Posted to dev@kafka.apache.org by "Matthias J. Sax" <mj...@apache.org> on 2026/05/27 05:43:04 UTC
[DISCUSS] Tightening time-based releases
Hello,
I would like to start a discussion about our time-based release
schedule. We have a discussion (that I personally find a little bit
annoying and tedious) about release plan dates on every single release
(the 4.4.0 discussion, is just another example). And we still often end
up with none-optimal time-frames (4.4 might also be an example here --
not by itself, but the impact on 4.5 release timeline -- cf my latest
reply on the other thread).
Given that we actually plan to have time-based releases, I think we
should agree on a more fixed schedule, which allows us to project all
release dates (including KIP/feature/code freeze) into the future and
just be done with it. -- And even if we need an exception from the rule,
we can easily get back on track on future release afterwards.
I was also looking into historic data, and while we overall don't do too
bad to stay on track for 3 release per year, we had to pay the price of
a few short release cycles to "shift back" (the previous 4.3 release is
a good example of it), while we still did shift somewhat forward
overall. These short releases cause even more pain IMHO.
To avoid problems with the holiday season end of the year, I would like
to propose the following fixed release cadence (this is not my personal
favorite, but let's start here):
1. KIP freeze is the second Wednesday of January, May, and September.
2. Feature freeze = KIP freeze + 3 weeks.
3. Code freeze = Feature freeze + 3 weeks.
4. Release target = Code freeze + 4 weeks.
While we never officially formalized the 3+3 weeks between KIP/feature
and feature/code freeze dates (and we used shorter time windows in the
past, ie, 2+2 weeks), 3+3 established itself since 4.0 release -- I am
totally open for other time frames, but believe we should not go shorter
than 2+2 weeks. I would also not make them longer than 3+3, as it would
just give us the subjective impression that releases are closer to each
other.
A 3+2 schedule would actually be my personal preference. For KIPs,
giving only 2 weeks to complete them is tight, even for simple KIPs. And
for bug-fixes, I would believe that 2 weeks are enough. Making it
overall 5 week instead of 6, also helps to keep releases 1 week "further
apart" from each other (not really, but we know how reality works, given
our subjective nature).
The above schedule implies that we would have target release dates late
March, July, and November. Even if we need more than 4 weeks after code
freeze, we still have some head room in the November release before the
holidays (we might hit Thanksgiving, but I think that's ok). For the KIP
freeze in January, it should also give enough time after the holidays to
complete KIPs and get them accepted (w/o being too close to the
holidays, eg, "first Wednesday in January" would effectively mean, that
KIPs must get voted before the holiday break).
If we want to take the holiday season into account even more, we could
also make the timeline between "release 3" and "release 1 of the
following year" two weeks longer, and the other two timelines 1 week
shorter. This would give us the following KIP freeze deadlines:
- third Wednesday of January
- second Wednesday of May
- first Wednesday of September
It also implies, that Thanksgiving would be less of an issue for
"release 3". This schedule is what I would personally prefer, instead of
an 100% equal distribution of our 52 weeks across all three releases.
For the upcoming 4.4 release, we should make it a 5-month cycle
targeting October instead of September, and we would also have a
slightly longer cycle for 4.6, which we should only start in January.
However, starting with 4.6 we would enter the above proposed fixed
timeline, putting us into a much better position going forward IMHO.
Looking forward to your thoughts on this idea.
-Matthias
Re: [DISCUSS] Tightening time-based releases
Posted by Chia-Ping Tsai <ch...@apache.org>.
hi all,
Thanks for driving this. I fully support moving to a fixed 3+2 schedule to eliminate our constant release alignment discussions. Christmas is wonderful, but honestly, Lunar New Year is my personal favorite. I guess Diwali is also a favorite for many of our core maintainers.
Hence, my two cents is a 5 / 3.5 / 3.5-month split:
Release 1: Early May target (KIP freeze in late Feb)
Release 2: Late August target (KIP freeze in mid-June)
Release 3: Early December target (KIP freeze in early Sept)
If we apply 3+2 policy to the current 4.4.0 schedule, it naturally pulls the code freeze forward to July 20. This allows us to target late August for 4.4.0, making it a perfect fit for "Release 2" and smoothly clearing September for the next KIP freeze
Best,
Chia-Ping
On 2026/05/27 05:43:04 "Matthias J. Sax" wrote:
> Hello,
>
> I would like to start a discussion about our time-based release
> schedule. We have a discussion (that I personally find a little bit
> annoying and tedious) about release plan dates on every single release
> (the 4.4.0 discussion, is just another example). And we still often end
> up with none-optimal time-frames (4.4 might also be an example here --
> not by itself, but the impact on 4.5 release timeline -- cf my latest
> reply on the other thread).
>
> Given that we actually plan to have time-based releases, I think we
> should agree on a more fixed schedule, which allows us to project all
> release dates (including KIP/feature/code freeze) into the future and
> just be done with it. -- And even if we need an exception from the rule,
> we can easily get back on track on future release afterwards.
>
> I was also looking into historic data, and while we overall don't do too
> bad to stay on track for 3 release per year, we had to pay the price of
> a few short release cycles to "shift back" (the previous 4.3 release is
> a good example of it), while we still did shift somewhat forward
> overall. These short releases cause even more pain IMHO.
>
> To avoid problems with the holiday season end of the year, I would like
> to propose the following fixed release cadence (this is not my personal
> favorite, but let's start here):
>
> 1. KIP freeze is the second Wednesday of January, May, and September.
> 2. Feature freeze = KIP freeze + 3 weeks.
> 3. Code freeze = Feature freeze + 3 weeks.
> 4. Release target = Code freeze + 4 weeks.
>
> While we never officially formalized the 3+3 weeks between KIP/feature
> and feature/code freeze dates (and we used shorter time windows in the
> past, ie, 2+2 weeks), 3+3 established itself since 4.0 release -- I am
> totally open for other time frames, but believe we should not go shorter
> than 2+2 weeks. I would also not make them longer than 3+3, as it would
> just give us the subjective impression that releases are closer to each
> other.
>
> A 3+2 schedule would actually be my personal preference. For KIPs,
> giving only 2 weeks to complete them is tight, even for simple KIPs. And
> for bug-fixes, I would believe that 2 weeks are enough. Making it
> overall 5 week instead of 6, also helps to keep releases 1 week "further
> apart" from each other (not really, but we know how reality works, given
> our subjective nature).
>
> The above schedule implies that we would have target release dates late
> March, July, and November. Even if we need more than 4 weeks after code
> freeze, we still have some head room in the November release before the
> holidays (we might hit Thanksgiving, but I think that's ok). For the KIP
> freeze in January, it should also give enough time after the holidays to
> complete KIPs and get them accepted (w/o being too close to the
> holidays, eg, "first Wednesday in January" would effectively mean, that
> KIPs must get voted before the holiday break).
>
> If we want to take the holiday season into account even more, we could
> also make the timeline between "release 3" and "release 1 of the
> following year" two weeks longer, and the other two timelines 1 week
> shorter. This would give us the following KIP freeze deadlines:
>
> - third Wednesday of January
> - second Wednesday of May
> - first Wednesday of September
>
> It also implies, that Thanksgiving would be less of an issue for
> "release 3". This schedule is what I would personally prefer, instead of
> an 100% equal distribution of our 52 weeks across all three releases.
>
>
>
> For the upcoming 4.4 release, we should make it a 5-month cycle
> targeting October instead of September, and we would also have a
> slightly longer cycle for 4.6, which we should only start in January.
> However, starting with 4.6 we would enter the above proposed fixed
> timeline, putting us into a much better position going forward IMHO.
>
>
> Looking forward to your thoughts on this idea.
>
>
> -Matthias
>
>
>
Re: [DISCUSS] Tightening time-based releases
Posted by Bill Bejeck <bb...@apache.org>.
Hi Matthias,
Thanks for leading a discussion on release dates. I think it will go a
long way to help with planning and delivery with a more concrete schedule.
I agree with Andrew for 3 releases with the 3+2 schedule.
-Bill
On Wed, May 27, 2026 at 3:44 AM Andrew Schofield <sc...@apache.org>
wrote:
> Hi Matthias,
> Thanks for driving this. I'm a bit less concerned about it than you, but
> stronger rules would eliminate the typical release schedule alignment
> discussions we've seen in all of the recent releases.
>
> I would go for 3 releases of equal lengths in March, July and November. I
> favour the 3+2 schedule.
>
> Thanks,
> Andrew
>
> On 2026/05/27 05:43:04 "Matthias J. Sax" wrote:
> > Hello,
> >
> > I would like to start a discussion about our time-based release
> > schedule. We have a discussion (that I personally find a little bit
> > annoying and tedious) about release plan dates on every single release
> > (the 4.4.0 discussion, is just another example). And we still often end
> > up with none-optimal time-frames (4.4 might also be an example here --
> > not by itself, but the impact on 4.5 release timeline -- cf my latest
> > reply on the other thread).
> >
> > Given that we actually plan to have time-based releases, I think we
> > should agree on a more fixed schedule, which allows us to project all
> > release dates (including KIP/feature/code freeze) into the future and
> > just be done with it. -- And even if we need an exception from the rule,
> > we can easily get back on track on future release afterwards.
> >
> > I was also looking into historic data, and while we overall don't do too
> > bad to stay on track for 3 release per year, we had to pay the price of
> > a few short release cycles to "shift back" (the previous 4.3 release is
> > a good example of it), while we still did shift somewhat forward
> > overall. These short releases cause even more pain IMHO.
> >
> > To avoid problems with the holiday season end of the year, I would like
> > to propose the following fixed release cadence (this is not my personal
> > favorite, but let's start here):
> >
> > 1. KIP freeze is the second Wednesday of January, May, and September.
> > 2. Feature freeze = KIP freeze + 3 weeks.
> > 3. Code freeze = Feature freeze + 3 weeks.
> > 4. Release target = Code freeze + 4 weeks.
> >
> > While we never officially formalized the 3+3 weeks between KIP/feature
> > and feature/code freeze dates (and we used shorter time windows in the
> > past, ie, 2+2 weeks), 3+3 established itself since 4.0 release -- I am
> > totally open for other time frames, but believe we should not go shorter
> > than 2+2 weeks. I would also not make them longer than 3+3, as it would
> > just give us the subjective impression that releases are closer to each
> > other.
