You are viewing a plain text version of this content. The canonical link for it is here.
Posted to dev@fineract.apache.org by "Santosh Math (JIRA)" <ji...@apache.org> on 2017/01/19 09:06:26 UTC
[jira] [Comment Edited] (FINERACT-226) If the Center meeting date
is modified before submitting JLG loan application then repayment schedule
generated is not proper
[ https://issues.apache.org/jira/browse/FINERACT-226?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=15829446#comment-15829446 ]
Santosh Math edited comment on FINERACT-226 at 1/19/17 9:06 AM:
----------------------------------------------------------------
Tested it on 16.12.01.RELEASE. The issue still exists.
was (Author: santoshmath):
The issue is still open
> If the Center meeting date is modified before submitting JLG loan application then repayment schedule generated is not proper
> -----------------------------------------------------------------------------------------------------------------------------
>
> Key: FINERACT-226
> URL: https://issues.apache.org/jira/browse/FINERACT-226
> Project: Apache Fineract
> Issue Type: Bug
> Components: Loan
> Reporter: subramanyasn
> Assignee: Markus Geiss
> Labels: confirm, p2
> Attachments: Change center meeting date.png
>
>
> 1. Create a Center and attache meeting on 01 July 2016 with weekly on Friday, Click on modify meeting and change the meeting day as Wednesday.
> 2. Create a Group under that Center and Create a Client under that group.
> 3. Submit new JLG loan application for a client on 06 July 2016. with weekly loan, approve and disburse on 06 July 2016.
> 4. Click on the repayment schedule
> It is displaying first repayment entry on 08 July 2016, which was previous meeting date. It should display first repayment date as from 13 July 2016
--