Posted to dev@harmony.apache.org by Mark Hindess <ma...@googlemail.com> on 2009/08/10 21:56:13 UTC

[general] Milestone 11 proposed dates

We are due another milestone build at the end of the month.  I think we
should consider the following dates:

  Feature freeze  Fri 14th August
  Code freeze     Fri 21st August
  Publish         Fri 28th August

We should track issues that must be fixed for M11 with JIRA using the
"Fix for" field.  There are currently a few issues marked this way but
I don't think any of them are "must fix" issues.  To see what they are
visit the Harmony JIRA homepage at:

  http://issues.apache.org/jira/browse/HARMONY

and click on "5.0M11" entry in the Versions column.

How do people feel about doing milestone release of the java6 branch in
this timescale?

Regards,
 Mark.



Re: [general] Milestone 11 proposed dates

Posted by Tim Ellison <t....@gmail.com>.
Sounds good to me.  I should be back from family vacation just in time
to join in with the M11 test-fest :-)

Regards,
Tim

On 10/Aug/2009 20:56, Mark Hindess wrote:
> We are due another milestone build at the end of the month.  I think we
> should consider the following dates:
> 
>   Feature freeze  Fri 14th August
>   Code freeze     Fri 21st August
>   Publish         Fri 28th August
> 
> We should track issues that must be fixed for M11 with JIRA using the
> "Fix for" field.  There are currently a few issues marked this way but
> I don't think any of them are "must fix" issues.  To see what they are
> visit the Harmony JIRA homepage at:
> 
>   http://issues.apache.org/jira/browse/HARMONY
> 
> and click on "5.0M11" entry in the Versions column.
> 
> How do people feel about doing milestone release of the java6 branch in
> this timescale?
> 
> Regards,
>  Mark.
> 
> 
> 

Re: [general] Milestone 11 proposed dates

Posted by Sean Qiu <se...@gmail.com>.
Maybe we can schedule the Java6 branch one week or one month later
than Java5's milestone.
So we can merge the milestone to as part of Java6's updates.


Best Regards
Sean, Xiao Xia Qiu




2009/8/11 Mark Hindess <ma...@googlemail.com>:
>
> We are due another milestone build at the end of the month.  I think we
> should consider the following dates:
>
>  Feature freeze  Fri 14th August
>  Code freeze     Fri 21st August
>  Publish         Fri 28th August
>
> We should track issues that must be fixed for M11 with JIRA using the
> "Fix for" field.  There are currently a few issues marked this way but
> I don't think any of them are "must fix" issues.  To see what they are
> visit the Harmony JIRA homepage at:
>
>  http://issues.apache.org/jira/browse/HARMONY
>
> and click on "5.0M11" entry in the Versions column.
>
> How do people feel about doing milestone release of the java6 branch in
> this timescale?
>
> Regards,
>  Mark.
>
>
>

Re: [general] Milestone 11 proposed dates

Posted by Xiao-Feng Li <xi...@gmail.com>.
On Tue, Aug 11, 2009 at 3:56 AM, Mark
Hindess<ma...@googlemail.com> wrote:
>
> We are due another milestone build at the end of the month.  I think we
> should consider the following dates:
>
>  Feature freeze  Fri 14th August
>  Code freeze     Fri 21st August
>  Publish         Fri 28th August
>
> We should track issues that must be fixed for M11 with JIRA using the
> "Fix for" field.  There are currently a few issues marked this way but
> I don't think any of them are "must fix" issues.  To see what they are
> visit the Harmony JIRA homepage at:
>
>  http://issues.apache.org/jira/browse/HARMONY
>
> and click on "5.0M11" entry in the Versions column.
>
> How do people feel about doing milestone release of the java6 branch in
> this timescale?

Looking forward to seeing this.

Thanks,
xiaofeng