Re: requirements

Hi Eric,

If you did not do yet I'd highly recommend to read Sharan's book

Jacques

Le 27/10/2014 06:04, Swapnil Shah a écrit :
> Essentially MRP need to take into account multiple factors into consideration while generating net requirement for any given part/product. The existing version of MRP algorithm is primarily meant to create the requirement plan (WHEN and HOW MUCH would be the required) for all parts in any standard manufacturing supply chain setup.
>
>   
>
> Parts at finished good (or any intermediate) level may or may not have the associated upstream Operation and Bill of Material (BoM) in the system. Two kinds of requirements are generated to fulfil the demand arisen out of existing Sales (Sales Orders and Sales Forecast) and Safety Stock requirement for that part.
>
>   
>
> One is Product Requirement that needs to be procured (i.e there is no upstream BoM set for these parts). Second, is Internal Requirement that needs to produced internally (i.e there are BoM associated to the given part and hence at component level the requirements are generated to fulfil the derived demand coming from downstream levels (i.e, to produce the downstream material so as to fulfil finished good's demand) and Safety Stock requirement for that part.
>
>   
>
> At very high level it should be based roughly on following formulation:
>
> *         Required Qty (at FG level) = Max (SalesDemand,ROQ) + MinimumStock (ROP) - QOH - ∑ On Order (Approved PO,Requirements and/or Incoming Production Runs)
>
> *         Required Qty (at BoM component or Intermediate level) = Max ((Sales Demand + Outgoing Production Runs),ROQ) + MinimumStock (ROP) - QOH - ∑ On Order (Approved PO and/or Incoming Production Runs)
>
>   
>
> The Product requirements furnished out of MRP (or outside of MRP flow) should be first approved and then can be converted to Purchase Order to given supplier for any part. Whereas the Internal Requirements can be approved and converted to Production Run for any given part. I hope it helps in answering some of the raised concerns.
>
>   
>
> Thanks & Regards,
>
> Swapnil Shah
>
>   
>
> |-----Original Message-----
>
> |From: Heidi Dehaes [mailto:info.olagos@gmail.com]
>
> |Sent: 17 October 2014 20:19
>
> |To: user
>
> |Subject: requirements
>
> |
>
> |Hello,
>
> |
>
> |Can someone explain to me what are the consequences of the creation of a
>
> |requirement of products after selling products for example.
>
> |(autorequirement set)
>
> |Does this already mean that automatically a purchase invoice is made for the
>
> |supplier?
>
> |
>
> |Regards,
>
> |Eric
>
> |
>
> |Olagos bvba
>
> |Heidi Dehaes
>
> |Kerkstraat 34
>
> |2570 Duffel
>
> |Belgium
>
> |Tel. :     015/31 53 04
>
> |GSM :    0485/22 35 80
>
> |E-mail :  <ma...@gmail.com> info.olagos@gmail.com
>
> | <http://www.olagos.eu> http://www.olagos.eu
>
> | <http://www.olagos.com> http://www.olagos.com
>
> | <http://www.olagos.be> http://www.olagos.be
>
> | <http://www.olagos.nl> http://www.olagos.nl
>
>

Re: requirements

Posted by Heidi Dehaes <in...@gmail.com>.
ok thank you Jacques.
ERic

Olagos bvba
Heidi Dehaes
Kerkstraat 34
2570 Duffel
Belgium
Tel. :     015/31 53 04
GSM :    0485/22 35 80
E-mail : info.olagos@gmail.com
http://www.olagos.eu
http://www.olagos.com
http://www.olagos.be
http://www.olagos.nl



2014-11-30 9:51 GMT+01:00 Jacques Le Roux <ja...@les7arts.com>:

> There is a link from https://cwiki.apache.org/confluence/display/OFBADMIN/
> OFBiz+Related+Books
>
> Jacques
>
> Le 29/11/2014 17:06, Heidi Dehaes a écrit :
>
>  Hello Sharan , Pierre,
>>
>> Thanks for your clear information and yes, i will buy your book. Just
>> don't
>> know at the moment where to buy it.
>>
>> Eric
>>
>> Olagos bvba
>> Heidi Dehaes
>> Kerkstraat 34
>> 2570 Duffel
>> Belgium
>> Tel. :     015/31 53 04
>> GSM :    0485/22 35 80
>> E-mail : info.olagos@gmail.com
>> http://www.olagos.eu
>> http://www.olagos.com
>> http://www.olagos.be
>> http://www.olagos.nl
>>
>>
>>
>> 2014-11-29 16:36 GMT+01:00 Sharan-F <sh...@gmail.com>:
>>
>>  Hi Jacques
>>>
>>> Thanks for the recommendation! Although Eric - the simple answer to your
>>> question is 'No. Creating a requirement doesnt mean that a purchase
>>> invoice
>>> automatically is made to a supplier.'
>>>
>>> A requirement is used as an indication that you need to order something
>>> from
>>> a supplier.
>>>
>>> You will still need some type of manual intervention to create the
>>> purchase
>>> order. In the case of requirement you can convert it into a purchase
>>> order
>>> using the Quick Purchase Order Entry.
>>>
>>> When you receive the goods from your supplier and receive them into
>>> OFBiz,
>>> this is generally when the purchase invoice is generated.
>>>
>>> I hope this helps.
>>>
>>> Thanks
>>> Sharan
>>>
>>>
>>>
>>>
>>>
>>>
>>>
>>>
>>> --
>>> View this message in context:
>>> http://ofbiz.135035.n4.nabble.com/requirements-tp4656888p4659211.html
>>> Sent from the OFBiz - User mailing list archive at Nabble.com.
>>>
>>>