> >
> > A 3+2 schedule would actually be my personal preference. For KIPs,
> > giving only 2 weeks to complete them is tight, even for simple KIPs. And
> > for bug-fixes, I would believe that 2 weeks are enough. Making it
> > overall 5 week instead of 6, also helps to keep releases 1 week "further
> > apart" from each other (not really, but we know how reality works, given
> > our subjective nature).
> >
> > The above schedule implies that we would have target release dates late
> > March, July, and November. Even if we need more than 4 weeks after code
> > freeze, we still have some head room in the November release before the
> > holidays (we might hit Thanksgiving, but I think that's ok). For the KIP
> > freeze in January, it should also give enough time after the holidays to
> > complete KIPs and get them accepted (w/o being too close to the
> > holidays, eg, "first Wednesday in January" would effectively mean, that
> > KIPs must get voted before the holiday break).
> >
> > If we want to take the holiday season into account even more, we could
> > also make the timeline between "release 3" and "release 1 of the
> > following year" two weeks longer, and the other two timelines 1 week
> > shorter. This would give us the following KIP freeze deadlines:
> >
> > - third Wednesday of January
> > - second Wednesday of May
> > - first Wednesday of September
> >
> > It also implies, that Thanksgiving would be less of an issue for
> > "release 3". This schedule is what I would personally prefer, instead of
> > an 100% equal distribution of our 52 weeks across all three releases.
> >
> >
> >
> > For the upcoming 4.4 release, we should make it a 5-month cycle
> > targeting October instead of September, and we would also have a
> > slightly longer cycle for 4.6, which we should only start in January.
> > However, starting with 4.6 we would enter the above proposed fixed
> > timeline, putting us into a much better position going forward IMHO.
> >
> >
> > Looking forward to your thoughts on this idea.
> >
> >
> > -Matthias
> >
> >
> >
>
Re: [DISCUSS] Tightening time-based releases
Posted by Chia-Ping Tsai via dev <de...@kafka.apache.org>.
+1 to option 2
I guess the culprit of the delay is still the "must-have backports/CVEs" :)
On 2026/10/31 20:44:28 Andrew Schofield via dev wrote:
> Hi Matthias,
> Option 2 works for me and seems like a good way to transition to
> the more regular release cadence in the future.
>
> Thanks,
> Andrew
>
> On 2026/10/29 22:32:18 Matthias J. Sax wrote:
> > Thanks Andrew.
> >
> > I see that you did keep Jan/13 for KIP freeze, and did not pull it
> > forward. LGTM.
> >
> >
> > > but I think it's very hard to be concrete about 4.6.0 at this point.
> >
> > Is it? In the end, if we say we want to follow the long-term proposed
> > timeline in general, we are looking into the following dates:
> >
> > Proposed KIP-freeze dates for 2027
> >
> > Release-1: March/3 (week 9)
> > Relasee-2: June/23 (week 25)
> > Release-3: Oct/13 (week 41)
> >
> > So there is two options:
> >
> > (1) We keep March/3, and do 4 release in 2027. Personally, I don't
> > think this make a lot of sense. With the Jan/13 KIP freeze for AK 4.5
> > the cycle for AK 4.6 would be way too short IMHO.
> >
> > (2) We treat the AK 4.5 release as release-1, ie, pull forward the
> > March/13 date to Jan/13, and follow with release-2 in June/23 as
> > planned. -- Here we would still have some wiggle room: release-1 is 7
> > weeks earlier than the proposed schedule, so it would make sense to pull
> > forward release-2, too. If we keep June/23 for release-2, we would have
> > 23 weeks for AK 4.6 release, and only 16 weeks for release-3. It might
> > be better to even it out and move release-2 forward by 3 week to have 20
> > weeks for AK 4.6, and 19 weeks for AK 4.7 with Oct/13 KIP freeze date as
> > originally proposed.
> >
> >
> > I would propose to go with option-2 and doing AK 4.6 with KIP freeze
> > Jun/2 (ie, 3 weeks earlier than the proposed long-term schedule).
> >
> >
> > -Matthias
> >
> >
> > On 10/12/26 3:17 AM, Andrew Schofield wrote:
> > > Hi,
> > > I have gone ahead with the 4.5.0 schedule as listed, but I think it's very
> > > hard to be concrete about 4.6.0 at this point.
> > >
> > > Thanks,
> > > Andrew
> > >
> > > On 2026/10/10 20:33:35 Muralidhar Basani via dev wrote:
> > >> Hi all,
> > >>
> > >> I'm not deeply involved in release management, so please take this as just
> > >> some data in case it's useful for the 4.5/4.6 discussion.
> > >>
> > >> I compared the planned dates on the wiki release plans with what actually
> > >> happened in git for the last five releases:
> > >>
> > >> Version Planned Feat Freeze Branch cut Planned target Released
> > >> Late RCs
> > >> 4.0.0 2024-12-11 2024-12-16 2025-01-29
> > >> 2025-03-18 48d 5
> > >> 4.1.0 2025-06-04 2025-06-10 2025-07-09
> > >> 2025-09-02 55d 4
> > >> 4.2.0 2025-11-19 2025-11-21 2026-01-07
> > >> 2026-02-16 40d 5
> > >> 4.3.0 2026-03-18 2026-03-18 2026-05-06
> > >> 2026-05-20 14d 3
> > >> 4.4.0 2026-07-29 2026-07-27 2026-09-09
> > >> 2026-10-12* 33d 5
> > >> (* expected)
> > >>
> > >> Feature freeze is usually on time; the time between code freeze and the
> > >> release is where we tend to need more than planned (median ~40 days after
> > >> the target). With the current 4.5.0 plan, that would put the 4.5.0 release
> > >> around late April 2027, which may be worth keeping in mind when choosing
> > >> the 4.6.0 dates.
> > >>
> > >> I put the small script in this PR, in case it's helpful for future
> > >> planning: https://github.com/apache/kafka/pull/23769
> > >> Added sample runs in the PR.
> > >> If this is not the direction we want, happy to close it.
> > >>
> > >>
> > >> Here is a short snippet from the scripts run
> > >>
> > >> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
> > >>
> > >> % python3 release/schedule.py
> > >> ....
> > >> ....
> > >> version KIP freeze derived from feature freeze code freeze
> > >> first RC target release realistic release
> > >> ------- ---------- ----------------- --------------
> > >> ----------- ---------- --------------
> > >> -----------------
> > >> 4.5.0 2027-01-13 wiki release plan 2027-02-03 2027-02-17
> > >> 2027-03-16 2027-03-17 2027-04-28
> > >> 4.6.0 2027-05-19 history 2027-06-09 2027-06-23
> > >> 2027-07-20 2027-07-21 2027-09-01
> > >> 4.7.0 2027-09-22 history 2027-10-13 2027-10-27
> > >> 2027-11-23 2027-11-24 2028-01-05
> > >> ...
> > >>
> > >> %python3 release/schedule.py --release-date 4.4.0=2026-10-12 status 4.6.0
> > >> ....
> > >> ....
> > >> Release 4.6.0 as of 2026-10-10 (dates: history)
> > >> KIP freeze 2027-05-19 (in 221 days)
> > >> feature freeze 2027-06-09 (in 242 days)
> > >> code freeze 2027-06-23 (in 256 days)
> > >> first RC 2027-07-20 (in 283 days)
> > >> target release 2027-07-21 (in 284 days)
> > >> realistic release 2027-09-01 (in 326 days)
> > >> ...
> > >> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
> > >>
> > >>
> > >> Thanks,
> > >> Murali
> > >>
> > >> On Sat, Oct 10, 2026 at 3:33 PM Matthias J. Sax <mj...@apache.org> wrote:
> > >>
> > >>> What's you rational for doing 4.6 in March already? If we so 4.5
> > >>> early/mid January, it would be a very small release. Given the overhead
> > >>> releases have, I am wondering if it would be worth doing?
> > >>>
> > >>> For 4.5, I am also ok to start a Jan/6 instead of Jan/13 with KIP
> > >>> freeze. If we do 4.6 in July (instead of March) I don't see a need to
> > >>> pull it forward by one a week though. But I am fine in any case.
> > >>>
> > >>> -Matthias
> > >>>
> > >>> On 9/28/26 11:49 PM, Dejan Stojadinović wrote:
> > >>>>> "Anyway, all I want to say is that the original schedule was hard to
> > >>>> follow. The codebase is large and CVEs are common these days."
> > >>>>
> > >>>> As an occasional contributor I can confirm this.
> > >>>> From my POV committers/maintainers are having a challenging task to keep
> > >>>> up, especially while trying to juggle around with multiple release
> > >>>> branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
> > >>>>
> > >>>> Best regards,
> > >>>> Dejan S.
> > >>>> https://github.com/dejan2609
> > >>>>
> > >>>>
> > >>>> On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org>
> > >>> wrote:
> > >>>>
> > >>>>> Hi Andrew,
> > >>>>>
> > >>>>> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
> > >>>>> since that puts the KIP freeze right after the holidays.
> > >>>>>
> > >>>>> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
> > >>>>> reaches code freeze. We had too many must-have changes in 4.4.0, which
> > >>>>> caused a serious delay. I try to review all backports but my tokens are
> > >>>>> limited :)
> > >>>>>
> > >>>>> Anyway, all I want to say is that the original schedule was hard to
> > >>>>> follow. The codebase is large and CVEs are common these days.
> > >>>>>
> > >>>>> Best,
> > >>>>> Chia-Ping
> > >>>>>
> > >>>>>
> > >>>>> On 2026/09/25 08:36:23 Andrew Schofield wrote:
> > >>>>>> Hi,
> > >>>>>> I'm starting to look at the release schedule for 4.5.0.
> > >>>>>>
> > >>>>>> In Chia-Ping's table from 29 May 2026, we have:
> > >>>>>>
> > >>>>>> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
> > >>>>>> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19,
> > >>> 2026
> > >>>>>> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
> > >>>>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> > >>>>>>
> > >>>>>> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
> > >>>>> freeze of Jan 13, 2027 which gives this.
> > >>>>>>
> > >>>>>> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon
> > >>> now
> > >>>>>> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17,
> > >>> 2027
> > >>>>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> > >>>>>>
> > >>>>>> I think we could even pull 4.5.0 a week earlier than that, but I don't
> > >>>>> think there's anything fundamentally wrong with a short 4.6.0 provided
> > >>>>> people know in advance.
