Process Versioning

Hi,

I've just made a small documentation to explain how process versioning
works. For a sneak peek before it gets mirrored:

http://cwiki.apache.org/ODExSITE/process-versioning.html

Feel free to tell me if some parts aren't as clear as I thought.

Cheers,
Matthieu

Re: Process Versioning

Posted by Matthieu Riou <ma...@gmail.com>.
Jim,

You're correct. However you need to add the endpoint definition to your
example.

If process C-1 uses endpoint foo and C-2 uses endpoint foo as well, then C-2
must be retired anyway and A can't continue using C-2. Otherwise your two
endpoints would conflict and the result is a mess. You can't enable two
processes (even two versions of the same process definition) on a single
endpoint.

On the other end if you changed C to use a different endpoint and you still
want to keep C-1 around you can still do it by "branching" which would be
renaming C to D for example and you would have C-1 and D-2 (remember that
the version number is increased globally, subversion style). That would be
an endpoint change so you'd have to update B to make it use the new endpoint
for D.

Cheers,
Matthieu

On 3/22/07, Jim Alateras <ji...@comware.com.au> wrote:
>
> Alex,
>
> Does that mean that if I have two proceses A and B that depend on
> process C, then they will both automatically bind to the latest version
> of process C...that is you can't nominate for process A to continue
> using Process C-1 and process B to use Process C-2.
>
>
> cheers
> </jima>
> Alex Boisvert wrote:
> > On 3/21/07, Jim Alateras <ji...@comware.com.au> wrote:
> >>
> >> I have BundleA-1/ProcessA-1, which calls BundleB-1/ProcessC-1. If I
> >> upgrade BundleB with BundleB-2/ProcessC-2 do i need to make changes to
> >> BundleA-1/ProcessA-1 or will it bind to the latest version of the
> >> ProcessC automatically?
> >
> >
> >
> > It should bind to the newest version (ProcessC -2) based on the fact
> that
> > ProcessC-1 will be retired as a result of deploying the new
> version.  This
> > is assuming you didn't change the service name or endpoint.
> >
> > alex
> >
>
>

Re: Process Versioning

Posted by Jim Alateras <ji...@comware.com.au>.
Alex,

Does that mean that if I have two proceses A and B that depend on 
process C, then they will both automatically bind to the latest version 
of process C...that is you can't nominate for process A to continue 
using Process C-1 and process B to use Process C-2.


cheers
</jima>
Alex Boisvert wrote:
> On 3/21/07, Jim Alateras <ji...@comware.com.au> wrote:
>>
>> I have BundleA-1/ProcessA-1, which calls BundleB-1/ProcessC-1. If I
>> upgrade BundleB with BundleB-2/ProcessC-2 do i need to make changes to
>> BundleA-1/ProcessA-1 or will it bind to the latest version of the
>> ProcessC automatically?
> 
> 
> 
> It should bind to the newest version (ProcessC -2) based on the fact that
> ProcessC-1 will be retired as a result of deploying the new version.  This
> is assuming you didn't change the service name or endpoint.
> 
> alex
> 


Re: Process Versioning

Posted by Alex Boisvert <bo...@intalio.com>.
On 3/21/07, Jim Alateras <ji...@comware.com.au> wrote:
>
> I have BundleA-1/ProcessA-1, which calls BundleB-1/ProcessC-1. If I
> upgrade BundleB with BundleB-2/ProcessC-2 do i need to make changes to
> BundleA-1/ProcessA-1 or will it bind to the latest version of the
> ProcessC automatically?



It should bind to the newest version (ProcessC -2) based on the fact that
ProcessC-1 will be retired as a result of deploying the new version.  This
is assuming you didn't change the service name or endpoint.

alex

Re: Process Versioning

Posted by Jim Alateras <ji...@comware.com.au>.
Matthieu,

Solid start on the versioning document. How does versioning work in the 
case where one process interacts with another process, which is in a 
separate bundle.

This is the use case

I have BundleA-1/ProcessA-1, which calls BundleB-1/ProcessC-1. If I 
upgrade BundleB with BundleB-2/ProcessC-2 do i need to make changes to 
BundleA-1/ProcessA-1 or will it bind to the latest version of the 
ProcessC automatically?

cheers
</jima>
Matthieu Riou wrote:
> Hi,
> 
> I've just made a small documentation to explain how process versioning
> works. For a sneak peek before it gets mirrored:
> 
> http://cwiki.apache.org/ODExSITE/process-versioning.html
> 
> Feel free to tell me if some parts aren't as clear as I thought.
> 
> Cheers,
> Matthieu
>