Scheduling
Hi,
I have a techincal question
is it ok to schedule two projects belonging to the same group and
dependencies between them in the same hour?
because I see that continuum resolves dependencies between the two
projects, if carried out by console,
is this true even when they are scheduled?
for example I have two projects A and B, with A dependent on B,
can you schedule these at the same time?
or should I say a continuum schedule A before B?
thank you very much
Maria
Re: Scheduling
Posted by Brett Porter <br...@apache.org>.
Yes, you should run them on the same schedule and let Continuum
resolve the dependencies between them.
- Brett
On 20/10/2008, at 6:03 AM, maria@funambol.com wrote:
> Hi,
> I have a techincal question
> is it ok to schedule two projects belonging to the same group and
> dependencies between them in the same hour?
> because I see that continuum resolves dependencies between the two
> projects, if carried out by console,
> is this true even when they are scheduled?
>
> for example I have two projects A and B, with A dependent on B,
> can you schedule these at the same time?
> or should I say a continuum schedule A before B?
>
>
> thank you very much