[PROPOSAL] Move out release schedule by ~1 month going forward
Hi all,
I’d like to propose that we shift all future releases forward by roughly 2 month. So, the releases would be as following (note that 5.2.0 is on the “legacy” schedule):
5.2.0 — December 2014
5.3.0 — April 2015 (this is an LTS)
6.0.0 — July 2015
6.1.0 — October 2015
6.2.0 — January 2016
6.3.0 — April 2016 (this is an LTS)
The rationale for this is basically that a release in November almost never makes sense. No one will deploy anything around Thanksgiving and/or the winter holidays. In addition, I feel these schedule fits better into how we have been scheduling ATS Summits.
Thoughts?
— Leif
RE: [PROPOSAL] Move out release schedule by ~1 month going forward
Posted by "Ross Gardler (MS OPEN TECH)" <Ro...@microsoft.com>.
Moving dev@community.apache.org to BCC so as not to create unnecessary traffic (I assume it was a mistake having it in the To line)
Microsoft Open Technologies, Inc.
A subsidiary of Microsoft Corporation
-----Original Message-----
From: Leif Hedstrom [mailto:zwoop@apache.org]
Sent: Monday, December 1, 2014 8:58 AM
To: dev@community.apache.org; users@trafficserver.apache.org
Subject: [PROPOSAL] Move out release schedule by ~1 month going forward
Hi all,
I’d like to propose that we shift all future releases forward by roughly 2 month. So, the releases would be as following (note that 5.2.0 is on the “legacy” schedule):
5.2.0 — December 2014
5.3.0 — April 2015 (this is an LTS)
6.0.0 — July 2015
6.1.0 — October 2015
6.2.0 — January 2016
6.3.0 — April 2016 (this is an LTS)
The rationale for this is basically that a release in November almost never makes sense. No one will deploy anything around Thanksgiving and/or the winter holidays. In addition, I feel these schedule fits better into how we have been scheduling ATS Summits.
Thoughts?
— Leif
Re: [PROPOSAL] Move out release schedule by ~1 month going forward
Posted by Leif Hedstrom <zw...@apache.org>.
> On Dec 1, 2014, at 9:57 AM, Leif Hedstrom <zw...@apache.org> wrote:
>
> Hi all,
Sorry about that, mail fails me again …
— leif
RE: [PROPOSAL] Move out release schedule by ~1 month going forward
Posted by "Ross Gardler (MS OPEN TECH)" <Ro...@microsoft.com>.
Moving dev@community.apache.org to BCC so as not to create unnecessary traffic (I assume it was a mistake having it in the To line)
Microsoft Open Technologies, Inc.
A subsidiary of Microsoft Corporation
-----Original Message-----
From: Leif Hedstrom [mailto:zwoop@apache.org]
Sent: Monday, December 1, 2014 8:58 AM
To: dev@community.apache.org; users@trafficserver.apache.org
Subject: [PROPOSAL] Move out release schedule by ~1 month going forward
Hi all,
I’d like to propose that we shift all future releases forward by roughly 2 month. So, the releases would be as following (note that 5.2.0 is on the “legacy” schedule):
5.2.0 — December 2014
5.3.0 — April 2015 (this is an LTS)
6.0.0 — July 2015
6.1.0 — October 2015
6.2.0 — January 2016
6.3.0 — April 2016 (this is an LTS)
The rationale for this is basically that a release in November almost never makes sense. No one will deploy anything around Thanksgiving and/or the winter holidays. In addition, I feel these schedule fits better into how we have been scheduling ATS Summits.
Thoughts?