Re: requirements

Posted by Jacques Le Roux <ja...@les7arts.com>.
There is a link from https://cwiki.apache.org/confluence/display/OFBADMIN/OFBiz+Related+Books

Jacques

Le 29/11/2014 17:06, Heidi Dehaes a écrit :
> Hello Sharan , Pierre,
>
> Thanks for your clear information and yes, i will buy your book. Just don't
> know at the moment where to buy it.
>
> Eric
>
> Olagos bvba
> Heidi Dehaes
> Kerkstraat 34
> 2570 Duffel
> Belgium
> Tel. :     015/31 53 04
> GSM :    0485/22 35 80
> E-mail : info.olagos@gmail.com
> http://www.olagos.eu
> http://www.olagos.com
> http://www.olagos.be
> http://www.olagos.nl
>
>
>
> 2014-11-29 16:36 GMT+01:00 Sharan-F <sh...@gmail.com>:
>
>> Hi Jacques
>>
>> Thanks for the recommendation! Although Eric - the simple answer to your
>> question is 'No. Creating a requirement doesnt mean that a purchase invoice
>> automatically is made to a supplier.'
>>
>> A requirement is used as an indication that you need to order something
>> from
>> a supplier.
>>
>> You will still need some type of manual intervention to create the purchase
>> order. In the case of requirement you can convert it into a purchase order
>> using the Quick Purchase Order Entry.
>>
>> When you receive the goods from your supplier and receive them into OFBiz,
>> this is generally when the purchase invoice is generated.
>>
>> I hope this helps.
>>
>> Thanks
>> Sharan
>>
>>
>>
>>
>>
>>
>>
>>
>> --
>> View this message in context:
>> http://ofbiz.135035.n4.nabble.com/requirements-tp4656888p4659211.html
>> Sent from the OFBiz - User mailing list archive at Nabble.com.
>>

Re: requirements

Posted by Heidi Dehaes <in...@gmail.com>.
Hello Sharan , Pierre,

Thanks for your clear information and yes, i will buy your book. Just don't
know at the moment where to buy it.

Eric

Olagos bvba
Heidi Dehaes
Kerkstraat 34
2570 Duffel
Belgium
Tel. :     015/31 53 04
GSM :    0485/22 35 80
E-mail : info.olagos@gmail.com
http://www.olagos.eu
http://www.olagos.com
http://www.olagos.be
http://www.olagos.nl



2014-11-29 16:36 GMT+01:00 Sharan-F <sh...@gmail.com>:

> Hi Jacques
>
> Thanks for the recommendation! Although Eric - the simple answer to your
> question is 'No. Creating a requirement doesnt mean that a purchase invoice
> automatically is made to a supplier.'
>
> A requirement is used as an indication that you need to order something
> from
> a supplier.
>
> You will still need some type of manual intervention to create the purchase
> order. In the case of requirement you can convert it into a purchase order
> using the Quick Purchase Order Entry.
>
> When you receive the goods from your supplier and receive them into OFBiz,
> this is generally when the purchase invoice is generated.
>
> I hope this helps.
>
> Thanks
> Sharan
>
>
>
>
>
>
>
>
> --
> View this message in context:
> http://ofbiz.135035.n4.nabble.com/requirements-tp4656888p4659211.html
> Sent from the OFBiz - User mailing list archive at Nabble.com.
>

Re: requirements

Posted by Sharan-F <sh...@gmail.com>.
Hi Jacques

Thanks for the recommendation! Although Eric - the simple answer to your
question is 'No. Creating a requirement doesnt mean that a purchase invoice
automatically is made to a supplier.'

A requirement is used as an indication that you need to order something from
a supplier.

You will still need some type of manual intervention to create the purchase
order. In the case of requirement you can convert it into a purchase order
using the Quick Purchase Order Entry.

When you receive the goods from your supplier and receive them into OFBiz,
this is generally when the purchase invoice is generated.

I hope this helps.

Thanks
Sharan








--