Posted to dev@airavata.apache.org by Suresh Marru <sm...@apache.org> on 2013/01/22 15:47:29 UTC

Release discipline & community involvement

Hi All,

As the RM for the first 5 release I have set a bad example on the release process which I would like to request all of us to consider fixing it. We have a very reasonable high commit activity but we are lagging behind on releases and feeling little disorganized. On a good side we are using JIRA efficiently to capture all issues but we are not using them effectively to plan releases (thanks Ate for the wake up call). 

How about we take our agile philosophy [1] literally ? Here is a plan I propose for the releases:

* Follow a strict 6-week release cycle? We can take exceptions but they have to be well justified. 

* 2 weeks JIRA-a-Thon: identify the release features: 
** To focus on quality then quantity, focus on only one or two major features (created as epics or stories) 
** call out for a virtual  to get all get all tasks related to the next release into jira (or tag existing ones to to the release version)
** this the time for the community to respond and make specific requests if they have a burning feature they would like to see in the next release 
** free new feature jira tagging to the next release
** advertise the next release notes (there may be more bug fixes added later) 

* 2 weeks Hack-a-Thon: Run through all the development (added to the 2 weeks of parallel development which happens during JIRA-a-Thon)
** address any deferred issues from previous release
** bug fixes coming through from previous releases 
** feature/bug fix freeze 
** defer any un-finished issues to next release

*1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
** The RC testing among other random testings will need to ensure all advertised release features/bug fixes are properly tested
** improve documentation along with creating release specific documentation

* 1 week Release-a-Thon: Fix RC issues, and iterating over and making a release (if all goes well) 

Spin the cycle 

applauses, grievances, yellings, welcome !! 

Cheers,
Suresh

[1] - http://airavata.apache.org/development/roadmap.html



Re: [VOTE] 6 week release cycle

Posted by Raminder Singh <ra...@gmail.com>.
+1 

On Apr 10, 2013, at 11:30 AM, Chathuri Wimalasena wrote:

> +1 for having 6 week release cycles.
> 
> Regards,
> Chathuri
> 
> 
> On Wed, Apr 10, 2013 at 11:08 AM, Amila Jayasekara
> <th...@gmail.com>wrote:
> 
>> +1, please.
>> 
>> Regards,
>> Amila
>> 
>> 
>> On Wed, Apr 10, 2013 at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:
>> 
>>> Hi All,
>>> 
>>> While drafting the board report I realized we are delaying our releases
>> by
>>> a long time. Our last release was in early january. We are slowly moving
>>> from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we
>>> please consider my proposal below and follow a strict 6 week cycle. Any
>>> delay, lets properly justify and take exception. Since i did not see any
>>> objections before, I will call upon a vote.
>>> 
>>> + 1 I agree 6 week release discipline will be good
>>> + 0 I do not have an opinion on this topic
>>> -1 I do not agree because …..
>>> 
>>> Cheers,
>>> Suresh
>>> 
>>> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
>>> 
>>>> Hi All,
>>>> 
>>>> As the RM for the first 5 release I have set a bad example on the
>>> release process which I would like to request all of us to consider
>> fixing
>>> it. We have a very reasonable high commit activity but we are lagging
>>> behind on releases and feeling little disorganized. On a good side we are
>>> using JIRA efficiently to capture all issues but we are not using them
>>> effectively to plan releases (thanks Ate for the wake up call).
>>>> 
>>>> How about we take our agile philosophy [1] literally ? Here is a plan I
>>> propose for the releases:
>>>> 
>>>> * Follow a strict 6-week release cycle? We can take exceptions but they
>>> have to be well justified.
>>>> 
>>>> * 2 weeks JIRA-a-Thon: identify the release features:
>>>> ** To focus on quality then quantity, focus on only one or two major
>>> features (created as epics or stories)
>>>> ** call out for a virtual  to get all get all tasks related to the next
>>> release into jira (or tag existing ones to to the release version)
>>>> ** this the time for the community to respond and make specific
>> requests
>>> if they have a burning feature they would like to see in the next release
>>>> ** free new feature jira tagging to the next release
>>>> ** advertise the next release notes (there may be more bug fixes added
>>> later)
>>>> 
>>>> * 2 weeks Hack-a-Thon: Run through all the development (added to the 2
>>> weeks of parallel development which happens during JIRA-a-Thon)
>>>> ** address any deferred issues from previous release
>>>> ** bug fixes coming through from previous releases
>>>> ** feature/bug fix freeze
>>>> ** defer any un-finished issues to next release
>>>> 
>>>> *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
>>>> ** The RC testing among other random testings will need to ensure all
>>> advertised release features/bug fixes are properly tested
>>>> ** improve documentation along with creating release specific
>>> documentation
>>>> 
>>>> * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a
>>> release (if all goes well)
>>>> 
>>>> Spin the cycle
>>>> 
>>>> applauses, grievances, yellings, welcome !!
>>>> 
>>>> Cheers,
>>>> Suresh
>>>> 
>>>> [1] - http://airavata.apache.org/development/roadmap.html
>>>> 
>>>> 
>>> 
>>> 
>> 


