I tried to write November report and here it is. please review.
S2Graph is a distributed and scalable OLTP graph database built on Apache
HBase to support fast traversal of extremely large graphs.
S2Graph has been incubating since 2015-11-29.
Three most important issues to address in the move towards graduation:
1. Make a third release.
2. Attract more users and contributors.
3. Build the developer community in both size and diversity.
Any issues that the Incubator PMC (IPMC) or ASF Board wish/need to be
aware of?
None
How has the community developed since the last report?
* We had our second official release 0.2.0 on Aug 26th 2017.
* There have been 2 PR from a new contributor
How has the project developed since the last report?
* Discuss the scope of next release.
- New Feature: Provide java client. (on going S2GRAPH-80)
- New Feature: Support more storage backend implementation. (ongoing
S2GRAPH-169, S2GRAPH-166)
- New Feature: Support more Index Provider implementation. (not started)
- New Feature: Implement TinkerPop`s Graph Compute for OLAP support
(not started)
How would you assess the podling's maturity?
Please feel free to add your own commentary.
[ ] Initial setup
[ ] Working towards first release
[x] Community building
[ ] Nearing graduation
[ ] Other:
Date of last release:
2017-08-26
When were the last committers or PPMC members elected?
None
Signed-off-by:
[ ](s2graph) Andrew Purtell
Comments:
[ ](s2graph) Seetharam Venkatesh
Comments:
[ ](s2graph) Sergio Fernández
Comments:
On Sat, Oct 28, 2017 at 9:11 PM <jo...@apache.org> wrote:
> Dear podling,
>
> This email was sent by an automated system on behalf of the Apache
> Incubator PMC. It is an initial reminder to give you plenty of time to
> prepare your quarterly board report.
>
> The board meeting is scheduled for Wed, 15 November 2017, 10:30 am PDT.
> The report for your podling will form a part of the Incubator PMC
> report. The Incubator PMC requires your report to be submitted 2 weeks
> before the board meeting, to allow sufficient time for review and
> submission (Wed, November 01).
>
> Please submit your report with sufficient time to allow the Incubator
> PMC, and subsequently board members to review and digest. Again, the
> very latest you should submit your report is 2 weeks prior to the board
> meeting.
>
> Thanks,
>
> The Apache Incubator PMC
>
> Submitting your Report
>
> ----------------------
>
> Your report should contain the following:
>
> * Your project name
> * A brief description of your project, which assumes no knowledge of
> the project or necessarily of its field
> * A list of the three most important issues to address in the move
> towards graduation.
> * Any issues that the Incubator PMC or ASF Board might wish/need to be
> aware of
> * How has the community developed since the last report
> * How has the project developed since the last report.
> * How does the podling rate their own maturity.
>
> This should be appended to the Incubator Wiki page at:
>
> https://wiki.apache.org/incubator/November2017
>
> Note: This is manually populated. You may need to wait a little before
> this page is created from a template.
>
> Mentors
> -------
>
> Mentors should review reports for their project(s) and sign them off on
> the Incubator wiki page. Signing off reports shows that you are
> following the project - projects that are not signed may raise alarms
> for the Incubator PMC.
>
> Incubator PMC
>
Re: Podling Report Reminder - November 2017
Posted by DO YUNG YOON <sh...@gmail.com>.
Thanks for your review Sergio.
On Fri, Nov 3, 2017 at 10:12 AM Sergio Fernández <wi...@apache.org> wrote:
> LGTM. Signing it off.
>
> On Tue, Oct 31, 2017 at 6:06 PM, DO YUNG YOON <sh...@gmail.com> wrote:
>
> > I tried to write November report and here it is. please review.
> >
> > S2Graph is a distributed and scalable OLTP graph database built on Apache
> > HBase to support fast traversal of extremely large graphs.
> >
> > S2Graph has been incubating since 2015-11-29.
> >
> > Three most important issues to address in the move towards graduation:
> >
> > 1. Make a third release.
> > 2. Attract more users and contributors.
> > 3. Build the developer community in both size and diversity.
> >
> > Any issues that the Incubator PMC (IPMC) or ASF Board wish/need to be
> > aware of?
> >
> > None
> >
> > How has the community developed since the last report?
> >
> > * We had our second official release 0.2.0 on Aug 26th 2017.
> > * There have been 2 PR from a new contributor
> > How has the project developed since the last report?
> >
> > * Discuss the scope of next release.
> > - New Feature: Provide java client. (on going S2GRAPH-80)
> > - New Feature: Support more storage backend implementation. (ongoing
> > S2GRAPH-169, S2GRAPH-166)
> > - New Feature: Support more Index Provider implementation. (not
> > started)
> > - New Feature: Implement TinkerPop`s Graph Compute for OLAP support
> > (not started)
> >
> > How would you assess the podling's maturity?
> > Please feel free to add your own commentary.
> >
> > [ ] Initial setup
> > [ ] Working towards first release
> > [x] Community building
> > [ ] Nearing graduation
> > [ ] Other:
> >
> > Date of last release:
> >
> > 2017-08-26
> >
> > When were the last committers or PPMC members elected?
> >
> > None
> >
> > Signed-off-by:
> >
> > [ ](s2graph) Andrew Purtell
> > Comments:
> > [ ](s2graph) Seetharam Venkatesh
> > Comments:
> > [ ](s2graph) Sergio Fernández
> > Comments:
> >
> >
> >
> > On Sat, Oct 28, 2017 at 9:11 PM <jo...@apache.org> wrote:
> >
> > > Dear podling,
> > >
> > > This email was sent by an automated system on behalf of the Apache
> > > Incubator PMC. It is an initial reminder to give you plenty of time to
> > > prepare your quarterly board report.
