You are viewing a plain text version of this content. The canonical link for it is here.
Posted to dev@ofbiz.apache.org by "Torstein Hegbom (JIRA)" <ji...@apache.org> on 2009/06/16 13:45:07 UTC

[jira] Commented: (OFBIZ-2615) Not possible to add resource to task in the project manager application

    [ https://issues.apache.org/jira/browse/OFBIZ-2615?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=12720078#action_12720078 ] 

Torstein Hegbom commented on OFBIZ-2615:
----------------------------------------

The steps 1 to 6 has to be done with the role: Project manager or administrator.

> Not possible to add resource to task in the project manager application
> -----------------------------------------------------------------------
>
>                 Key: OFBIZ-2615
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-2615
>             Project: OFBiz
>          Issue Type: Bug
>    Affects Versions: Release Branch 9.04
>         Environment: https://demo904.ofbiz.org/projectmgr/control/createTaskPartyAssign
>            Reporter: Torstein Hegbom
>             Fix For: Release Branch 9.04
>
>
> Not possible to add resource to task in the project manager application
> Try the following:
> 1. Enter the project manager application
> 2. Select Project in at the menu
> 3. Select the project "Demo Project1 Cust1[9000]"
> 4. Select task3 in the task-overview-window
> 5. Select Resources
> 6. Select "Analist1 Jo" add the date and press "Add"
> ----------
> The Result: 
> -----------
> The following message is shown:
> --
> The Following Errors Occurred:
> In set-nonpk-fields a value was not found with the specified valueAcsr: assignment, not setting fields
> ---
> -----------------
> Work-around
> ------------------
> Logg in as Analist1, and assign the task. That will work.

-- 
This message is automatically generated by JIRA.
-
You can reply to this email to add a comment to the issue online.