> > >>>>>>
> > >>>>>> Are people happy with the 4.5.0 (revised) dates above? Would a week
> > >>>>> earlier be better given that it gives an extra week to 4.6.0 which is
> > >>>>> looking very squeezed?
> > >>>>>>
> > >>>>>> Thanks,
> > >>>>>> Andrew
> > >>>>>>
> > >>>>>> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> > >>>>>>> Hi all,
> > >>>>>>>
> > >>>>>>> +1 to the 4.5 schedule, given the delay of 4.4.0.
> > >>>>>>>
> > >>>>>>> I think having 4.5 land right on Lunar New Year should be fine this
> > >>>>> time, since "too close" is the real issue here.
> > >>>>>>>
> > >>>>>>> Best,
> > >>>>>>> Chia-Ping
> > >>>>>>>
> > >>>>>>>> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> > >>>>>>>>
> > >>>>>>>> I don't think we have for 4.5... I believe that there was a slight,
> > >>>>> high level agreement for the long term, that we want to follow the
> > >>>>> "calendar week proposal"?
> > >>>>>>>>
> > >>>>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
> > >>>>> feature freeze
> > >>>>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
> > >>>>>>>>
> > >>>>>>>> AK 4.4 KIP freeze was Jul/8.
> > >>>>>>>>
> > >>>>>>>> For 2026, week 41 would be Oct/7 which is way too close IMHO.
> > >>>>>>>> For 2027, week 9 would be Mar/3 which seems to be too far out?
> > >>>>>>>>
> > >>>>>>>> Second release (week 25) for 2027 would be Jun/23, which would be
> > >>>>> 4.6?
> > >>>>>>>>
> > >>>>>>>> So the question remains, where to put 4.5 so we can start to follow
> > >>>>> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
> > >>>>> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
> > >>>>> freeze dates. Of course, the release would overlap with Chinese New
> > >>> Year,
> > >>>>> but it would be the last time we have this overlap.
> > >>>>>>>>
> > >>>>>>>> Just my 2tc.
> > >>>>>>>>
> > >>>>>>>>
> > >>>>>>>> -Matthias
> > >>>>>>>>
> > >>>>>>>>> On 9/15/26 8:17 AM, David Jacot wrote:
> > >>>>>>>>> Hi all,
> > >>>>>>>>> Have we converged on the schedule that we want to use yet? Based on
> > >>>>>>>>> the last emails, it is not so clear to me. For your context, I am
> > >>>>>>>>> trying to figure out the timeline for 4.5.
> > >>>>>>>>> Best,
> > >>>>>>>>> David
> > >>>>>>>>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
> > >>>>> christololov@gmail.com> wrote:
> > >>>>>>>>>>
> > >>>>>>>>>> I think we could be a bit more lax with the KIP freeze of 6.7.0
> > >>>>> when
> > >>>>>>>>>> 2034 comes around to account for LNY :)
> > >>>>>>>>>>
> > >>>>>>>>>> Joking aside, my preference between "KIP freeze would be
> > >>>>> Wednesday's,
> > >>>>>>>>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> > >>>>>>>>>> weeks" and "start Q1 release with X buffer after LYN and complete
> > >>>>> Q3
> > >>>>>>>>>> release with Y buffer before Christmas" would be to start with the
> > >>>>>>>>>> first and adjust by shifting by 1 week on individual basis the ones
> > >>>>>>>>>> which are too close. I am okay with too close being defined as 2
> > >>>>>>>>>> weeks. Based on your very detailed tables we seem to have only a
> > >>>>> few
> > >>>>>>>>>> such outliers in the next decade.
> > >>>>>>>>>>
> > >>>>>>>>>> Best,
> > >>>>>>>>>> Christo
> > >>>>>>>>>>
> > >>>>>>>>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
> > >>>>> wrote:
> > >>>>>>>>>>>
> > >>>>>>>>>>> Matthias, you are definitely a master of scheduling! I'm +100 to
> > >>>>> your plans.
> > >>>>>>>>>>>
> > >>>>>>>>>>> Also, it is absolutely helpful to write down the exact release
> > >>>>> dates for the next few years at once. It will ease our anxiety a lot!
> > >>> I'd
> > >>>>> be more than happy to update the wiki with these dates once we all
> > >>> agree on
> > >>>>> this new schedule. For example:
> > >>>>>>>>>>>
> > >>>>>>>>>>> Version KIP Freeze Feature Freeze Code Freeze Target
> > >>>>> Release
> > >>>>>>>>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
> > >>>>> 2026
> > >>>>>>>>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
> > >>>>> 2026
> > >>>>>>>>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
> > >>>>> 2027
> > >>>>>>>>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
> > >>>>> 2027
> > >>>>>>>>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
> > >>>>> 2027
> > >>>>>>>>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
> > >>>>> 2028
> > >>>>>>>>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
> > >>>>> 2028
> > >>>>>>>>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
> > >>>>> 2028
> > >>>>>>>>>>>
> > >>>>>>>>>>> Furthermore, let's do our best to avoid fixing release blockers
> > >>>>> under the Christmas tree :)
> > >>>>>>>>>>>
> > >>>>>>>>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> > >>>>>>>>>>>> Thanks for the input.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> > >>>>>>>>>>>> windows gets a lot of support.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> However, the idea of dividing the release windows not into 3
> > >>>>> equally
> > >>>>>>>>>>>> long junks, but be more flexible to account for holiday seasons,
> > >>>>> seems
> > >>>>>>>>>>>> not to get a lot of support? Not sure why... I personally think
> > >>>>> it would
> > >>>>>>>>>>>> be good to take it into account, and I also think that Chia-Ping
> > >>>>> raises
> > >>>>>>>>>>>> a very good point.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
> > >>>>> it. I
> > >>>>>>>>>>>> did actually briefly think about it, but it's difficult, and
> > >>>>> thus I just
> > >>>>>>>>>>>> started with something simple as proposal to kick off a
> > >>>>> discussion.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> I think, Diwali is short enough to not make it a concern
> > >>>>> (similar to
> > >>>>>>>>>>>> Thanksgiving)?
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> For Lunar New Year, I agree that it would be good to plan for it.
> > >>>>>>>>>>>> However, it seems it's shifting quite a lot year-over-year what
> > >>>>> makes it
> > >>>>>>>>>>>> very difficult (w/o a huge window) to include?
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
> > >>>>> (this
> > >>>>>>>>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
> > >>>>> month
> > >>>>>>>>>>>> releases does not sound very appealing?
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> I was playing with it a little bit more. Overall we have 52
> > >>>>> weeks, so
> > >>>>>>>>>>>> roughly 17.3 weeks per release. So we can naturally split it into
> > >>>>>>>>>>>> 17/17/18 using the additional week for the holidays. But that's
> > >>>>> not good
> > >>>>>>>>>>>> enough to take both Christmas and Lunar New Year into account.
> > >>>>> However,
> > >>>>>>>>>>>> with a 16/16/20, we could make it work I believe, even if it
> > >>>>> does cut it
> > >>>>>>>>>>>> tight sometimes... To be able to phrase a "simple rule", we can
> > >>>>> use ISO
> > >>>>>>>>>>>> weeks:
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
> > >>>>> freeze
> > >>>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
> > >>>>> for most
> > >>>>>>>>>>>> years:
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > >>>>>>>>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
> > >>>>> Buffer │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
> > >>>>> tightest with realistic LNY │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
> > >>>>> │
> > >>>>>>>>>>>>>
> > >>>>>
> > >>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> Guess, we could also make it week-8 instead of 9, and accept
> > >>>>> that 2034
> > >>>>>>>>>>>> would cut it too short (or be even more flexible and keep week-9
> > >>>>> for
> > >>>>>>>>>>>> 2034 as an exception to the rule), but that's a single year...
> > >>>>> for 2029
> > >>>>>>>>>>>> and 2032 we still have one week buffer.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> For Christmas, we would still ensure that the release can go out
> > >>>>> on
> > >>>>>>>>>>>> time, too. The below Q3 target release date is 4 weeks after code
> > >>>>>>>>>>>> freeze. This is a little bit more tight, as we often need more
> > >>>>> than 4
> > >>>>>>>>>>>> weeks to get it done:
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>> ┌──────┬──────────────────────────┬────────────────┐
> > >>>>>>>>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2026 │ Dec 9 │ 16 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2027 │ Dec 15 │ 10 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2028 │ Dec 13 │ 12 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2029 │ Dec 12 │ 13 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2030 │ Dec 11 │ 14 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2031 │ Dec 10 │ 15 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2032 │ Dec 8 │ 17 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2033 │ Dec 14 │ 11 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2034 │ Dec 13 │ 12 │
> > >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>>>>> │ 2035 │ Dec 12 │ 13 │
> > >>>>>>>>>>>>> └──────┴──────────────────────────┴────────────────┘
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> For some years, we would still cut it a little bit tight, but we
> > >>>>> could
> > >>>>>>>>>>>> also apply an exception to the rule, to compensate for it. If we
> > >>>>> have
> > >>>>>>>>>>>> enough buffer room from LYN, we can start the Q1 release train a
> > >>>>> week
> > >>>>>>>>>>>> earlier, reducing the Q3->Q1 timeline by one week.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> Curious to hear what people think about it. In the end, if we
> > >>>>> can agree
> > >>>>>>>>>>>> on high level rules like "start Q1 release with X buffer after
> > >>>>> LYN", and
> > >>>>>>>>>>>> "complete Q3 release with Y buffer before Christmas", and still
> > >>>>> aim for
> > >>>>>>>>>>>> an as balance week-allocation per release, we can just put
> > >>>>> together a
> > >>>>>>>>>>>> release plan for the next 10 years and be done with it.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> -Matthias
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> > >>>>>>>>>>>>> Hello,
> > >>>>>>>>>>>>>
> > >>>>>>>>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
> > >>>>> release
> > >>>>>>>>>>>>> coincided with a reasonable amount of holidays, so I would
> > >>>>> favour a
> > >>>>>>>>>>>>> 3+2 schedule with releases in March, July and November.