Re: [VOTE] 6 week release cycle

Posted by Chathuri Wimalasena <ka...@gmail.com>.
+1 for having 6 week release cycles.

Regards,
Chathuri


On Wed, Apr 10, 2013 at 11:08 AM, Amila Jayasekara
<th...@gmail.com>wrote:

> +1, please.
>
> Regards,
> Amila
>
>
> On Wed, Apr 10, 2013 at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:
>
> > Hi All,
> >
> > While drafting the board report I realized we are delaying our releases
> by
> > a long time. Our last release was in early january. We are slowly moving
> > from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we
> > please consider my proposal below and follow a strict 6 week cycle. Any
> > delay, lets properly justify and take exception. Since i did not see any
> > objections before, I will call upon a vote.
> >
> > + 1 I agree 6 week release discipline will be good
> > + 0 I do not have an opinion on this topic
> > -1 I do not agree because …..
> >
> > Cheers,
> > Suresh
> >
> > On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
> >
> > > Hi All,
> > >
> > > As the RM for the first 5 release I have set a bad example on the
> > release process which I would like to request all of us to consider
> fixing
> > it. We have a very reasonable high commit activity but we are lagging
> > behind on releases and feeling little disorganized. On a good side we are
> > using JIRA efficiently to capture all issues but we are not using them
> > effectively to plan releases (thanks Ate for the wake up call).
> > >
> > > How about we take our agile philosophy [1] literally ? Here is a plan I
> > propose for the releases:
> > >
> > > * Follow a strict 6-week release cycle? We can take exceptions but they
> > have to be well justified.
> > >
> > > * 2 weeks JIRA-a-Thon: identify the release features:
> > > ** To focus on quality then quantity, focus on only one or two major
> > features (created as epics or stories)
> > > ** call out for a virtual  to get all get all tasks related to the next
> > release into jira (or tag existing ones to to the release version)
> > > ** this the time for the community to respond and make specific
> requests
> > if they have a burning feature they would like to see in the next release
> > > ** free new feature jira tagging to the next release
> > > ** advertise the next release notes (there may be more bug fixes added
> > later)
> > >
> > > * 2 weeks Hack-a-Thon: Run through all the development (added to the 2
> > weeks of parallel development which happens during JIRA-a-Thon)
> > > ** address any deferred issues from previous release
> > > ** bug fixes coming through from previous releases
> > > ** feature/bug fix freeze
> > > ** defer any un-finished issues to next release
> > >
> > > *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
> > > ** The RC testing among other random testings will need to ensure all
> > advertised release features/bug fixes are properly tested
> > > ** improve documentation along with creating release specific
> > documentation
> > >
> > > * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a
> > release (if all goes well)
> > >
> > > Spin the cycle
> > >
> > > applauses, grievances, yellings, welcome !!
> > >
> > > Cheers,
> > > Suresh
> > >
> > > [1] - http://airavata.apache.org/development/roadmap.html
> > >
> > >
> >
> >
>

Re: [VOTE] 6 week release cycle

Posted by Amila Jayasekara <th...@gmail.com>.
+1, please.

