[jira] [Resolved] (FINERACT-1447) Overdraft Interest calculated is wrong
[ https://issues.apache.org/jira/browse/FINERACT-1447?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]
Manoj Mohanan resolved FINERACT-1447.
-------------------------------------
Resolution: Fixed
> Overdraft Interest calculated is wrong
> --------------------------------------
>
> Key: FINERACT-1447
> URL: https://issues.apache.org/jira/browse/FINERACT-1447
> Project: Apache Fineract
> Issue Type: Bug
> Components: Savings
> Affects Versions: 1.5.0
> Reporter: Manoj Mohanan
> Assignee: Shemin Anto
> Priority: Major
> Attachments: Screenshot from 2021-10-04 12-22-49.png, app_server_usage.png
>
>
> Here is the scenario for replicating the bug.
>
> Step 1 -> Day 1 (current day minus 2): Withdraw 100.
> Step 2 -> Post interest.
> Step 3 -> Day 2: (current day minus 1): Withdraw 1000.
>
> Screenshots attached.
>
> Current interest earned not posted shows: -11.13
> Expected interest earned not posted: 1,112.01 / 100 = 11.1201
--