> > >>>>>>>>>>>>>
> > >>>>>>>>>>>>> Best,
> > >>>>>>>>>>>>> Christo
> > >>>>>>>>>>>>>
> > >>>>>>>>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
> > >>>>> wrote:
> > >>>>>>>>>>>>>>
> > >>>>>>>>>>>>>> Hi,
> > >>>>>>>>>>>>>>
> > >>>>>>>>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
> > >>>>> schofielaj@apache.org>
> > >>>>>>>>>>>>>> wrote:
> > >>>>>>>>>>>>>>
> > >>>>>>>>>>>>>>> I would go for 3 releases of equal lengths in March, July and
> > >>>>> November. I
> > >>>>>>>>>>>>>>> favour the 3+2 schedule.
> > >>>>>>>>>>>>>>>
> > >>>>>>>>>>>>>>
> > >>>>>>>>>>>>>> +1
> > >>>>>>>>>>>>>>
> > >>>>>>>>>>>>>> Thanks,
> > >>>>>>>>>>>>>> Ismael
> > >>>>>>>>>>>>
> > >>>>>>>>>>>>
> > >>>>>>>>
> > >>>>>>>
> > >>>>>>
> > >>>>>
> > >>>
> > >>>
> > >>
> >
> >
>
Re: [DISCUSS] Tightening time-based releases
Posted by Andrew Schofield via dev <de...@kafka.apache.org>.
Hi Matthias,
Option 2 works for me and seems like a good way to transition to
the more regular release cadence in the future.
Thanks,
Andrew
On 2026/10/29 22:32:18 Matthias J. Sax wrote:
> Thanks Andrew.
>
> I see that you did keep Jan/13 for KIP freeze, and did not pull it
> forward. LGTM.
>
>
> > but I think it's very hard to be concrete about 4.6.0 at this point.
>
> Is it? In the end, if we say we want to follow the long-term proposed
> timeline in general, we are looking into the following dates:
>
> Proposed KIP-freeze dates for 2027
>
> Release-1: March/3 (week 9)
> Relasee-2: June/23 (week 25)
> Release-3: Oct/13 (week 41)
>
> So there is two options:
>
> (1) We keep March/3, and do 4 release in 2027. Personally, I don't
> think this make a lot of sense. With the Jan/13 KIP freeze for AK 4.5
> the cycle for AK 4.6 would be way too short IMHO.
>
> (2) We treat the AK 4.5 release as release-1, ie, pull forward the
> March/13 date to Jan/13, and follow with release-2 in June/23 as
> planned. -- Here we would still have some wiggle room: release-1 is 7
> weeks earlier than the proposed schedule, so it would make sense to pull
> forward release-2, too. If we keep June/23 for release-2, we would have
> 23 weeks for AK 4.6 release, and only 16 weeks for release-3. It might
> be better to even it out and move release-2 forward by 3 week to have 20
> weeks for AK 4.6, and 19 weeks for AK 4.7 with Oct/13 KIP freeze date as
> originally proposed.
>
>
> I would propose to go with option-2 and doing AK 4.6 with KIP freeze
> Jun/2 (ie, 3 weeks earlier than the proposed long-term schedule).
>
>
> -Matthias
>
>
> On 10/12/26 3:17 AM, Andrew Schofield wrote:
> > Hi,
> > I have gone ahead with the 4.5.0 schedule as listed, but I think it's very
> > hard to be concrete about 4.6.0 at this point.
> >
> > Thanks,
> > Andrew
> >
> > On 2026/10/10 20:33:35 Muralidhar Basani via dev wrote:
> >> Hi all,
> >>
> >> I'm not deeply involved in release management, so please take this as just
> >> some data in case it's useful for the 4.5/4.6 discussion.
> >>
> >> I compared the planned dates on the wiki release plans with what actually
> >> happened in git for the last five releases:
> >>
> >> Version Planned Feat Freeze Branch cut Planned target Released
> >> Late RCs
> >> 4.0.0 2024-12-11 2024-12-16 2025-01-29
> >> 2025-03-18 48d 5
> >> 4.1.0 2025-06-04 2025-06-10 2025-07-09
> >> 2025-09-02 55d 4
> >> 4.2.0 2025-11-19 2025-11-21 2026-01-07
> >> 2026-02-16 40d 5
> >> 4.3.0 2026-03-18 2026-03-18 2026-05-06
> >> 2026-05-20 14d 3
> >> 4.4.0 2026-07-29 2026-07-27 2026-09-09
> >> 2026-10-12* 33d 5
> >> (* expected)
> >>
> >> Feature freeze is usually on time; the time between code freeze and the
> >> release is where we tend to need more than planned (median ~40 days after
> >> the target). With the current 4.5.0 plan, that would put the 4.5.0 release
> >> around late April 2027, which may be worth keeping in mind when choosing
> >> the 4.6.0 dates.
> >>
> >> I put the small script in this PR, in case it's helpful for future
> >> planning: https://github.com/apache/kafka/pull/23769
> >> Added sample runs in the PR.
> >> If this is not the direction we want, happy to close it.
> >>
> >>
> >> Here is a short snippet from the scripts run
> >>
> >> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
> >>
> >> % python3 release/schedule.py
> >> ....
> >> ....
> >> version KIP freeze derived from feature freeze code freeze
> >> first RC target release realistic release
> >> ------- ---------- ----------------- --------------
> >> ----------- ---------- --------------
> >> -----------------
> >> 4.5.0 2027-01-13 wiki release plan 2027-02-03 2027-02-17
> >> 2027-03-16 2027-03-17 2027-04-28
> >> 4.6.0 2027-05-19 history 2027-06-09 2027-06-23
> >> 2027-07-20 2027-07-21 2027-09-01
> >> 4.7.0 2027-09-22 history 2027-10-13 2027-10-27
> >> 2027-11-23 2027-11-24 2028-01-05
> >> ...
> >>
> >> %python3 release/schedule.py --release-date 4.4.0=2026-10-12 status 4.6.0
> >> ....
> >> ....
> >> Release 4.6.0 as of 2026-10-10 (dates: history)
> >> KIP freeze 2027-05-19 (in 221 days)
> >> feature freeze 2027-06-09 (in 242 days)
> >> code freeze 2027-06-23 (in 256 days)
> >> first RC 2027-07-20 (in 283 days)
> >> target release 2027-07-21 (in 284 days)
> >> realistic release 2027-09-01 (in 326 days)
> >> ...
> >> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
> >>
> >>
> >> Thanks,
> >> Murali
> >>
> >> On Sat, Oct 10, 2026 at 3:33 PM Matthias J. Sax <mj...@apache.org> wrote:
> >>
> >>> What's you rational for doing 4.6 in March already? If we so 4.5
> >>> early/mid January, it would be a very small release. Given the overhead
> >>> releases have, I am wondering if it would be worth doing?
> >>>
> >>> For 4.5, I am also ok to start a Jan/6 instead of Jan/13 with KIP
> >>> freeze. If we do 4.6 in July (instead of March) I don't see a need to
> >>> pull it forward by one a week though. But I am fine in any case.
> >>>
> >>> -Matthias
> >>>
> >>> On 9/28/26 11:49 PM, Dejan Stojadinović wrote:
> >>>>> "Anyway, all I want to say is that the original schedule was hard to
> >>>> follow. The codebase is large and CVEs are common these days."
> >>>>
> >>>> As an occasional contributor I can confirm this.
> >>>> From my POV committers/maintainers are having a challenging task to keep
> >>>> up, especially while trying to juggle around with multiple release
> >>>> branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
> >>>>
> >>>> Best regards,
> >>>> Dejan S.
> >>>> https://github.com/dejan2609
> >>>>
> >>>>
> >>>> On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org>
> >>> wrote:
> >>>>
> >>>>> Hi Andrew,
> >>>>>
> >>>>> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
> >>>>> since that puts the KIP freeze right after the holidays.
> >>>>>
> >>>>> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
> >>>>> reaches code freeze. We had too many must-have changes in 4.4.0, which
> >>>>> caused a serious delay. I try to review all backports but my tokens are
> >>>>> limited :)
> >>>>>
> >>>>> Anyway, all I want to say is that the original schedule was hard to
> >>>>> follow. The codebase is large and CVEs are common these days.
> >>>>>
> >>>>> Best,
> >>>>> Chia-Ping
> >>>>>
> >>>>>
> >>>>> On 2026/09/25 08:36:23 Andrew Schofield wrote:
> >>>>>> Hi,
> >>>>>> I'm starting to look at the release schedule for 4.5.0.
> >>>>>>
> >>>>>> In Chia-Ping's table from 29 May 2026, we have:
> >>>>>>
> >>>>>> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
> >>>>>> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19,
> >>> 2026
> >>>>>> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
> >>>>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> >>>>>>
> >>>>>> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
> >>>>> freeze of Jan 13, 2027 which gives this.
> >>>>>>
> >>>>>> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon
> >>> now
> >>>>>> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17,
> >>> 2027
> >>>>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> >>>>>>
> >>>>>> I think we could even pull 4.5.0 a week earlier than that, but I don't
> >>>>> think there's anything fundamentally wrong with a short 4.6.0 provided
> >>>>> people know in advance.
> >>>>>>
> >>>>>> Are people happy with the 4.5.0 (revised) dates above? Would a week
> >>>>> earlier be better given that it gives an extra week to 4.6.0 which is
> >>>>> looking very squeezed?
> >>>>>>
> >>>>>> Thanks,
> >>>>>> Andrew
> >>>>>>
> >>>>>> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> >>>>>>> Hi all,
> >>>>>>>
> >>>>>>> +1 to the 4.5 schedule, given the delay of 4.4.0.
> >>>>>>>
> >>>>>>> I think having 4.5 land right on Lunar New Year should be fine this
> >>>>> time, since "too close" is the real issue here.
> >>>>>>>
> >>>>>>> Best,
> >>>>>>> Chia-Ping
> >>>>>>>
> >>>>>>>> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> >>>>>>>>
> >>>>>>>> I don't think we have for 4.5... I believe that there was a slight,
> >>>>> high level agreement for the long term, that we want to follow the
> >>>>> "calendar week proposal"?
> >>>>>>>>
> >>>>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
> >>>>> feature freeze
> >>>>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
> >>>>>>>>
> >>>>>>>> AK 4.4 KIP freeze was Jul/8.
> >>>>>>>>
> >>>>>>>> For 2026, week 41 would be Oct/7 which is way too close IMHO.
> >>>>>>>> For 2027, week 9 would be Mar/3 which seems to be too far out?
> >>>>>>>>
> >>>>>>>> Second release (week 25) for 2027 would be Jun/23, which would be
> >>>>> 4.6?
