You are viewing a plain text version of this content. The canonical link for it is here.
Posted to commits@airflow.apache.org by "Isaac Steele (JIRA)" <ji...@apache.org> on 2016/07/27 19:56:20 UTC

[jira] [Created] (AIRFLOW-372) DAGs can run before start_date time

Isaac Steele created AIRFLOW-372:
------------------------------------

             Summary: DAGs can run before start_date time
                 Key: AIRFLOW-372
                 URL: https://issues.apache.org/jira/browse/AIRFLOW-372
             Project: Apache Airflow
          Issue Type: Bug
    Affects Versions: Airflow 1.7.1.2
            Reporter: Isaac Steele


If you turn off a DAG in the UI, there seemingly is no way to prevent "missed" runs to schedule after the DAG is turned back on. I thought the workaround for this, since it is not a parameterized option to prevent, would be to update the start_date in the DAG code before turning the DAG back on. This does not work, and therefore the scheduler is running dag_runs *before* the listed start_date.

To reproduce:
# Create a DAG with a schedule_interval
# Let the DAG run at least once
# Turn off the DAG in the UI
# Allow the schedule_interval to pass at least twice
# Update the start_date in the DAG to be be after the two interval time
# (I then removed the compiled python file and restarted airflow/scheduler just to make sure)
# Turn DAG back on in UI

Result: All dag_runs that were "missed" while the DAG was turned off run, despite the start_date being later.

Ideally the start_date would always be honored. And also there would be a parameter to just not run any "missed" dag_runs.
 



--