You are viewing a plain text version of this content. The canonical link for it is here.
Posted to yarn-issues@hadoop.apache.org by "Eric Payne (Jira)" <ji...@apache.org> on 2021/10/04 20:08:00 UTC

[jira] [Reopened] (YARN-8127) Resource leak when async scheduling is enabled

     [ https://issues.apache.org/jira/browse/YARN-8127?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]

Eric Payne reopened YARN-8127:
------------------------------

Attched branch-2.10 patch. Reopening and putting in PATCH AVAILABLE state to kick the prec-mmit build.
The backport is clean except for a couple of minor unit test changes.
If all goes well, I will cherry-pick back to 2.10 and fixup the unit test there.

> Resource leak when async scheduling is enabled
> ----------------------------------------------
>
>                 Key: YARN-8127
>                 URL: https://issues.apache.org/jira/browse/YARN-8127
>             Project: Hadoop YARN
>          Issue Type: Bug
>            Reporter: Weiwei Yang
>            Assignee: Tao Yang
>            Priority: Critical
>             Fix For: 3.2.0, 3.1.1
>
>         Attachments: YARN-8127.001.patch, YARN-8127.002.patch, YARN-8127.003.patch, YARN-8127.004.patch, YARN-8127.branch-2.10.004.patch
>
>
> Brief steps to reproduce
>  # Enable async scheduling, 5 threads
>  # Submit a lot of jobs trying to exhaust cluster resource
>  # After a while, observed NM allocatedĀ resourceĀ is more than resource requested by allocated containers
> Looks like the commit phase is not sync handling reserved containers, causing some proposal incorrectly accepted, subsequently resource was deducted multiple times for a container.



--
This message was sent by Atlassian Jira
(v8.3.4#803005)

---------------------------------------------------------------------
To unsubscribe, e-mail: yarn-issues-unsubscribe@hadoop.apache.org