> >>>>>>>>
> >>>>>>>> So the question remains, where to put 4.5 so we can start to follow
> >>>>> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
> >>>>> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
> >>>>> freeze dates. Of course, the release would overlap with Chinese New
> >>> Year,
> >>>>> but it would be the last time we have this overlap.
> >>>>>>>>
> >>>>>>>> Just my 2tc.
> >>>>>>>>
> >>>>>>>>
> >>>>>>>> -Matthias
> >>>>>>>>
> >>>>>>>>> On 9/15/26 8:17 AM, David Jacot wrote:
> >>>>>>>>> Hi all,
> >>>>>>>>> Have we converged on the schedule that we want to use yet? Based on
> >>>>>>>>> the last emails, it is not so clear to me. For your context, I am
> >>>>>>>>> trying to figure out the timeline for 4.5.
> >>>>>>>>> Best,
> >>>>>>>>> David
> >>>>>>>>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
> >>>>> christololov@gmail.com> wrote:
> >>>>>>>>>>
> >>>>>>>>>> I think we could be a bit more lax with the KIP freeze of 6.7.0
> >>>>> when
> >>>>>>>>>> 2034 comes around to account for LNY :)
> >>>>>>>>>>
> >>>>>>>>>> Joking aside, my preference between "KIP freeze would be
> >>>>> Wednesday's,
> >>>>>>>>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> >>>>>>>>>> weeks" and "start Q1 release with X buffer after LYN and complete
> >>>>> Q3
> >>>>>>>>>> release with Y buffer before Christmas" would be to start with the
> >>>>>>>>>> first and adjust by shifting by 1 week on individual basis the ones
> >>>>>>>>>> which are too close. I am okay with too close being defined as 2
> >>>>>>>>>> weeks. Based on your very detailed tables we seem to have only a
> >>>>> few
> >>>>>>>>>> such outliers in the next decade.
> >>>>>>>>>>
> >>>>>>>>>> Best,
> >>>>>>>>>> Christo
> >>>>>>>>>>
> >>>>>>>>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
> >>>>> wrote:
> >>>>>>>>>>>
> >>>>>>>>>>> Matthias, you are definitely a master of scheduling! I'm +100 to
> >>>>> your plans.
> >>>>>>>>>>>
> >>>>>>>>>>> Also, it is absolutely helpful to write down the exact release
> >>>>> dates for the next few years at once. It will ease our anxiety a lot!
> >>> I'd
> >>>>> be more than happy to update the wiki with these dates once we all
> >>> agree on
> >>>>> this new schedule. For example:
> >>>>>>>>>>>
> >>>>>>>>>>> Version KIP Freeze Feature Freeze Code Freeze Target
> >>>>> Release
> >>>>>>>>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
> >>>>> 2026
> >>>>>>>>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
> >>>>> 2026
> >>>>>>>>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
> >>>>> 2027
> >>>>>>>>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
> >>>>> 2027
> >>>>>>>>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
> >>>>> 2027
> >>>>>>>>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
> >>>>> 2028
> >>>>>>>>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
> >>>>> 2028
> >>>>>>>>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
> >>>>> 2028
> >>>>>>>>>>>
> >>>>>>>>>>> Furthermore, let's do our best to avoid fixing release blockers
> >>>>> under the Christmas tree :)
> >>>>>>>>>>>
> >>>>>>>>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> >>>>>>>>>>>> Thanks for the input.
> >>>>>>>>>>>>
> >>>>>>>>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> >>>>>>>>>>>> windows gets a lot of support.
> >>>>>>>>>>>>
> >>>>>>>>>>>> However, the idea of dividing the release windows not into 3
> >>>>> equally
> >>>>>>>>>>>> long junks, but be more flexible to account for holiday seasons,
> >>>>> seems
> >>>>>>>>>>>> not to get a lot of support? Not sure why... I personally think
> >>>>> it would
> >>>>>>>>>>>> be good to take it into account, and I also think that Chia-Ping
> >>>>> raises
> >>>>>>>>>>>> a very good point.
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
> >>>>> it. I
> >>>>>>>>>>>> did actually briefly think about it, but it's difficult, and
> >>>>> thus I just
> >>>>>>>>>>>> started with something simple as proposal to kick off a
> >>>>> discussion.
> >>>>>>>>>>>>
> >>>>>>>>>>>> I think, Diwali is short enough to not make it a concern
> >>>>> (similar to
> >>>>>>>>>>>> Thanksgiving)?
> >>>>>>>>>>>>
> >>>>>>>>>>>> For Lunar New Year, I agree that it would be good to plan for it.
> >>>>>>>>>>>> However, it seems it's shifting quite a lot year-over-year what
> >>>>> makes it
> >>>>>>>>>>>> very difficult (w/o a huge window) to include?
> >>>>>>>>>>>>
> >>>>>>>>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
> >>>>> (this
> >>>>>>>>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
> >>>>> month
> >>>>>>>>>>>> releases does not sound very appealing?
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>> I was playing with it a little bit more. Overall we have 52
> >>>>> weeks, so
> >>>>>>>>>>>> roughly 17.3 weeks per release. So we can naturally split it into
> >>>>>>>>>>>> 17/17/18 using the additional week for the holidays. But that's
> >>>>> not good
> >>>>>>>>>>>> enough to take both Christmas and Lunar New Year into account.
> >>>>> However,
> >>>>>>>>>>>> with a 16/16/20, we could make it work I believe, even if it
> >>>>> does cut it
> >>>>>>>>>>>> tight sometimes... To be able to phrase a "simple rule", we can
> >>>>> use ISO
> >>>>>>>>>>>> weeks:
> >>>>>>>>>>>>
> >>>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
> >>>>> freeze
> >>>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
> >>>>>>>>>>>>
> >>>>>>>>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
> >>>>> for most
> >>>>>>>>>>>> years:
> >>>>>>>>>>>>
> >>>>>>>>>>>>>
> >>>>>
> >>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> >>>>>>>>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
> >>>>> Buffer │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
> >>>>> tightest with realistic LNY │
> >>>>>>>>>>>>>
> >>>>>
> >>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
> >>>>> │
> >>>>>>>>>>>>>
> >>>>>
> >>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> >>>>>>>>>>>>
> >>>>>>>>>>>> Guess, we could also make it week-8 instead of 9, and accept
> >>>>> that 2034
> >>>>>>>>>>>> would cut it too short (or be even more flexible and keep week-9
> >>>>> for
> >>>>>>>>>>>> 2034 as an exception to the rule), but that's a single year...
> >>>>> for 2029
> >>>>>>>>>>>> and 2032 we still have one week buffer.
> >>>>>>>>>>>>
> >>>>>>>>>>>> For Christmas, we would still ensure that the release can go out
> >>>>> on
> >>>>>>>>>>>> time, too. The below Q3 target release date is 4 weeks after code
> >>>>>>>>>>>> freeze. This is a little bit more tight, as we often need more
> >>>>> than 4
> >>>>>>>>>>>> weeks to get it done:
> >>>>>>>>>>>>
> >>>>>>>>>>>>> ┌──────┬──────────────────────────┬────────────────┐
> >>>>>>>>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2026 │ Dec 9 │ 16 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2027 │ Dec 15 │ 10 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2028 │ Dec 13 │ 12 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2029 │ Dec 12 │ 13 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2030 │ Dec 11 │ 14 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2031 │ Dec 10 │ 15 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2032 │ Dec 8 │ 17 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2033 │ Dec 14 │ 11 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2034 │ Dec 13 │ 12 │
> >>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>>>>> │ 2035 │ Dec 12 │ 13 │
> >>>>>>>>>>>>> └──────┴──────────────────────────┴────────────────┘
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>> For some years, we would still cut it a little bit tight, but we
> >>>>> could
> >>>>>>>>>>>> also apply an exception to the rule, to compensate for it. If we
> >>>>> have
> >>>>>>>>>>>> enough buffer room from LYN, we can start the Q1 release train a
> >>>>> week
> >>>>>>>>>>>> earlier, reducing the Q3->Q1 timeline by one week.
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>> Curious to hear what people think about it. In the end, if we
> >>>>> can agree
> >>>>>>>>>>>> on high level rules like "start Q1 release with X buffer after
> >>>>> LYN", and
> >>>>>>>>>>>> "complete Q3 release with Y buffer before Christmas", and still
> >>>>> aim for
> >>>>>>>>>>>> an as balance week-allocation per release, we can just put
> >>>>> together a
> >>>>>>>>>>>> release plan for the next 10 years and be done with it.
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>> -Matthias
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> >>>>>>>>>>>>> Hello,
> >>>>>>>>>>>>>
> >>>>>>>>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
> >>>>> release
> >>>>>>>>>>>>> coincided with a reasonable amount of holidays, so I would
> >>>>> favour a
> >>>>>>>>>>>>> 3+2 schedule with releases in March, July and November.
> >>>>>>>>>>>>>
> >>>>>>>>>>>>> Best,
> >>>>>>>>>>>>> Christo
> >>>>>>>>>>>>>
> >>>>>>>>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
> >>>>> wrote:
> >>>>>>>>>>>>>>
> >>>>>>>>>>>>>> Hi,
> >>>>>>>>>>>>>>
> >>>>>>>>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
> >>>>> schofielaj@apache.org>
> >>>>>>>>>>>>>> wrote:
> >>>>>>>>>>>>>>
> >>>>>>>>>>>>>>> I would go for 3 releases of equal lengths in March, July and
> >>>>> November. I
> >>>>>>>>>>>>>>> favour the 3+2 schedule.
> >>>>>>>>>>>>>>>
> >>>>>>>>>>>>>>
> >>>>>>>>>>>>>> +1
> >>>>>>>>>>>>>>
> >>>>>>>>>>>>>> Thanks,
> >>>>>>>>>>>>>> Ismael
> >>>>>>>>>>>>
> >>>>>>>>>>>>
> >>>>>>>>
> >>>>>>>
> >>>>>>
> >>>>>
> >>>
> >>>
> >>
>
>
Re: [DISCUSS] Tightening time-based releases
Posted by "Matthias J. Sax" <mj...@apache.org>.
Thanks Andrew.
I see that you did keep Jan/13 for KIP freeze, and did not pull it
forward. LGTM.
> but I think it's very hard to be concrete about 4.6.0 at this point.
