Posted to yarn-issues@hadoop.apache.org by "Daniel Templeton (JIRA)" <ji...@apache.org> on 2016/07/13 22:05:20 UTC

[jira] [Commented] (YARN-4464) default value of yarn.resourcemanager.state-store.max-completed-applications should lower.

    [ https://issues.apache.org/jira/browse/YARN-4464?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=15375862#comment-15375862 ] 

Daniel Templeton commented on YARN-4464:
----------------------------------------

With ATS, I don't see a lot of need to keep 10k completed apps lying about. Not only is it a startup burden, but it also is a ZK burden.  We regularly tell customers to set it lower because of ZK cache load.  Improving the recovery logic is something we should also do, but the best doesn't need to be the enemy of the good.  [~vinodkv], [~Naganarasimha], [~kasha], can we come to a conclusion?

> default value of yarn.resourcemanager.state-store.max-completed-applications should lower.
> ------------------------------------------------------------------------------------------
>
>                 Key: YARN-4464
>                 URL: https://issues.apache.org/jira/browse/YARN-4464
>             Project: Hadoop YARN
>          Issue Type: Wish
>          Components: resourcemanager
>            Reporter: KWON BYUNGCHANG
>            Assignee: Daniel Templeton
>            Priority: Blocker
>         Attachments: YARN-4464.001.patch, YARN-4464.002.patch, YARN-4464.003.patch, YARN-4464.004.patch
>
>
> my cluster has 120 nodes.
> I configured RM Restart feature.
> {code}
> yarn.resourcemanager.recovery.enabled=true
> yarn.resourcemanager.store.class=org.apache.hadoop.yarn.server.resourcemanager.recovery.FileSystemRMStateStore
> yarn.resourcemanager.fs.state-store.uri=/system/yarn/rmstore
> {code}
> unfortunately I did not configure {{yarn.resourcemanager.state-store.max-completed-applications}}.
> so that property configured default value 10,000.
> I have restarted RM due to changing another configuartion.
> I expected that RM restart immediately.
> recovery process was very slow.  I have waited about 20min.  
> realize missing {{yarn.resourcemanager.state-store.max-completed-applications}}.
> its default value is very huge.  
> need to change lower value or document notice on [RM Restart page|http://hadoop.apache.org/docs/stable/hadoop-yarn/hadoop-yarn-site/ResourceManagerRestart.html].



--
This message was sent by Atlassian JIRA
(v6.3.4#6332)

---------------------------------------------------------------------
To unsubscribe, e-mail: yarn-issues-unsubscribe@hadoop.apache.org