Posted to dev@santuario.apache.org by Raul Benito <ra...@apache.org> on 2006/06/14 13:41:38 UTC

Java XML Sec 1.4 release planning.

Hi Everyone,

I have commited near all changes that I want to be in for the next release
of Java XML Security.
So I'm thinking of creating several beta jar in order to increase our
population of testers...

My plan is having two beta and three release candidates, separated by one
week each.

Jun16 Fri-  1.4Beta0              (Near feature complete: I want to include
some xpath optimizations not very big)
Jun23 Fri - 1.4Beta1              (Feature complete, only fixes)
Jul2 Sun  - 1.4RC0                (From now on only bug fixes).
Jul7 Fri    - 1.4RC1
Jul14 Fri  - 1.4RC2
Jul21 Fri  - 1.4RC3-> Jul28 Fri final.

1)is it Ok this plan?
[ ]+1
[ ]  0
[ ] -1
2) I will generate a plain jar, and post the URL to the list, so people can
get it. and test with their application
Do you think it is ok?
[ ] +1
[ ]   0
[ ]  -1 (give suggestions,please...)


3)Do you miss any feature or bug fix left?
[ ] Yes (state which)
[ ] No

Please test it thoroughly. There are several changes that speed up the
things that I don't know if it can lead to problems in multithread
environments.
I have done my tests but I don't want that bugs like
http://issues.apache.org/bugzilla/show_bug.cgi?id=38605 happens again.

Regards,

Raul




-- 
http://r-bg.com

Re: Java XML Sec 1.4 release planning.

Posted by Davanum Srinivas <da...@gmail.com>.
+1 from me.

On 6/18/06, Raul Benito <ra...@apache.org> wrote:
> As no one but Sean, has vote I assume that more or less you agree with the
> planning. I include Sean sugestion. And We will have release candidate every
> two weeks(instead of every one in the previous plan).
>
> Regards
>  Raul
>
> On 6/14/06, Sean Mullan <Se...@sun.com> wrote:
> > +1 to all questions, with one concern. At least in the US, this is
> > summer vacation season, so I think we should add slightly more time in
> > the schedule to allow for sufficient testing. I would propose 2 months
> > from beta 0 to final release.
> >
> > Thanks,
> > Sean
> >
> > Raul Benito wrote:
> > > Hi Everyone,
> > >
> > > I have commited near all changes that I want to be in for the next
> > > release of Java XML Security.
> > > So I'm thinking of creating several beta jar in order to increase our
> > > population of testers...
> > >
> > > My plan is having two beta and three release candidates, separated by
> > > one week each.
> > >
> > > Jun16 Fri-  1.4Beta0              (Near feature complete: I want to
> > > include some xpath optimizations not very big)
> > > Jun23 Fri - 1.4Beta1              (Feature complete, only fixes)
> > > Jul2 Sun  - 1.4RC0                (From now on only bug fixes).
> > > Jul7 Fri    - 1.4RC1
> > > Jul14 Fri  - 1.4RC2
> > > Jul21 Fri  - 1.4RC3-> Jul28 Fri final.
> > >
> > > 1)is it Ok this plan?
> > > [ ]+1
> > > [ ]  0
> > > [ ] -1
> > > 2) I will generate a plain jar, and post the URL to the list, so people
> > > can get it. and test with their application
> > > Do you think it is ok?
> > > [ ] +1
> > > [ ]   0
> > > [ ]  -1 (give suggestions,please...)
> > >
> > >
> > > 3)Do you miss any feature or bug fix left?
> > > [ ] Yes (state which)
> > > [ ] No
> > >
> > > Please test it thoroughly. There are several changes that speed up the
> > > things that I don't know if it can lead to problems in multithread
> > > environments.
> > > I have done my tests but I don't want that bugs like
> > > http://issues.apache.org/ bugzilla/show_bug.cgi?id=38605
> > > <
> http://issues.apache.org/bugzilla/show_bug.cgi?id=38605>
> happens again.
> > >
> > > Regards,
> > >
> > > Raul
> > >
> > >
> > >
> > >
> > > --
> > > http://r-bg.com
> >
> >
>
>
>
> --
> http://r-bg.com


-- 
Davanum Srinivas : http://wso2.com/blogs/

Re: Java XML Sec 1.4 release planning.

