Posted to dev@openoffice.apache.org by "Dennis E. Hamilton" <or...@apache.org> on 2012/09/25 21:20:41 UTC
[DISCUSS][PMC] Proposed Initial PMC List and process
My recommendation:
48-hour steps are too short. Take at least 72 minimums, state fixed UTC earliest-end date-times (so no one has to figure out when "from now" is), and maybe skip over weekend days.
There's no rush.
- Dennis
-----Original Message-----
From: Andrew Rist [mailto:andrew.rist@oracle.com]
Sent: Tuesday, September 25, 2012 11:36
To: ooo-dev
Subject: [PMC] Proposed Initial PMC List and process
[ ... ]
Proposed Process:
* 48 hour window to build consensus on this process moving forward
(Tues-Wed)
* 48 hour (+48 hour weekend) discussion period (Thurs-Fri + Sat Sun) -
stabilization of the finalized Initial PMC List
* 72 hour vote on the resulting list as the initial PMC list (ending
next Wed.)
[ ... ]
Re: [DISCUSS][PMC] Proposed Initial PMC List and process
Posted by Peter Junge <pe...@gmx.org>.
On 9/26/2012 3:20 AM, Dennis E. Hamilton wrote:
> My recommendation:
>
> 48-hour steps are too short. Take at least 72 minimums, state fixed UTC earliest-end date-times (so no one has to figure out when "from now" is), and maybe skip over weekend days.
>
> There's no rush.
+1
>
> - Dennis
>
> -----Original Message-----
> From: Andrew Rist [mailto:andrew.rist@oracle.com]
> Sent: Tuesday, September 25, 2012 11:36
> To: ooo-dev
> Subject: [PMC] Proposed Initial PMC List and process
>
> [ ... ]
>
> Proposed Process:
>
> * 48 hour window to build consensus on this process moving forward
> (Tues-Wed)
> * 48 hour (+48 hour weekend) discussion period (Thurs-Fri + Sat Sun) -
> stabilization of the finalized Initial PMC List
> * 72 hour vote on the resulting list as the initial PMC list (ending
> next Wed.)
>
> [ ... ]
>
>