Thomas Mueller commented on OAK-5970:
-------------------------------------

[~chetanm], with reindexing using oak-run, what is the current plan / state? I think JMX is not needed in this case.

> (Re-)Indexing: estimate progress / ETA
> --------------------------------------
>
>                 Key: OAK-5970
>                 URL: https://issues.apache.org/jira/browse/OAK-5970
>             Project: Jackrabbit Oak
>          Issue Type: New Feature
>          Components: indexing
>            Reporter: Thomas Mueller
>            Assignee: Chetan Mehrotra
>             Fix For: 1.8
>
>
> Reindexing can take a long time, so it would be good if we can estimate where we are at (for example in percent of the relevant number of nodes). It might also be possible to estimate when indexing will be done, and the current path.



--