Specify dates instead of revisions?

I seem to remember some discussion a while back about taking dates as revision 
parameters instead of actual rev numbers, but I don't remember what the 
conclusion was. Dates don't seem work in 0.15; does that mean this feature 
has been dropped? tigris.org's mail list archive search is clunky and didn't 
help me find much.

Anyway, I'm curious because I'd like to put up a couple web pages with 
information about some projects I'm working on. I'd like them to show commits 
for the past day/week/month/etc, something like this (URL wrap alert):

http://bonsai.mozilla.org/cvsquery.cgi?treeid=default&module=Chimera&branch=CHIMERA_M1_0_1_BRANCH&branchtype=match&dir=&file=&filetype=match&who=&whotype=match&sortby=Change+Size&hours=2&date=day&mindate=&maxdate=&cvsroot=%2Fcvsroot

It'd be a lot easier to do this if I could use dates instead of having to 
parse thru the log output to grab the requested date(s).

-- 
Ben Gollmer

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@subversion.tigris.org
For additional commands, e-mail: dev-help@subversion.tigris.org

Re: Specify dates instead of revisions?

Posted by Ben Gollmer <be...@jatosoft.com>.
On Saturday 23 November 2002 13:19, Greg Hudson wrote:
> On Sat, 2002-11-23 at 07:12, Nuutti Kotivuori wrote:
> >   svn log -r "{2002-11-20}:{2002-11-21}" http://svn.collab.net/repos/svn
> >
> > Atleast, relatively fine.
> >
> > It would seem there's a slight "bug" here. It shows me one entry
> > before the start time.
>
> This is consistent with our rules:
>
> "{DATE}", as a revision, means "the most recent revision as of DATE."
>
> -r R1:R2 means "from R1 to R2 inclusive."
>
> Certainly, users might expect date ranges to operate specially ("the
> revisions between these two dates").  But that's kind of an ugly special
> case.

Thanks guys. I wasn't using the curly braces.

Maybe something should be added to the cli help? Right now (0.15) it says

-r [--revision] arg      : specify revision number ARG (or X:Y range)

-- 
Ben

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@subversion.tigris.org
For additional commands, e-mail: dev-help@subversion.tigris.org

Re: Specify dates instead of revisions?

Posted by Greg Hudson <gh...@MIT.EDU>.
On Sat, 2002-11-23 at 07:12, Nuutti Kotivuori wrote:
>   svn log -r "{2002-11-20}:{2002-11-21}" http://svn.collab.net/repos/svn
> 
> Atleast, relatively fine.
> 
> It would seem there's a slight "bug" here. It shows me one entry
> before the start time.

This is consistent with our rules:

"{DATE}", as a revision, means "the most recent revision as of DATE."

-r R1:R2 means "from R1 to R2 inclusive."

Certainly, users might expect date ranges to operate specially ("the
revisions between these two dates").  But that's kind of an ugly special
case.


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@subversion.tigris.org
For additional commands, e-mail: dev-help@subversion.tigris.org

Re: Specify dates instead of revisions?

Posted by Nuutti Kotivuori <na...@iki.fi>.
Ben Gollmer wrote:
> I seem to remember some discussion a while back about taking dates
> as revision parameters instead of actual rev numbers, but I don't
> remember what the conclusion was. Dates don't seem work in 0.15;
> does that mean this feature has been dropped? tigris.org's mail list
> archive search is clunky and didn't help me find much.

It should work. This is 0.14.5 and this works fine:

  svn log -r "{2002-11-20}:{2002-11-21}" http://svn.collab.net/repos/svn

Atleast, relatively fine.

It would seem there's a slight "bug" here. It shows me one entry
before the start time. This is the correct behaviour when typing just
one date - such as "{2002-11-20}" to find the commit preceding that -
and it's correct behaviour for the end date - but it's not correct
behaviour for a range.

I don't know if fixing this is trivial, though.