Is it? In the end, if we say we want to follow the long-term proposed
timeline in general, we are looking into the following dates:
Proposed KIP-freeze dates for 2027
Release-1: March/3 (week 9)
Relasee-2: June/23 (week 25)
Release-3: Oct/13 (week 41)
So there is two options:
(1) We keep March/3, and do 4 release in 2027. Personally, I don't
think this make a lot of sense. With the Jan/13 KIP freeze for AK 4.5
the cycle for AK 4.6 would be way too short IMHO.
(2) We treat the AK 4.5 release as release-1, ie, pull forward the
March/13 date to Jan/13, and follow with release-2 in June/23 as
planned. -- Here we would still have some wiggle room: release-1 is 7
weeks earlier than the proposed schedule, so it would make sense to pull
forward release-2, too. If we keep June/23 for release-2, we would have
23 weeks for AK 4.6 release, and only 16 weeks for release-3. It might
be better to even it out and move release-2 forward by 3 week to have 20
weeks for AK 4.6, and 19 weeks for AK 4.7 with Oct/13 KIP freeze date as
originally proposed.
I would propose to go with option-2 and doing AK 4.6 with KIP freeze
Jun/2 (ie, 3 weeks earlier than the proposed long-term schedule).
-Matthias
On 10/12/26 3:17 AM, Andrew Schofield wrote:
> Hi,
> I have gone ahead with the 4.5.0 schedule as listed, but I think it's very
> hard to be concrete about 4.6.0 at this point.
>
> Thanks,
> Andrew
>
> On 2026/10/10 20:33:35 Muralidhar Basani via dev wrote:
>> Hi all,
>>
>> I'm not deeply involved in release management, so please take this as just
>> some data in case it's useful for the 4.5/4.6 discussion.
>>
>> I compared the planned dates on the wiki release plans with what actually
>> happened in git for the last five releases:
>>
>> Version Planned Feat Freeze Branch cut Planned target Released
>> Late RCs
>> 4.0.0 2024-12-11 2024-12-16 2025-01-29
>> 2025-03-18 48d 5
>> 4.1.0 2025-06-04 2025-06-10 2025-07-09
>> 2025-09-02 55d 4
>> 4.2.0 2025-11-19 2025-11-21 2026-01-07
>> 2026-02-16 40d 5
>> 4.3.0 2026-03-18 2026-03-18 2026-05-06
>> 2026-05-20 14d 3
>> 4.4.0 2026-07-29 2026-07-27 2026-09-09
>> 2026-10-12* 33d 5
>> (* expected)
>>
>> Feature freeze is usually on time; the time between code freeze and the
>> release is where we tend to need more than planned (median ~40 days after
>> the target). With the current 4.5.0 plan, that would put the 4.5.0 release
>> around late April 2027, which may be worth keeping in mind when choosing
>> the 4.6.0 dates.
>>
>> I put the small script in this PR, in case it's helpful for future
>> planning: https://github.com/apache/kafka/pull/23769
>> Added sample runs in the PR.
>> If this is not the direction we want, happy to close it.
>>
>>
>> Here is a short snippet from the scripts run
>>
>> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
>>
>> % python3 release/schedule.py
>> ....
>> ....
>> version KIP freeze derived from feature freeze code freeze
>> first RC target release realistic release
>> ------- ---------- ----------------- --------------
>> ----------- ---------- --------------
>> -----------------
>> 4.5.0 2027-01-13 wiki release plan 2027-02-03 2027-02-17
>> 2027-03-16 2027-03-17 2027-04-28
>> 4.6.0 2027-05-19 history 2027-06-09 2027-06-23
>> 2027-07-20 2027-07-21 2027-09-01
>> 4.7.0 2027-09-22 history 2027-10-13 2027-10-27
>> 2027-11-23 2027-11-24 2028-01-05
>> ...
>>
>> %python3 release/schedule.py --release-date 4.4.0=2026-10-12 status 4.6.0
>> ....
>> ....
>> Release 4.6.0 as of 2026-10-10 (dates: history)
>> KIP freeze 2027-05-19 (in 221 days)
>> feature freeze 2027-06-09 (in 242 days)
>> code freeze 2027-06-23 (in 256 days)
>> first RC 2027-07-20 (in 283 days)
>> target release 2027-07-21 (in 284 days)
>> realistic release 2027-09-01 (in 326 days)
>> ...
>> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
>>
>>
>> Thanks,
>> Murali
>>
>> On Sat, Oct 10, 2026 at 3:33 PM Matthias J. Sax <mj...@apache.org> wrote:
>>
>>> What's you rational for doing 4.6 in March already? If we so 4.5
>>> early/mid January, it would be a very small release. Given the overhead
>>> releases have, I am wondering if it would be worth doing?
>>>
>>> For 4.5, I am also ok to start a Jan/6 instead of Jan/13 with KIP
>>> freeze. If we do 4.6 in July (instead of March) I don't see a need to
>>> pull it forward by one a week though. But I am fine in any case.
>>>
>>> -Matthias
>>>
>>> On 9/28/26 11:49 PM, Dejan Stojadinović wrote:
>>>>> "Anyway, all I want to say is that the original schedule was hard to
>>>> follow. The codebase is large and CVEs are common these days."
>>>>
>>>> As an occasional contributor I can confirm this.
>>>> From my POV committers/maintainers are having a challenging task to keep
>>>> up, especially while trying to juggle around with multiple release
>>>> branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
>>>>
>>>> Best regards,
>>>> Dejan S.
>>>> https://github.com/dejan2609
>>>>
>>>>
>>>> On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org>
>>> wrote:
>>>>
>>>>> Hi Andrew,
>>>>>
>>>>> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
>>>>> since that puts the KIP freeze right after the holidays.
>>>>>
>>>>> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
>>>>> reaches code freeze. We had too many must-have changes in 4.4.0, which
>>>>> caused a serious delay. I try to review all backports but my tokens are
>>>>> limited :)
>>>>>
>>>>> Anyway, all I want to say is that the original schedule was hard to
>>>>> follow. The codebase is large and CVEs are common these days.
>>>>>
>>>>> Best,
>>>>> Chia-Ping
>>>>>
>>>>>
>>>>> On 2026/09/25 08:36:23 Andrew Schofield wrote:
>>>>>> Hi,
>>>>>> I'm starting to look at the release schedule for 4.5.0.
>>>>>>
>>>>>> In Chia-Ping's table from 29 May 2026, we have:
>>>>>>
>>>>>> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
>>>>>> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19,
>>> 2026
>>>>>> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
>>>>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
>>>>>>
>>>>>> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
>>>>> freeze of Jan 13, 2027 which gives this.
>>>>>>
>>>>>> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon
>>> now
>>>>>> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17,
>>> 2027
>>>>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
>>>>>>
>>>>>> I think we could even pull 4.5.0 a week earlier than that, but I don't
>>>>> think there's anything fundamentally wrong with a short 4.6.0 provided
>>>>> people know in advance.
>>>>>>
>>>>>> Are people happy with the 4.5.0 (revised) dates above? Would a week
>>>>> earlier be better given that it gives an extra week to 4.6.0 which is
>>>>> looking very squeezed?
>>>>>>
>>>>>> Thanks,
>>>>>> Andrew
>>>>>>
>>>>>> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
>>>>>>> Hi all,
>>>>>>>
>>>>>>> +1 to the 4.5 schedule, given the delay of 4.4.0.
>>>>>>>
>>>>>>> I think having 4.5 land right on Lunar New Year should be fine this
>>>>> time, since "too close" is the real issue here.
>>>>>>>
>>>>>>> Best,
>>>>>>> Chia-Ping
>>>>>>>
>>>>>>>> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
>>>>>>>>
>>>>>>>> I don't think we have for 4.5... I believe that there was a slight,
>>>>> high level agreement for the long term, that we want to follow the
>>>>> "calendar week proposal"?
>>>>>>>>
>>>>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
>>>>> feature freeze
>>>>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
>>>>>>>>
>>>>>>>> AK 4.4 KIP freeze was Jul/8.
>>>>>>>>
>>>>>>>> For 2026, week 41 would be Oct/7 which is way too close IMHO.
>>>>>>>> For 2027, week 9 would be Mar/3 which seems to be too far out?
>>>>>>>>
>>>>>>>> Second release (week 25) for 2027 would be Jun/23, which would be
>>>>> 4.6?
>>>>>>>>
>>>>>>>> So the question remains, where to put 4.5 so we can start to follow
>>>>> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
>>>>> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
>>>>> freeze dates. Of course, the release would overlap with Chinese New
>>> Year,
>>>>> but it would be the last time we have this overlap.
>>>>>>>>
>>>>>>>> Just my 2tc.
>>>>>>>>
>>>>>>>>
>>>>>>>> -Matthias
>>>>>>>>
>>>>>>>>> On 9/15/26 8:17 AM, David Jacot wrote:
>>>>>>>>> Hi all,
>>>>>>>>> Have we converged on the schedule that we want to use yet? Based on
>>>>>>>>> the last emails, it is not so clear to me. For your context, I am
>>>>>>>>> trying to figure out the timeline for 4.5.
>>>>>>>>> Best,
>>>>>>>>> David
>>>>>>>>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
>>>>> christololov@gmail.com> wrote:
>>>>>>>>>>
>>>>>>>>>> I think we could be a bit more lax with the KIP freeze of 6.7.0
>>>>> when
>>>>>>>>>> 2034 comes around to account for LNY :)
>>>>>>>>>>
>>>>>>>>>> Joking aside, my preference between "KIP freeze would be
>>>>> Wednesday's,
>>>>>>>>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
>>>>>>>>>> weeks" and "start Q1 release with X buffer after LYN and complete
>>>>> Q3
>>>>>>>>>> release with Y buffer before Christmas" would be to start with the
>>>>>>>>>> first and adjust by shifting by 1 week on individual basis the ones
>>>>>>>>>> which are too close. I am okay with too close being defined as 2
>>>>>>>>>> weeks. Based on your very detailed tables we seem to have only a
>>>>> few
>>>>>>>>>> such outliers in the next decade.
>>>>>>>>>>
>>>>>>>>>> Best,
>>>>>>>>>> Christo
>>>>>>>>>>
>>>>>>>>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
>>>>> wrote:
>>>>>>>>>>>
>>>>>>>>>>> Matthias, you are definitely a master of scheduling! I'm +100 to
>>>>> your plans.
>>>>>>>>>>>
>>>>>>>>>>> Also, it is absolutely helpful to write down the exact release
>>>>> dates for the next few years at once. It will ease our anxiety a lot!