Regards,
Amila


On Wed, Apr 10, 2013 at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:

> Hi All,
>
> While drafting the board report I realized we are delaying our releases by
> a long time. Our last release was in early january. We are slowly moving
> from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we
> please consider my proposal below and follow a strict 6 week cycle. Any
> delay, lets properly justify and take exception. Since i did not see any
> objections before, I will call upon a vote.
>
> + 1 I agree 6 week release discipline will be good
> + 0 I do not have an opinion on this topic
> -1 I do not agree because …..
>
> Cheers,
> Suresh
>
> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
>
> > Hi All,
> >
> > As the RM for the first 5 release I have set a bad example on the
> release process which I would like to request all of us to consider fixing
> it. We have a very reasonable high commit activity but we are lagging
> behind on releases and feeling little disorganized. On a good side we are
> using JIRA efficiently to capture all issues but we are not using them
> effectively to plan releases (thanks Ate for the wake up call).
> >
> > How about we take our agile philosophy [1] literally ? Here is a plan I
> propose for the releases:
> >
> > * Follow a strict 6-week release cycle? We can take exceptions but they
> have to be well justified.
> >
> > * 2 weeks JIRA-a-Thon: identify the release features:
> > ** To focus on quality then quantity, focus on only one or two major
> features (created as epics or stories)
> > ** call out for a virtual  to get all get all tasks related to the next
> release into jira (or tag existing ones to to the release version)
> > ** this the time for the community to respond and make specific requests
> if they have a burning feature they would like to see in the next release
> > ** free new feature jira tagging to the next release
> > ** advertise the next release notes (there may be more bug fixes added
> later)
> >
> > * 2 weeks Hack-a-Thon: Run through all the development (added to the 2
> weeks of parallel development which happens during JIRA-a-Thon)
> > ** address any deferred issues from previous release
> > ** bug fixes coming through from previous releases
> > ** feature/bug fix freeze
> > ** defer any un-finished issues to next release
> >
> > *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
> > ** The RC testing among other random testings will need to ensure all
> advertised release features/bug fixes are properly tested
> > ** improve documentation along with creating release specific
> documentation
> >
> > * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a
> release (if all goes well)
> >
> > Spin the cycle
> >
> > applauses, grievances, yellings, welcome !!
> >
> > Cheers,
> > Suresh
> >
> > [1] - http://airavata.apache.org/development/roadmap.html
> >
> >
>
>

Re: [VOTE] 6 week release cycle

Posted by Marlon Pierce <ma...@iu.edu>.
-----BEGIN PGP SIGNED MESSAGE-----
Hash: SHA1