Posted by Raul Benito <ra...@apache.org>.
As no one but Sean, has vote I assume that more or less you agree with the
planning. I include Sean sugestion. And We will have release candidate every
two weeks(instead of every one in the previous plan).

Regards
Raul

On 6/14/06, Sean Mullan <Se...@sun.com> wrote:
>
> +1 to all questions, with one concern. At least in the US, this is
> summer vacation season, so I think we should add slightly more time in
> the schedule to allow for sufficient testing. I would propose 2 months
> from beta 0 to final release.
>
> Thanks,
> Sean
>
> Raul Benito wrote:
> > Hi Everyone,
> >
> > I have commited near all changes that I want to be in for the next
> > release of Java XML Security.
> > So I'm thinking of creating several beta jar in order to increase our
> > population of testers...
> >
> > My plan is having two beta and three release candidates, separated by
> > one week each.
> >
> > Jun16 Fri-  1.4Beta0              (Near feature complete: I want to
> > include some xpath optimizations not very big)
> > Jun23 Fri - 1.4Beta1              (Feature complete, only fixes)
> > Jul2 Sun  - 1.4RC0                (From now on only bug fixes).
> > Jul7 Fri    - 1.4RC1
> > Jul14 Fri  - 1.4RC2
> > Jul21 Fri  - 1.4RC3-> Jul28 Fri final.
> >
> > 1)is it Ok this plan?
> > [ ]+1
> > [ ]  0
> > [ ] -1
> > 2) I will generate a plain jar, and post the URL to the list, so people
> > can get it. and test with their application
> > Do you think it is ok?
> > [ ] +1
> > [ ]   0
> > [ ]  -1 (give suggestions,please...)
> >
> >
> > 3)Do you miss any feature or bug fix left?
> > [ ] Yes (state which)
> > [ ] No
> >
> > Please test it thoroughly. There are several changes that speed up the
> > things that I don't know if it can lead to problems in multithread
> > environments.
> > I have done my tests but I don't want that bugs like
> > http://issues.apache.org/ bugzilla/show_bug.cgi?id=38605
> > <http://issues.apache.org/bugzilla/show_bug.cgi?id=38605> happens again.
> >
> > Regards,
> >
> > Raul
> >
> >
> >
> >
> > --
> > http://r-bg.com
>
>


-- 
http://r-bg.com

Re: Java XML Sec 1.4 release planning.

Posted by Sean Mullan <Se...@Sun.COM>.
+1 to all questions, with one concern. At least in the US, this is 
summer vacation season, so I think we should add slightly more time in 
the schedule to allow for sufficient testing. I would propose 2 months 
from beta 0 to final release.

Thanks,
Sean

Raul Benito wrote:
> Hi Everyone,
> 
> I have commited near all changes that I want to be in for the next 
> release of Java XML Security.
> So I'm thinking of creating several beta jar in order to increase our 
> population of testers...
> 
> My plan is having two beta and three release candidates, separated by 
> one week each.
> 
> Jun16 Fri-  1.4Beta0              (Near feature complete: I want to 
> include some xpath optimizations not very big)
> Jun23 Fri - 1.4Beta1              (Feature complete, only fixes)
> Jul2 Sun  - 1.4RC0                (From now on only bug fixes).
> Jul7 Fri    - 1.4RC1                 
> Jul14 Fri  - 1.4RC2
> Jul21 Fri  - 1.4RC3-> Jul28 Fri final.
> 
> 1)is it Ok this plan?
> [ ]+1
> [ ]  0
> [ ] -1
> 2) I will generate a plain jar, and post the URL to the list, so people 
> can get it. and test with their application
> Do you think it is ok?
> [ ] +1
> [ ]   0
> [ ]  -1 (give suggestions,please...)
> 
> 
> 3)Do you miss any feature or bug fix left?
> [ ] Yes (state which)
> [ ] No
> 
> Please test it thoroughly. There are several changes that speed up the 
> things that I don't know if it can lead to problems in multithread 
> environments.
> I have done my tests but I don't want that bugs like
> http://issues.apache.org/ bugzilla/show_bug.cgi?id=38605 
> <http://issues.apache.org/bugzilla/show_bug.cgi?id=38605> happens again.
> 
> Regards,
> 
> Raul
> 
> 
> 
> 
> -- 
> http://r-bg.com