

Nige

On Jul 24, 2009, at 4:25 PM, Konstantin Boudnik wrote:

> I second Konstantin's point: FI tests are likely to take a pretty  
> hefty chunk of overall dev. time. Considering that people'd be  
> facing a certain learning curve to master this new technology we are  
> likely to need more time for the completion of the development of  
> the code & tests.
>
> +1 for farther push back, e.g. until 9/18/09
>
> Konstantin (aka Cos)
>
> On 7/24/09 4:18 PM, Konstantin Shvachko wrote:
>> I would like to clarify the append plans.
>> Right now according to our planning schedule we need about
>> 8 weeks to complete the implementation of the design.
>> This will include all the functionality and unit testing
>> according to the test plan.
>>
>> September 4 deadline gives us about 6 weeks to commit the features.
>> Which is 2 weeks short off our schedule.
>> This of course if the implementation will not go much faster than  
>> we predicted :-).
>>
>> So, we can either move the freeze a couple of weeks further ahead.
>> Or we can also use some help from the people familiar with the  
>> design.
>> E.g. there is a lot of hours scheduled to unit test writing using  
>> fault
>> injection, etc.
>>
>> Thanks,
>> --Konstantin
>>
>> Amr Awadallah wrote:
>>> +1 for stable append.
>>>
>>> -- amr
>>>
>>> Dhruba Borthakur wrote:
>>>> +1
>>>>
>>>>
>>>>
>>>>
>>>>
>>>> On 7/24/09, Jim Kellerman  
>>>> (POWERSET)<Ji...@microsoft.com>  wrote:
>>>>
>>>>> +1
>>>>>
>>>>>
>>>>>> -----Original Message-----
>>>>>> From: Owen O'Malley [mailto:omalley@apache.org]
>>>>>> Sent: Friday, July 24, 2009 1:11 PM
>>>>>> To: common-dev@hadoop.apache.org
>>>>>> Subject: [VOTE] Push back code freeze for 0.21
>>>>>>
>>>>>> I'd like to push the date for the code freeze back to 4  
>>>>>> September to
>>>>>> give the file append more time to be finished well. Clearly,  
>>>>>> I'm +1.
>>>>>>
>>>>>> -- Owen
>>>>>>
>>>>>
>>>>
>
> -- 
> With best regards,
> 	Konstantin Boudnik (aka Cos)
>
>        Yahoo! Grid Computing
>        +1 (408) 349-4049
>
> 2CAC 8312 4870 D885 8616  6115 220F 6980 1F27 E622
> Attention! Streams of consciousness are disallowed
>


Re: [VOTE] Push back code freeze for 0.21

Posted by Konstantin Boudnik <co...@yahoo-inc.com>.
I second Konstantin's point: FI tests are likely to take a pretty hefty chunk of 
overall dev. time. Considering that people'd be facing a certain learning curve 
to master this new technology we are likely to need more time for the completion 
of the development of the code & tests.

+1 for farther push back, e.g. until 9/18/09

Konstantin (aka Cos)

On 7/24/09 4:18 PM, Konstantin Shvachko wrote:
> I would like to clarify the append plans.
> Right now according to our planning schedule we need about
> 8 weeks to complete the implementation of the design.
> This will include all the functionality and unit testing
> according to the test plan.
>
> September 4 deadline gives us about 6 weeks to commit the features.
> Which is 2 weeks short off our schedule.
> This of course if the implementation will not go much faster than we predicted :-).
>
> So, we can either move the freeze a couple of weeks further ahead.
> Or we can also use some help from the people familiar with the design.
> E.g. there is a lot of hours scheduled to unit test writing using fault
> injection, etc.
>
> Thanks,
> --Konstantin
>
> Amr Awadallah wrote:
>> +1 for stable append.
>>
>> -- amr
>>
>> Dhruba Borthakur wrote:
>>> +1
>>>
>>>
>>>
>>>
>>>
>>> On 7/24/09, Jim Kellerman (POWERSET)<Ji...@microsoft.com>  wrote:
>>>
>>>> +1
>>>>
>>>>
>>>>> -----Original Message-----
>>>>> From: Owen O'Malley [mailto:omalley@apache.org]
>>>>> Sent: Friday, July 24, 2009 1:11 PM
>>>>> To: common-dev@hadoop.apache.org
>>>>> Subject: [VOTE] Push back code freeze for 0.21
>>>>>
>>>>> I'd like to push the date for the code freeze back to 4 September to
>>>>> give the file append more time to be finished well. Clearly, I'm +1.
>>>>>
>>>>> -- Owen
>>>>>
>>>>
>>>

-- 
With best regards,
	Konstantin Boudnik (aka Cos)

         Yahoo! Grid Computing
         +1 (408) 349-4049

2CAC 8312 4870 D885 8616  6115 220F 6980 1F27 E622
Attention! Streams of consciousness are disallowed


Re: [VOTE] Push back code freeze for 0.21

Posted by Konstantin Shvachko <sh...@yahoo-inc.com>.
I would like to clarify the append plans.
Right now according to our planning schedule we need about
8 weeks to complete the implementation of the design.
This will include all the functionality and unit testing
according to the test plan.

September 4 deadline gives us about 6 weeks to commit the features.
Which is 2 weeks short off our schedule.
This of course if the implementation will not go much faster than we predicted :-).

So, we can either move the freeze a couple of weeks further ahead.
Or we can also use some help from the people familiar with the design.
E.g. there is a lot of hours scheduled to unit test writing using fault
injection, etc.

