Posted to dev@airavata.apache.org by Bibrak Qamar <bi...@gmail.com> on 2019/06/27 19:53:21 UTC

Comments on Scheduler for Airavata

Hi all,

I have been working with Dimuthu on a Meta-Scheduler for Airavata. And
until now I have sketched out a few things that I wanted to share with the
broader community and get some feedback.

As you know that Apache Airavata currently does not have a scheduler that
intelligently schedules jobs before submitting to compute resources
(clusters).

In this context there are a few main functionalities that can be provided:

(1) throttling jobs before submitting to compute resources,
(2) be aware of the load on various clusters and intelligently
dispatch series of user jobs to multiple clusters thereby
increasing throughput and
(3) making it easy and fair for multiple users to use a single
community account.

To achieve (1) and (3) I think we need to have two limits on users. One is
number of jobs that they can submit that are in the queue and the other
limit is on the number of jobs that the Airavata Scheduler allows to go to
execution (i.e. they are dispatched to physical cluster).

To achieve (2) I have read a bit on literature about batch job scheduling
on clusters. Following are ways that guide scheduling policies:


   -

   FCFS (First come first serve)

   -

   SJF (Shortest job first)

   -

   LJF(Longest job first)

   -

   Advance reservation  —> can we do this? Since at the physical
machine level it will also have its own scheduler?

   -

   Backfilling*

   -

   Preemptive backfilling —> let high priority jobs be given
precedence over lower



*Backfill: Each job has a start time as well as a wall clock limit.
Therefore, finish time can be found for all the jobs that are in the queue
along with the earliest time the resources are going to be free in order to
start the high priority jobs. Backfill uses this knowledge to give
resources to jobs that can complete in between the waiting and makes the
most out of the available resources.

I think, with the Airavata Meta-Scheduler, we have a unique challenge that
is not present in schedulers for clusters. It is that the Meta-Scheduler
for Airavata is going to piggyback on the scheduler of the physical
cluster. In that case we don't have control over the scheduling since the
cluster will have its own policies and therefore we cannot guarantee good
accuracy in terms of when our jobs finish (or when do they really start to
begin with). So, how aggressively should we do scheduling? Is it worth it
to be more aggressive?

Also I anticipate following four statuses a Job cab be in:

1 - Airavata Queue
2 - Cluster Queue
3 - Executing
4 - Stopped


To get started and write the scheduler I have written a little cluster
simulator. It takes in jobs and puts them in queue and later based on FCFS
basis executes them. This infrastructure will later be used to develop the
meta-scheduler for airavata by plugging in the meta-scheduler between
loadGenerator and clusterSimulator. Once the meta-scheduler is perfected we
then integrate it into airavata repository.

The code base is sent as a pull request to airavata-sandbox repo:
https://github.com/apache/airavata-sandbox/pull/40

Looking forward to your feedback!

Bibrak Qamar