+1

On 4/10/13 9:33 AM, Saminda Wijeratne wrote:
> +1.
> 
> Quick release cycles is good to stabilize new features. Perhaps
> further we can make 6 weeks the upper limit so that we can go for
> shorter release cycles if needed.
> 
> 
> On Wed, Apr 10, 2013 at 8:13 AM, Suresh Marru <sm...@apache.org>
> wrote:
> 
>> Hi All,
>> 
>> While drafting the board report I realized we are delaying our
>> releases by a long time. Our last release was in early january.
>> We are slowly moving from 2 months to 3 to 4 months. As soon as
>> 0.7 release is done, can we please consider my proposal below and
>> follow a strict 6 week cycle. Any delay, lets properly justify
>> and take exception. Since i did not see any objections before, I
>> will call upon a vote.
>> 
>> + 1 I agree 6 week release discipline will be good + 0 I do not
>> have an opinion on this topic -1 I do not agree because …..
>> 
>> Cheers, Suresh
>> 
>> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org>
>> wrote:
>> 
>>> Hi All,
>>> 
>>> As the RM for the first 5 release I have set a bad example on
>>> the
>> release process which I would like to request all of us to
>> consider fixing it. We have a very reasonable high commit
>> activity but we are lagging behind on releases and feeling little
>> disorganized. On a good side we are using JIRA efficiently to
>> capture all issues but we are not using them effectively to plan
>> releases (thanks Ate for the wake up call).
>>> 
>>> How about we take our agile philosophy [1] literally ? Here is
>>> a plan I
>> propose for the releases:
>>> 
>>> * Follow a strict 6-week release cycle? We can take exceptions
>>> but they
>> have to be well justified.
>>> 
>>> * 2 weeks JIRA-a-Thon: identify the release features: ** To
>>> focus on quality then quantity, focus on only one or two major
>> features (created as epics or stories)
>>> ** call out for a virtual  to get all get all tasks related to
>>> the next
>> release into jira (or tag existing ones to to the release
>> version)
>>> ** this the time for the community to respond and make specific
>>> requests
>> if they have a burning feature they would like to see in the next
>> release
>>> ** free new feature jira tagging to the next release **
>>> advertise the next release notes (there may be more bug fixes
>>> added
>> later)
>>> 
>>> * 2 weeks Hack-a-Thon: Run through all the development (added
>>> to the 2
>> weeks of parallel development which happens during JIRA-a-Thon)
>>> ** address any deferred issues from previous release ** bug
>>> fixes coming through from previous releases ** feature/bug fix
>>> freeze ** defer any un-finished issues to next release
>>> 
>>> *1 week Test-a-Thon: Integrations and testing on trunk and 1
>>> RC ** The RC testing among other random testings will need to
>>> ensure all
>> advertised release features/bug fixes are properly tested
>>> ** improve documentation along with creating release specific
>> documentation
>>> 
>>> * 1 week Release-a-Thon: Fix RC issues, and iterating over and
>>> making a
>> release (if all goes well)
>>> 
>>> Spin the cycle
>>> 
>>> applauses, grievances, yellings, welcome !!
>>> 
>>> Cheers, Suresh
>>> 
>>> [1] - http://airavata.apache.org/development/roadmap.html
>>> 
>>> 
>> 
>> 
> 
-----BEGIN PGP SIGNATURE-----
Version: GnuPG/MacGPG2 v2.0.18 (Darwin)
Comment: GPGTools - http://gpgtools.org
Comment: Using GnuPG with Thunderbird - http://www.enigmail.net/

iQEcBAEBAgAGBQJRZXlLAAoJEOEgD2XReDo54YsH/AqsAcya4FT4W8jBli09DWbb
MuYIJUZJ3qNBeTj8stUkqyqnU2Zf74S95F71V8ifKVLZ7OgYbsRXF/C0Rtnrf5iF
qaYuf+1wmK7N99bXjC3U/ZBBI5Zg/NPAaJ7sMwSELU0YD9PQ3XTpDx2yyiVZJPJW
liBMopn8xdZGN5rjUD8gRNCgI6SW7E6VRP+6RnWNPpZ79iIubPpotw9exkkVnLd5
nA4rmiMxsXBVf4cxhgdkUXmtHar+YIUmNM6rEwAIkq3qp/DAIO2QtC6MeJYXexKH
N2T13ikjmC/EvK+PHMUrAxNu92dYBOUATJpUFaSjLF8JoxxDXDRNRNT8hTIcc/I=
=NblN
-----END PGP SIGNATURE-----

Re: [VOTE] 6 week release cycle

Posted by Saminda Wijeratne <sa...@gmail.com>.
+1.

Quick release cycles is good to stabilize new features. Perhaps further we
can make 6 weeks the upper limit so that we can go for shorter release
cycles if needed.


On Wed, Apr 10, 2013 at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:

> Hi All,
>
> While drafting the board report I realized we are delaying our releases by
> a long time. Our last release was in early january. We are slowly moving
> from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we
> please consider my proposal below and follow a strict 6 week cycle. Any
> delay, lets properly justify and take exception. Since i did not see any
> objections before, I will call upon a vote.
>
> + 1 I agree 6 week release discipline will be good
> + 0 I do not have an opinion on this topic
> -1 I do not agree because …..
>
> Cheers,
> Suresh
>
> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
>
> > Hi All,
> >
> > As the RM for the first 5 release I have set a bad example on the
> release process which I would like to request all of us to consider fixing
> it. We have a very reasonable high commit activity but we are lagging
> behind on releases and feeling little disorganized. On a good side we are
> using JIRA efficiently to capture all issues but we are not using them
> effectively to plan releases (thanks Ate for the wake up call).
> >
> > How about we take our agile philosophy [1] literally ? Here is a plan I
> propose for the releases:
> >
> > * Follow a strict 6-week release cycle? We can take exceptions but they
> have to be well justified.
> >
> > * 2 weeks JIRA-a-Thon: identify the release features:
> > ** To focus on quality then quantity, focus on only one or two major
> features (created as epics or stories)
> > ** call out for a virtual  to get all get all tasks related to the next
> release into jira (or tag existing ones to to the release version)
> > ** this the time for the community to respond and make specific requests
> if they have a burning feature they would like to see in the next release
> > ** free new feature jira tagging to the next release
> > ** advertise the next release notes (there may be more bug fixes added
> later)
> >
> > * 2 weeks Hack-a-Thon: Run through all the development (added to the 2
> weeks of parallel development which happens during JIRA-a-Thon)
> > ** address any deferred issues from previous release
> > ** bug fixes coming through from previous releases
> > ** feature/bug fix freeze
> > ** defer any un-finished issues to next release
> >
> > *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
> > ** The RC testing among other random testings will need to ensure all
> advertised release features/bug fixes are properly tested
> > ** improve documentation along with creating release specific
> documentation
> >
> > * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a
> release (if all goes well)
> >
> > Spin the cycle
> >
> > applauses, grievances, yellings, welcome !!
> >
> > Cheers,
> > Suresh
> >
> > [1] - http://airavata.apache.org/development/roadmap.html
> >
> >
>
>

Re: [VOTE] 6 week release cycle

Posted by Heshan Suriyaarachchi <he...@gmail.com>.
On Wed, Apr 10, 2013 at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:

> Hi All,
>
> While drafting the board report I realized we are delaying our releases by
> a long time. Our last release was in early january. We are slowly moving
> from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we
> please consider my proposal below and follow a strict 6 week cycle. Any
> delay, lets properly justify and take exception. Since i did not see any
> objections before, I will call upon a vote.
>
+1

Then we can focus on defined set of new features and test them properly and
do the release.

>
> + 1 I agree 6 week release discipline will be good
> + 0 I do not have an opinion on this topic
> -1 I do not agree because …..
>
> Cheers,
> Suresh
>
> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
>
> > Hi All,
> >
> > As the RM for the first 5 release I have set a bad example on the
> release process which I would like to request all of us to consider fixing
> it. We have a very reasonable high commit activity but we are lagging
> behind on releases and feeling little disorganized. On a good side we are
> using JIRA efficiently to capture all issues but we are not using them
> effectively to plan releases (thanks Ate for the wake up call).
> >
> > How about we take our agile philosophy [1] literally ? Here is a plan I
> propose for the releases:
> >
> > * Follow a strict 6-week release cycle? We can take exceptions but they
> have to be well justified.
> >
> > * 2 weeks JIRA-a-Thon: identify the release features:
> > ** To focus on quality then quantity, focus on only one or two major
> features (created as epics or stories)
> > ** call out for a virtual  to get all get all tasks related to the next
> release into jira (or tag existing ones to to the release version)
> > ** this the time for the community to respond and make specific requests
> if they have a burning feature they would like to see in the next release
> > ** free new feature jira tagging to the next release
> > ** advertise the next release notes (there may be more bug fixes added
> later)
> >
> > * 2 weeks Hack-a-Thon: Run through all the development (added to the 2
> weeks of parallel development which happens during JIRA-a-Thon)
> > ** address any deferred issues from previous release
> > ** bug fixes coming through from previous releases
> > ** feature/bug fix freeze
> > ** defer any un-finished issues to next release
> >
> > *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
> > ** The RC testing among other random testings will need to ensure all
> advertised release features/bug fixes are properly tested
> > ** improve documentation along with creating release specific
> documentation
> >
> > * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a
> release (if all goes well)
> >
> > Spin the cycle
> >
> > applauses, grievances, yellings, welcome !!
> >
> > Cheers,
> > Suresh
> >
> > [1] - http://airavata.apache.org/development/roadmap.html
> >
> >
>
>


-- 
Regards,
Heshan Suriyaarachchi

http://heshans.blogspot.com/
http://www.linkedin.com/in/heshan

Re: [VOTE] 6 week release cycle

Posted by Suresh Marru <sm...@apache.org>.
Here is my + 1.

