You are viewing a plain text version of this content. The canonical link for it is here.
Posted to npanday-dev@incubator.apache.org by Jukka Zitting <ju...@gmail.com> on 2012/02/08 16:27:16 UTC

NPanday report is late

Hi,

The February 2012 [1] report from NPanday is still missing. If you
don't have a report ready for this month, please note so in the wiki
page and prepare to report again next month.

What's the status of the NPanday project nowadays? You missed also the
November 2011 report [2], but the earlier report [3] seems positive
and I see quite a bit of activity around the project.

[1] http://wiki.apache.org/incubator/February2012
[2] http://wiki.apache.org/incubator/November2011
[3] http://wiki.apache.org/incubator/August2011

BR,

Jukka Zitting

Re: NPanday report is late

Posted by Dennis Lundberg <de...@apache.org>.
I've signed off the report now.

On 2012-02-10 07:12, Brett Porter wrote:
> I've added the following:
> 
> ---
> NPanday allows projects using the .NET framework to be built with Apache Maven. NPanday has been incubating since August 2010.
> 
> Discussion has been low over the holiday period, but steady work has been put into knocking issues marked for the next releases. There are very few left, and a good number of fixes complete, so a release should come quite shortly. This would be a good opportunity to focus on a graduation plan, and to better promote the project among the .NET and Maven communities and increase the number of users and contributors.
> 
> We continue to see small growth in users, and occasional patch submissions, but haven't added a new committer in a while.
> 
> The top priorities towards graduation are:
> 
> * work out a concrete plan towards graduation in the next quarter
> * encourage newer contributors to do so on a continuing basis.
> 
> There are no issues for the Incubator PMC or board at this time.
> ---
> 
> 
> Sorry about the delay. If anyone is concerned about lack of review, feel free to pull it out and we can resubmit next month...
> 
> Cheers,
> Brett
> 
> On 09/02/2012, at 3:39 AM, Brett Porter wrote:
> 
>> It slipped my mind as we reported in December, not remembering that was a catch up. Thought it was next month.
>>
>> I'll get something together tomorrow.
>>
>> - Brett
>>
>> On 09/02/2012, at 3:27 AM, Jukka Zitting wrote:
>>
>>> Hi,
>>>
>>> The February 2012 [1] report from NPanday is still missing. If you
>>> don't have a report ready for this month, please note so in the wiki
>>> page and prepare to report again next month.
>>>
>>> What's the status of the NPanday project nowadays? You missed also the
>>> November 2011 report [2], but the earlier report [3] seems positive
>>> and I see quite a bit of activity around the project.
>>>
>>> [1] http://wiki.apache.org/incubator/February2012
>>> [2] http://wiki.apache.org/incubator/November2011
>>> [3] http://wiki.apache.org/incubator/August2011
>>>
>>> BR,
>>>
>>> Jukka Zitting
>>
>> --
>> Brett Porter
>> brett@apache.org
>> http://brettporter.wordpress.com/
>> http://au.linkedin.com/in/brettporter
>> http://twitter.com/brettporter
>>
>>
>>
>>
>>
> 
> --
> Brett Porter
> brett@apache.org
> http://brettporter.wordpress.com/
> http://au.linkedin.com/in/brettporter
> http://twitter.com/brettporter
> 
> 
> 
> 
> 
> 


-- 
Dennis Lundberg

Re: NPanday report is late

Posted by Brett Porter <br...@apache.org>.
I've added the following:

---
NPanday allows projects using the .NET framework to be built with Apache Maven. NPanday has been incubating since August 2010.

Discussion has been low over the holiday period, but steady work has been put into knocking issues marked for the next releases. There are very few left, and a good number of fixes complete, so a release should come quite shortly. This would be a good opportunity to focus on a graduation plan, and to better promote the project among the .NET and Maven communities and increase the number of users and contributors.

We continue to see small growth in users, and occasional patch submissions, but haven't added a new committer in a while.

The top priorities towards graduation are:

* work out a concrete plan towards graduation in the next quarter
* encourage newer contributors to do so on a continuing basis.

There are no issues for the Incubator PMC or board at this time.
---


Sorry about the delay. If anyone is concerned about lack of review, feel free to pull it out and we can resubmit next month...

Cheers,
Brett

On 09/02/2012, at 3:39 AM, Brett Porter wrote:

> It slipped my mind as we reported in December, not remembering that was a catch up. Thought it was next month.
> 
> I'll get something together tomorrow.
> 
> - Brett
> 
> On 09/02/2012, at 3:27 AM, Jukka Zitting wrote:
> 
>> Hi,
>> 
>> The February 2012 [1] report from NPanday is still missing. If you
>> don't have a report ready for this month, please note so in the wiki
>> page and prepare to report again next month.
>> 
>> What's the status of the NPanday project nowadays? You missed also the
>> November 2011 report [2], but the earlier report [3] seems positive
>> and I see quite a bit of activity around the project.
>> 
>> [1] http://wiki.apache.org/incubator/February2012
>> [2] http://wiki.apache.org/incubator/November2011
>> [3] http://wiki.apache.org/incubator/August2011
>> 
>> BR,
>> 
>> Jukka Zitting
> 
> --
> Brett Porter
> brett@apache.org
> http://brettporter.wordpress.com/
> http://au.linkedin.com/in/brettporter
> http://twitter.com/brettporter
> 
> 
> 
> 
> 

--
Brett Porter
brett@apache.org
http://brettporter.wordpress.com/
http://au.linkedin.com/in/brettporter
http://twitter.com/brettporter






Re: NPanday report is late

Posted by Brett Porter <br...@apache.org>.
It slipped my mind as we reported in December, not remembering that was a catch up. Thought it was next month.

I'll get something together tomorrow.

- Brett

On 09/02/2012, at 3:27 AM, Jukka Zitting wrote:

> Hi,
> 
> The February 2012 [1] report from NPanday is still missing. If you
> don't have a report ready for this month, please note so in the wiki
> page and prepare to report again next month.
> 
> What's the status of the NPanday project nowadays? You missed also the
> November 2011 report [2], but the earlier report [3] seems positive
> and I see quite a bit of activity around the project.
> 
> [1] http://wiki.apache.org/incubator/February2012
> [2] http://wiki.apache.org/incubator/November2011
> [3] http://wiki.apache.org/incubator/August2011
> 
> BR,
> 
> Jukka Zitting

--
Brett Porter
brett@apache.org
http://brettporter.wordpress.com/
http://au.linkedin.com/in/brettporter
http://twitter.com/brettporter