Thanks,
--Konstantin

Amr Awadallah wrote:
> +1 for stable append.
> 
> -- amr
> 
> Dhruba Borthakur wrote:
>> +1
>>
>>
>>
>>
>>
>> On 7/24/09, Jim Kellerman (POWERSET) <Ji...@microsoft.com> wrote:
>>  
>>> +1
>>>
>>>    
>>>> -----Original Message-----
>>>> From: Owen O'Malley [mailto:omalley@apache.org]
>>>> Sent: Friday, July 24, 2009 1:11 PM
>>>> To: common-dev@hadoop.apache.org
>>>> Subject: [VOTE] Push back code freeze for 0.21
>>>>
>>>> I'd like to push the date for the code freeze back to 4 September to
>>>> give the file append more time to be finished well. Clearly, I'm +1.
>>>>
>>>> -- Owen
>>>>       
>>>     
>>
>>   
> 

Re: [VOTE] Push back code freeze for 0.21

Posted by Amr Awadallah <aa...@cloudera.com>.
+1 for stable append.

-- amr

Dhruba Borthakur wrote:
> +1
>
>
>
>
>
> On 7/24/09, Jim Kellerman (POWERSET) <Ji...@microsoft.com> wrote:
>   
>> +1
>>
>>     
>>> -----Original Message-----
>>> From: Owen O'Malley [mailto:omalley@apache.org]
>>> Sent: Friday, July 24, 2009 1:11 PM
>>> To: common-dev@hadoop.apache.org
>>> Subject: [VOTE] Push back code freeze for 0.21
>>>
>>> I'd like to push the date for the code freeze back to 4 September to
>>> give the file append more time to be finished well. Clearly, I'm +1.
>>>
>>> -- Owen
>>>       
>>     
>
>   

Re: [VOTE] Push back code freeze for 0.21

Posted by Dhruba Borthakur <dh...@gmail.com>.
+1





On 7/24/09, Jim Kellerman (POWERSET) <Ji...@microsoft.com> wrote:
> +1
>
>> -----Original Message-----
>> From: Owen O'Malley [mailto:omalley@apache.org]
>> Sent: Friday, July 24, 2009 1:11 PM
>> To: common-dev@hadoop.apache.org
>> Subject: [VOTE] Push back code freeze for 0.21
>>
>> I'd like to push the date for the code freeze back to 4 September to
>> give the file append more time to be finished well. Clearly, I'm +1.
>>
>> -- Owen
>
>

-- 
Sent from Gmail for mobile | mobile.google.com

RE: [VOTE] Push back code freeze for 0.21

Posted by "Jim Kellerman (POWERSET)" <Ji...@microsoft.com>.
+1

> -----Original Message-----
> From: Owen O'Malley [mailto:omalley@apache.org]
> Sent: Friday, July 24, 2009 1:11 PM
> To: common-dev@hadoop.apache.org
> Subject: [VOTE] Push back code freeze for 0.21
>
> I'd like to push the date for the code freeze back to 4 September to
> give the file append more time to be finished well. Clearly, I'm +1.
>
> -- Owen


Re: [VOTE] Push back code freeze for 0.21

Posted by Philip Zeyliger <ph...@cloudera.com>.
+1

On Fri, Jul 24, 2009 at 1:57 PM, Arun C Murthy <ac...@yahoo-inc.com> wrote:

> +1
>
> Arun
>
> On Jul 24, 2009, at 1:10 PM, Owen O'Malley wrote:
>
>  I'd like to push the date for the code freeze back to 4 September to give
>> the file append more time to be finished well. Clearly, I'm +1.
>>
>> -- Owen
>>
>
>

Re: [VOTE] Push back code freeze for 0.21

Posted by Arun C Murthy <ac...@yahoo-inc.com>.
+1

Arun

On Jul 24, 2009, at 1:10 PM, Owen O'Malley wrote:

> I'd like to push the date for the code freeze back to 4 September to  
> give the file append more time to be finished well. Clearly, I'm +1.
>
> -- Owen


Re: [VOTE] Push back code freeze for 0.21

Posted by Todd Lipcon <to...@cloudera.com>.
+1 - having good stable append is crucial before we start working on 0.22
imo

-Todd

On Fri, Jul 24, 2009 at 1:15 PM, Matei Zaharia <ma...@eecs.berkeley.edu>wrote:

> +1
>
> Matei
>
>
> On Jul 24, 2009, at 1:10 PM, Owen O'Malley wrote:
>
>  I'd like to push the date for the code freeze back to 4 September to give
>> the file append more time to be finished well. Clearly, I'm +1.
>>
>> -- Owen
>>
>
>

Re: [VOTE] Push back code freeze for 0.21

Posted by Matei Zaharia <ma...@eecs.berkeley.edu>.
+1

Matei

On Jul 24, 2009, at 1:10 PM, Owen O'Malley wrote:

> I'd like to push the date for the code freeze back to 4 September to  
> give the file append more time to be finished well. Clearly, I'm +1.
>
> -- Owen


Re: [VOTE] Push back code freeze for 0.21

Posted by Hairong Kuang <ha...@yahoo-inc.com>.
+1.

Hairong


On 7/24/09 1:10 PM, "Owen O'Malley" <om...@apache.org> wrote:

> I'd like to push the date for the code freeze back to 4 September to
> give the file append more time to be finished well. Clearly, I'm +1.
> 
> -- Owen