>>> I'd
>>>>> be more than happy to update the wiki with these dates once we all
>>> agree on
>>>>> this new schedule. For example:
>>>>>>>>>>>
>>>>>>>>>>> Version KIP Freeze Feature Freeze Code Freeze Target
>>>>> Release
>>>>>>>>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
>>>>> 2026
>>>>>>>>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
>>>>> 2026
>>>>>>>>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
>>>>> 2027
>>>>>>>>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
>>>>> 2027
>>>>>>>>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
>>>>> 2027
>>>>>>>>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
>>>>> 2028
>>>>>>>>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
>>>>> 2028
>>>>>>>>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
>>>>> 2028
>>>>>>>>>>>
>>>>>>>>>>> Furthermore, let's do our best to avoid fixing release blockers
>>>>> under the Christmas tree :)
>>>>>>>>>>>
>>>>>>>>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
>>>>>>>>>>>> Thanks for the input.
>>>>>>>>>>>>
>>>>>>>>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
>>>>>>>>>>>> windows gets a lot of support.
>>>>>>>>>>>>
>>>>>>>>>>>> However, the idea of dividing the release windows not into 3
>>>>> equally
>>>>>>>>>>>> long junks, but be more flexible to account for holiday seasons,
>>>>> seems
>>>>>>>>>>>> not to get a lot of support? Not sure why... I personally think
>>>>> it would
>>>>>>>>>>>> be good to take it into account, and I also think that Chia-Ping
>>>>> raises
>>>>>>>>>>>> a very good point.
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
>>>>> it. I
>>>>>>>>>>>> did actually briefly think about it, but it's difficult, and
>>>>> thus I just
>>>>>>>>>>>> started with something simple as proposal to kick off a
>>>>> discussion.
>>>>>>>>>>>>
>>>>>>>>>>>> I think, Diwali is short enough to not make it a concern
>>>>> (similar to
>>>>>>>>>>>> Thanksgiving)?
>>>>>>>>>>>>
>>>>>>>>>>>> For Lunar New Year, I agree that it would be good to plan for it.
>>>>>>>>>>>> However, it seems it's shifting quite a lot year-over-year what
>>>>> makes it
>>>>>>>>>>>> very difficult (w/o a huge window) to include?
>>>>>>>>>>>>
>>>>>>>>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
>>>>> (this
>>>>>>>>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
>>>>> month
>>>>>>>>>>>> releases does not sound very appealing?
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>> I was playing with it a little bit more. Overall we have 52
>>>>> weeks, so
>>>>>>>>>>>> roughly 17.3 weeks per release. So we can naturally split it into
>>>>>>>>>>>> 17/17/18 using the additional week for the holidays. But that's
>>>>> not good
>>>>>>>>>>>> enough to take both Christmas and Lunar New Year into account.
>>>>> However,
>>>>>>>>>>>> with a 16/16/20, we could make it work I believe, even if it
>>>>> does cut it
>>>>>>>>>>>> tight sometimes... To be able to phrase a "simple rule", we can
>>>>> use ISO
>>>>>>>>>>>> weeks:
>>>>>>>>>>>>
>>>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
>>>>> freeze
>>>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
>>>>>>>>>>>>
>>>>>>>>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
>>>>> for most
>>>>>>>>>>>> years:
>>>>>>>>>>>>
>>>>>>>>>>>>>
>>>>>
>>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
>>>>>>>>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
>>>>> Buffer │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
>>>>> tightest with realistic LNY │
>>>>>>>>>>>>>
>>>>>
>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
>>>>> │
>>>>>>>>>>>>>
>>>>>
>>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
>>>>>>>>>>>>
>>>>>>>>>>>> Guess, we could also make it week-8 instead of 9, and accept
>>>>> that 2034
>>>>>>>>>>>> would cut it too short (or be even more flexible and keep week-9
>>>>> for
>>>>>>>>>>>> 2034 as an exception to the rule), but that's a single year...
>>>>> for 2029
>>>>>>>>>>>> and 2032 we still have one week buffer.
>>>>>>>>>>>>
>>>>>>>>>>>> For Christmas, we would still ensure that the release can go out
>>>>> on
>>>>>>>>>>>> time, too. The below Q3 target release date is 4 weeks after code
>>>>>>>>>>>> freeze. This is a little bit more tight, as we often need more
>>>>> than 4
>>>>>>>>>>>> weeks to get it done:
>>>>>>>>>>>>
>>>>>>>>>>>>> ┌──────┬──────────────────────────┬────────────────┐
>>>>>>>>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2026 │ Dec 9 │ 16 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2027 │ Dec 15 │ 10 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2028 │ Dec 13 │ 12 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2029 │ Dec 12 │ 13 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2030 │ Dec 11 │ 14 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2031 │ Dec 10 │ 15 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2032 │ Dec 8 │ 17 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2033 │ Dec 14 │ 11 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2034 │ Dec 13 │ 12 │
>>>>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>>>>> │ 2035 │ Dec 12 │ 13 │
>>>>>>>>>>>>> └──────┴──────────────────────────┴────────────────┘
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>> For some years, we would still cut it a little bit tight, but we
>>>>> could
>>>>>>>>>>>> also apply an exception to the rule, to compensate for it. If we
>>>>> have
>>>>>>>>>>>> enough buffer room from LYN, we can start the Q1 release train a
>>>>> week
>>>>>>>>>>>> earlier, reducing the Q3->Q1 timeline by one week.
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>> Curious to hear what people think about it. In the end, if we
>>>>> can agree
>>>>>>>>>>>> on high level rules like "start Q1 release with X buffer after
>>>>> LYN", and
>>>>>>>>>>>> "complete Q3 release with Y buffer before Christmas", and still
>>>>> aim for
>>>>>>>>>>>> an as balance week-allocation per release, we can just put
>>>>> together a
>>>>>>>>>>>> release plan for the next 10 years and be done with it.
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>> -Matthias
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
>>>>>>>>>>>>> Hello,
>>>>>>>>>>>>>
>>>>>>>>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
>>>>> release
>>>>>>>>>>>>> coincided with a reasonable amount of holidays, so I would
>>>>> favour a
>>>>>>>>>>>>> 3+2 schedule with releases in March, July and November.
>>>>>>>>>>>>>
>>>>>>>>>>>>> Best,
>>>>>>>>>>>>> Christo
>>>>>>>>>>>>>
>>>>>>>>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
>>>>> wrote:
>>>>>>>>>>>>>>
>>>>>>>>>>>>>> Hi,
>>>>>>>>>>>>>>
>>>>>>>>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
>>>>> schofielaj@apache.org>
>>>>>>>>>>>>>> wrote:
>>>>>>>>>>>>>>
>>>>>>>>>>>>>>> I would go for 3 releases of equal lengths in March, July and
>>>>> November. I
>>>>>>>>>>>>>>> favour the 3+2 schedule.
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>
>>>>>>>>>>>>>> +1
>>>>>>>>>>>>>>
>>>>>>>>>>>>>> Thanks,
>>>>>>>>>>>>>> Ismael
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>
>>>>>>>
>>>>>>
>>>>>
>>>
>>>
>>
Re: [DISCUSS] Tightening time-based releases
Posted by Andrew Schofield <sc...@apache.org>.
Hi,
I have gone ahead with the 4.5.0 schedule as listed, but I think it's very
hard to be concrete about 4.6.0 at this point.
Thanks,
Andrew
On 2026/10/10 20:33:35 Muralidhar Basani via dev wrote:
> Hi all,
>
> I'm not deeply involved in release management, so please take this as just
> some data in case it's useful for the 4.5/4.6 discussion.
>
> I compared the planned dates on the wiki release plans with what actually
> happened in git for the last five releases:
>
> Version Planned Feat Freeze Branch cut Planned target Released
> Late RCs
> 4.0.0 2024-12-11 2024-12-16 2025-01-29
> 2025-03-18 48d 5
> 4.1.0 2025-06-04 2025-06-10 2025-07-09
> 2025-09-02 55d 4
> 4.2.0 2025-11-19 2025-11-21 2026-01-07
> 2026-02-16 40d 5
> 4.3.0 2026-03-18 2026-03-18 2026-05-06
> 2026-05-20 14d 3
> 4.4.0 2026-07-29 2026-07-27 2026-09-09
> 2026-10-12* 33d 5
> (* expected)
>
> Feature freeze is usually on time; the time between code freeze and the
> release is where we tend to need more than planned (median ~40 days after
> the target). With the current 4.5.0 plan, that would put the 4.5.0 release
> around late April 2027, which may be worth keeping in mind when choosing
> the 4.6.0 dates.
>
> I put the small script in this PR, in case it's helpful for future
> planning: https://github.com/apache/kafka/pull/23769
> Added sample runs in the PR.
> If this is not the direction we want, happy to close it.
>
>
> Here is a short snippet from the scripts run
>
> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
>
> % python3 release/schedule.py
> ....
> ....
> version KIP freeze derived from feature freeze code freeze
> first RC target release realistic release
> ------- ---------- ----------------- --------------
> ----------- ---------- --------------
> -----------------
> 4.5.0 2027-01-13 wiki release plan 2027-02-03 2027-02-17
> 2027-03-16 2027-03-17 2027-04-28
> 4.6.0 2027-05-19 history 2027-06-09 2027-06-23
> 2027-07-20 2027-07-21 2027-09-01
> 4.7.0 2027-09-22 history 2027-10-13 2027-10-27
> 2027-11-23 2027-11-24 2028-01-05
> ...
>
> %python3 release/schedule.py --release-date 4.4.0=2026-10-12 status 4.6.0
> ....
> ....
> Release 4.6.0 as of 2026-10-10 (dates: history)
> KIP freeze 2027-05-19 (in 221 days)
> feature freeze 2027-06-09 (in 242 days)
> code freeze 2027-06-23 (in 256 days)
> first RC 2027-07-20 (in 283 days)
> target release 2027-07-21 (in 284 days)
> realistic release 2027-09-01 (in 326 days)
> ...
> ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
>
>
> Thanks,
> Murali
>
> On Sat, Oct 10, 2026 at 3:33 PM Matthias J. Sax <mj...@apache.org> wrote:
>
> > What's you rational for doing 4.6 in March already? If we so 4.5
> > early/mid January, it would be a very small release. Given the overhead
> > releases have, I am wondering if it would be worth doing?