We have consensus so far, but since this is a policy, I will leave it open for few more hours before closing, if you have any disagreements please voice them now.

Cheers,
Suresh

On Apr 10, 2013, at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:

> Hi All,
> 
> While drafting the board report I realized we are delaying our releases by a long time. Our last release was in early january. We are slowly moving from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we please consider my proposal below and follow a strict 6 week cycle. Any delay, lets properly justify and take exception. Since i did not see any objections before, I will call upon a vote.
> 
> + 1 I agree 6 week release discipline will be good
> + 0 I do not have an opinion on this topic
> -1 I do not agree because …..
> 
> Cheers,
> Suresh
> 
> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
> 
>> Hi All,
>> 
>> As the RM for the first 5 release I have set a bad example on the release process which I would like to request all of us to consider fixing it. We have a very reasonable high commit activity but we are lagging behind on releases and feeling little disorganized. On a good side we are using JIRA efficiently to capture all issues but we are not using them effectively to plan releases (thanks Ate for the wake up call). 
>> 
>> How about we take our agile philosophy [1] literally ? Here is a plan I propose for the releases:
>> 
>> * Follow a strict 6-week release cycle? We can take exceptions but they have to be well justified. 
>> 
>> * 2 weeks JIRA-a-Thon: identify the release features: 
>> ** To focus on quality then quantity, focus on only one or two major features (created as epics or stories) 
>> ** call out for a virtual  to get all get all tasks related to the next release into jira (or tag existing ones to to the release version)
>> ** this the time for the community to respond and make specific requests if they have a burning feature they would like to see in the next release 
>> ** free new feature jira tagging to the next release
>> ** advertise the next release notes (there may be more bug fixes added later) 
>> 
>> * 2 weeks Hack-a-Thon: Run through all the development (added to the 2 weeks of parallel development which happens during JIRA-a-Thon)
>> ** address any deferred issues from previous release
>> ** bug fixes coming through from previous releases 
>> ** feature/bug fix freeze 
>> ** defer any un-finished issues to next release
>> 
>> *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
>> ** The RC testing among other random testings will need to ensure all advertised release features/bug fixes are properly tested
>> ** improve documentation along with creating release specific documentation
>> 
>> * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a release (if all goes well) 
>> 
>> Spin the cycle 
>> 
>> applauses, grievances, yellings, welcome !! 
>> 
>> Cheers,
>> Suresh
>> 
>> [1] - http://airavata.apache.org/development/roadmap.html
>> 
>> 
> 


[RESULT] [VOTE] 6 week release cycle

Posted by Suresh Marru <sm...@apache.org>.
With 72+ hours, this vote is now closed with the following tally:

+1 Saminda Wijeratne*
+1 Marlon Pierce*
+1 Heshan Suriyaarachchi*
+1 Amila Jayasekara*
+1 Chathuri Wimalasena*
+1 Raminder Singh*
+1 Suresh Marru*

* Binding votes - Airavata PMC Member

The VOTE passes with 7 +1 binding votes and no negatives. The resolution is: Airavata will follow a 6 week release cycle. I will update the website. 

Cheers,
Suresh
On Apr 10, 2013, at 8:13 AM, Suresh Marru <sm...@apache.org> wrote:

> Hi All,
> 
> While drafting the board report I realized we are delaying our releases by a long time. Our last release was in early january. We are slowly moving from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we please consider my proposal below and follow a strict 6 week cycle. Any delay, lets properly justify and take exception. Since i did not see any objections before, I will call upon a vote.
> 
> + 1 I agree 6 week release discipline will be good
> + 0 I do not have an opinion on this topic
> -1 I do not agree because …..
> 
> Cheers,
> Suresh
> 
> On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:
> 
>> Hi All,
>> 
>> As the RM for the first 5 release I have set a bad example on the release process which I would like to request all of us to consider fixing it. We have a very reasonable high commit activity but we are lagging behind on releases and feeling little disorganized. On a good side we are using JIRA efficiently to capture all issues but we are not using them effectively to plan releases (thanks Ate for the wake up call). 
>> 
>> How about we take our agile philosophy [1] literally ? Here is a plan I propose for the releases:
>> 
>> * Follow a strict 6-week release cycle? We can take exceptions but they have to be well justified. 
>> 
>> * 2 weeks JIRA-a-Thon: identify the release features: 
>> ** To focus on quality then quantity, focus on only one or two major features (created as epics or stories) 
>> ** call out for a virtual  to get all get all tasks related to the next release into jira (or tag existing ones to to the release version)
>> ** this the time for the community to respond and make specific requests if they have a burning feature they would like to see in the next release 
>> ** free new feature jira tagging to the next release
>> ** advertise the next release notes (there may be more bug fixes added later) 
>> 
>> * 2 weeks Hack-a-Thon: Run through all the development (added to the 2 weeks of parallel development which happens during JIRA-a-Thon)
>> ** address any deferred issues from previous release
>> ** bug fixes coming through from previous releases 
>> ** feature/bug fix freeze 
>> ** defer any un-finished issues to next release
>> 
>> *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
>> ** The RC testing among other random testings will need to ensure all advertised release features/bug fixes are properly tested
>> ** improve documentation along with creating release specific documentation
>> 
>> * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a release (if all goes well) 
>> 
>> Spin the cycle 
>> 
>> applauses, grievances, yellings, welcome !! 
>> 
>> Cheers,
>> Suresh
>> 
>> [1] - http://airavata.apache.org/development/roadmap.html
>> 
>> 
> 


[VOTE] 6 week release cycle

Posted by Suresh Marru <sm...@apache.org>.
Hi All,

While drafting the board report I realized we are delaying our releases by a long time. Our last release was in early january. We are slowly moving from 2 months to 3 to 4 months. As soon as 0.7 release is done, can we please consider my proposal below and follow a strict 6 week cycle. Any delay, lets properly justify and take exception. Since i did not see any objections before, I will call upon a vote.

+ 1 I agree 6 week release discipline will be good
+ 0 I do not have an opinion on this topic
-1 I do not agree because …..

Cheers,
Suresh

On Jan 22, 2013, at 9:47 AM, Suresh Marru <sm...@apache.org> wrote:

> Hi All,
> 
> As the RM for the first 5 release I have set a bad example on the release process which I would like to request all of us to consider fixing it. We have a very reasonable high commit activity but we are lagging behind on releases and feeling little disorganized. On a good side we are using JIRA efficiently to capture all issues but we are not using them effectively to plan releases (thanks Ate for the wake up call). 
> 
> How about we take our agile philosophy [1] literally ? Here is a plan I propose for the releases:
> 
> * Follow a strict 6-week release cycle? We can take exceptions but they have to be well justified. 
> 
> * 2 weeks JIRA-a-Thon: identify the release features: 
> ** To focus on quality then quantity, focus on only one or two major features (created as epics or stories) 
> ** call out for a virtual  to get all get all tasks related to the next release into jira (or tag existing ones to to the release version)
> ** this the time for the community to respond and make specific requests if they have a burning feature they would like to see in the next release 
> ** free new feature jira tagging to the next release
> ** advertise the next release notes (there may be more bug fixes added later) 
> 
> * 2 weeks Hack-a-Thon: Run through all the development (added to the 2 weeks of parallel development which happens during JIRA-a-Thon)
> ** address any deferred issues from previous release
> ** bug fixes coming through from previous releases 
> ** feature/bug fix freeze 
> ** defer any un-finished issues to next release
> 
> *1 week Test-a-Thon: Integrations and testing on trunk and 1 RC
> ** The RC testing among other random testings will need to ensure all advertised release features/bug fixes are properly tested
> ** improve documentation along with creating release specific documentation
> 
> * 1 week Release-a-Thon: Fix RC issues, and iterating over and making a release (if all goes well) 
> 
> Spin the cycle 
> 
> applauses, grievances, yellings, welcome !! 
> 
> Cheers,
> Suresh
> 