> > >
> > > The board meeting is scheduled for Wed, 15 November 2017, 10:30 am PDT.
> > > The report for your podling will form a part of the Incubator PMC
> > > report. The Incubator PMC requires your report to be submitted 2 weeks
> > > before the board meeting, to allow sufficient time for review and
> > > submission (Wed, November 01).
> > >
> > > Please submit your report with sufficient time to allow the Incubator
> > > PMC, and subsequently board members to review and digest. Again, the
> > > very latest you should submit your report is 2 weeks prior to the board
> > > meeting.
> > >
> > > Thanks,
> > >
> > > The Apache Incubator PMC
> > >
> > > Submitting your Report
> > >
> > > ----------------------
> > >
> > > Your report should contain the following:
> > >
> > > * Your project name
> > > * A brief description of your project, which assumes no knowledge of
> > > the project or necessarily of its field
> > > * A list of the three most important issues to address in the move
> > > towards graduation.
> > > * Any issues that the Incubator PMC or ASF Board might wish/need to
> be
> > > aware of
> > > * How has the community developed since the last report
> > > * How has the project developed since the last report.
> > > * How does the podling rate their own maturity.
> > >
> > > This should be appended to the Incubator Wiki page at:
> > >
> > > https://wiki.apache.org/incubator/November2017
> > >
> > > Note: This is manually populated. You may need to wait a little before
> > > this page is created from a template.
> > >
> > > Mentors
> > > -------
> > >
> > > Mentors should review reports for their project(s) and sign them off on
> > > the Incubator wiki page. Signing off reports shows that you are
> > > following the project - projects that are not signed may raise alarms
> > > for the Incubator PMC.
> > >
> > > Incubator PMC
> > >
> >
>
Re: Podling Report Reminder - November 2017
Posted by Sergio Fernández <wi...@apache.org>.
LGTM. Signing it off.
On Tue, Oct 31, 2017 at 6:06 PM, DO YUNG YOON <sh...@gmail.com> wrote:
> I tried to write November report and here it is. please review.
>
> S2Graph is a distributed and scalable OLTP graph database built on Apache
> HBase to support fast traversal of extremely large graphs.
>
> S2Graph has been incubating since 2015-11-29.
>
> Three most important issues to address in the move towards graduation:
>
> 1. Make a third release.
> 2. Attract more users and contributors.
> 3. Build the developer community in both size and diversity.
>
> Any issues that the Incubator PMC (IPMC) or ASF Board wish/need to be
> aware of?
>
> None
>
> How has the community developed since the last report?
>
> * We had our second official release 0.2.0 on Aug 26th 2017.
> * There have been 2 PR from a new contributor
> How has the project developed since the last report?
>
> * Discuss the scope of next release.
> - New Feature: Provide java client. (on going S2GRAPH-80)
> - New Feature: Support more storage backend implementation. (ongoing
> S2GRAPH-169, S2GRAPH-166)
> - New Feature: Support more Index Provider implementation. (not
> started)
> - New Feature: Implement TinkerPop`s Graph Compute for OLAP support
> (not started)
>
> How would you assess the podling's maturity?
> Please feel free to add your own commentary.
>
> [ ] Initial setup
> [ ] Working towards first release
> [x] Community building
> [ ] Nearing graduation
> [ ] Other:
>
> Date of last release:
>
> 2017-08-26
>
> When were the last committers or PPMC members elected?
>
> None
>
> Signed-off-by:
>
> [ ](s2graph) Andrew Purtell
> Comments:
> [ ](s2graph) Seetharam Venkatesh
> Comments:
> [ ](s2graph) Sergio Fernández
> Comments:
>
>
>
> On Sat, Oct 28, 2017 at 9:11 PM <jo...@apache.org> wrote:
>
> > Dear podling,
> >
> > This email was sent by an automated system on behalf of the Apache
> > Incubator PMC. It is an initial reminder to give you plenty of time to
> > prepare your quarterly board report.
> >
> > The board meeting is scheduled for Wed, 15 November 2017, 10:30 am PDT.
> > The report for your podling will form a part of the Incubator PMC
> > report. The Incubator PMC requires your report to be submitted 2 weeks
> > before the board meeting, to allow sufficient time for review and
> > submission (Wed, November 01).
> >
> > Please submit your report with sufficient time to allow the Incubator
> > PMC, and subsequently board members to review and digest. Again, the
> > very latest you should submit your report is 2 weeks prior to the board
> > meeting.
> >
> > Thanks,
> >
> > The Apache Incubator PMC
> >
> > Submitting your Report
> >
> > ----------------------
> >
> > Your report should contain the following:
> >
> > * Your project name
> > * A brief description of your project, which assumes no knowledge of
> > the project or necessarily of its field
> > * A list of the three most important issues to address in the move
> > towards graduation.
> > * Any issues that the Incubator PMC or ASF Board might wish/need to be
> > aware of
> > * How has the community developed since the last report
> > * How has the project developed since the last report.
> > * How does the podling rate their own maturity.
> >
> > This should be appended to the Incubator Wiki page at:
> >
> > https://wiki.apache.org/incubator/November2017
> >
> > Note: This is manually populated. You may need to wait a little before
> > this page is created from a template.
> >
> > Mentors
> > -------
> >
> > Mentors should review reports for their project(s) and sign them off on
> > the Incubator wiki page. Signing off reports shows that you are
> > following the project - projects that are not signed may raise alarms
> > for the Incubator PMC.
> >
> > Incubator PMC
> >
>