> >
> > For 4.5, I am also ok to start a Jan/6 instead of Jan/13 with KIP
> > freeze. If we do 4.6 in July (instead of March) I don't see a need to
> > pull it forward by one a week though. But I am fine in any case.
> >
> > -Matthias
> >
> > On 9/28/26 11:49 PM, Dejan Stojadinović wrote:
> > >> "Anyway, all I want to say is that the original schedule was hard to
> > > follow. The codebase is large and CVEs are common these days."
> > >
> > > As an occasional contributor I can confirm this.
> > > From my POV committers/maintainers are having a challenging task to keep
> > > up, especially while trying to juggle around with multiple release
> > > branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
> > >
> > > Best regards,
> > > Dejan S.
> > > https://github.com/dejan2609
> > >
> > >
> > > On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org>
> > wrote:
> > >
> > >> Hi Andrew,
> > >>
> > >> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
> > >> since that puts the KIP freeze right after the holidays.
> > >>
> > >> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
> > >> reaches code freeze. We had too many must-have changes in 4.4.0, which
> > >> caused a serious delay. I try to review all backports but my tokens are
> > >> limited :)
> > >>
> > >> Anyway, all I want to say is that the original schedule was hard to
> > >> follow. The codebase is large and CVEs are common these days.
> > >>
> > >> Best,
> > >> Chia-Ping
> > >>
> > >>
> > >> On 2026/09/25 08:36:23 Andrew Schofield wrote:
> > >>> Hi,
> > >>> I'm starting to look at the release schedule for 4.5.0.
> > >>>
> > >>> In Chia-Ping's table from 29 May 2026, we have:
> > >>>
> > >>> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
> > >>> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19,
> > 2026
> > >>> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
> > >>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> > >>>
> > >>> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
> > >> freeze of Jan 13, 2027 which gives this.
> > >>>
> > >>> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon
> > now
> > >>> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17,
> > 2027
> > >>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> > >>>
> > >>> I think we could even pull 4.5.0 a week earlier than that, but I don't
> > >> think there's anything fundamentally wrong with a short 4.6.0 provided
> > >> people know in advance.
> > >>>
> > >>> Are people happy with the 4.5.0 (revised) dates above? Would a week
> > >> earlier be better given that it gives an extra week to 4.6.0 which is
> > >> looking very squeezed?
> > >>>
> > >>> Thanks,
> > >>> Andrew
> > >>>
> > >>> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> > >>>> Hi all,
> > >>>>
> > >>>> +1 to the 4.5 schedule, given the delay of 4.4.0.
> > >>>>
> > >>>> I think having 4.5 land right on Lunar New Year should be fine this
> > >> time, since "too close" is the real issue here.
> > >>>>
> > >>>> Best,
> > >>>> Chia-Ping
> > >>>>
> > >>>>> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> > >>>>>
> > >>>>> I don't think we have for 4.5... I believe that there was a slight,
> > >> high level agreement for the long term, that we want to follow the
> > >> "calendar week proposal"?
> > >>>>>
> > >>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
> > >> feature freeze
> > >>>>>>>>>> +3 weeks, and code freeze +2 weeks.
> > >>>>>
> > >>>>> AK 4.4 KIP freeze was Jul/8.
> > >>>>>
> > >>>>> For 2026, week 41 would be Oct/7 which is way too close IMHO.
> > >>>>> For 2027, week 9 would be Mar/3 which seems to be too far out?
> > >>>>>
> > >>>>> Second release (week 25) for 2027 would be Jun/23, which would be
> > >> 4.6?
> > >>>>>
> > >>>>> So the question remains, where to put 4.5 so we can start to follow
> > >> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
> > >> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
> > >> freeze dates. Of course, the release would overlap with Chinese New
> > Year,
> > >> but it would be the last time we have this overlap.
> > >>>>>
> > >>>>> Just my 2tc.
> > >>>>>
> > >>>>>
> > >>>>> -Matthias
> > >>>>>
> > >>>>>> On 9/15/26 8:17 AM, David Jacot wrote:
> > >>>>>> Hi all,
> > >>>>>> Have we converged on the schedule that we want to use yet? Based on
> > >>>>>> the last emails, it is not so clear to me. For your context, I am
> > >>>>>> trying to figure out the timeline for 4.5.
> > >>>>>> Best,
> > >>>>>> David
> > >>>>>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
> > >> christololov@gmail.com> wrote:
> > >>>>>>>
> > >>>>>>> I think we could be a bit more lax with the KIP freeze of 6.7.0
> > >> when
> > >>>>>>> 2034 comes around to account for LNY :)
> > >>>>>>>
> > >>>>>>> Joking aside, my preference between "KIP freeze would be
> > >> Wednesday's,
> > >>>>>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> > >>>>>>> weeks" and "start Q1 release with X buffer after LYN and complete
> > >> Q3
> > >>>>>>> release with Y buffer before Christmas" would be to start with the
> > >>>>>>> first and adjust by shifting by 1 week on individual basis the ones
> > >>>>>>> which are too close. I am okay with too close being defined as 2
> > >>>>>>> weeks. Based on your very detailed tables we seem to have only a
> > >> few
> > >>>>>>> such outliers in the next decade.
> > >>>>>>>
> > >>>>>>> Best,
> > >>>>>>> Christo
> > >>>>>>>
> > >>>>>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
> > >> wrote:
> > >>>>>>>>
> > >>>>>>>> Matthias, you are definitely a master of scheduling! I'm +100 to
> > >> your plans.
> > >>>>>>>>
> > >>>>>>>> Also, it is absolutely helpful to write down the exact release
> > >> dates for the next few years at once. It will ease our anxiety a lot!
> > I'd
> > >> be more than happy to update the wiki with these dates once we all
> > agree on
> > >> this new schedule. For example:
> > >>>>>>>>
> > >>>>>>>> Version KIP Freeze Feature Freeze Code Freeze Target
> > >> Release
> > >>>>>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
> > >> 2026
> > >>>>>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
> > >> 2026
> > >>>>>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
> > >> 2027
> > >>>>>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
> > >> 2027
> > >>>>>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
> > >> 2027
> > >>>>>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
> > >> 2028
> > >>>>>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
> > >> 2028
> > >>>>>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
> > >> 2028
> > >>>>>>>>
> > >>>>>>>> Furthermore, let's do our best to avoid fixing release blockers
> > >> under the Christmas tree :)
> > >>>>>>>>
> > >>>>>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> > >>>>>>>>> Thanks for the input.
> > >>>>>>>>>
> > >>>>>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> > >>>>>>>>> windows gets a lot of support.
> > >>>>>>>>>
> > >>>>>>>>> However, the idea of dividing the release windows not into 3
> > >> equally
> > >>>>>>>>> long junks, but be more flexible to account for holiday seasons,
> > >> seems
> > >>>>>>>>> not to get a lot of support? Not sure why... I personally think
> > >> it would
> > >>>>>>>>> be good to take it into account, and I also think that Chia-Ping
> > >> raises
> > >>>>>>>>> a very good point.
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
> > >> it. I
> > >>>>>>>>> did actually briefly think about it, but it's difficult, and
> > >> thus I just
> > >>>>>>>>> started with something simple as proposal to kick off a
> > >> discussion.
> > >>>>>>>>>
> > >>>>>>>>> I think, Diwali is short enough to not make it a concern
> > >> (similar to
> > >>>>>>>>> Thanksgiving)?
> > >>>>>>>>>
> > >>>>>>>>> For Lunar New Year, I agree that it would be good to plan for it.
> > >>>>>>>>> However, it seems it's shifting quite a lot year-over-year what
> > >> makes it
> > >>>>>>>>> very difficult (w/o a huge window) to include?
> > >>>>>>>>>
> > >>>>>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
> > >> (this
> > >>>>>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
> > >> month
> > >>>>>>>>> releases does not sound very appealing?
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>> I was playing with it a little bit more. Overall we have 52
> > >> weeks, so
> > >>>>>>>>> roughly 17.3 weeks per release. So we can naturally split it into
> > >>>>>>>>> 17/17/18 using the additional week for the holidays. But that's
> > >> not good
> > >>>>>>>>> enough to take both Christmas and Lunar New Year into account.
> > >> However,
> > >>>>>>>>> with a 16/16/20, we could make it work I believe, even if it
> > >> does cut it
> > >>>>>>>>> tight sometimes... To be able to phrase a "simple rule", we can
> > >> use ISO
> > >>>>>>>>> weeks:
> > >>>>>>>>>
> > >>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
> > >> freeze
> > >>>>>>>>> +3 weeks, and code freeze +2 weeks.
> > >>>>>>>>>
> > >>>>>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
> > >> for most
> > >>>>>>>>> years:
> > >>>>>>>>>
> > >>>>>>>>>>
> > >>
> > ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > >>>>>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
> > >> Buffer │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
> > >> │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
> > >> tightest with realistic LNY │
> > >>>>>>>>>>
> > >>
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
> > >> │
> > >>>>>>>>>>
> > >>
> > └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> > >>>>>>>>>
> > >>>>>>>>> Guess, we could also make it week-8 instead of 9, and accept
> > >> that 2034
> > >>>>>>>>> would cut it too short (or be even more flexible and keep week-9
> > >> for
> > >>>>>>>>> 2034 as an exception to the rule), but that's a single year...
> > >> for 2029
> > >>>>>>>>> and 2032 we still have one week buffer.
> > >>>>>>>>>
> > >>>>>>>>> For Christmas, we would still ensure that the release can go out
> > >> on
> > >>>>>>>>> time, too. The below Q3 target release date is 4 weeks after code
> > >>>>>>>>> freeze. This is a little bit more tight, as we often need more
> > >> than 4
> > >>>>>>>>> weeks to get it done:
> > >>>>>>>>>
> > >>>>>>>>>> ┌──────┬──────────────────────────┬────────────────┐
> > >>>>>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2026 │ Dec 9 │ 16 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2027 │ Dec 15 │ 10 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2028 │ Dec 13 │ 12 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2029 │ Dec 12 │ 13 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2030 │ Dec 11 │ 14 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2031 │ Dec 10 │ 15 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2032 │ Dec 8 │ 17 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2033 │ Dec 14 │ 11 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2034 │ Dec 13 │ 12 │
> > >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>>>>>> │ 2035 │ Dec 12 │ 13 │
> > >>>>>>>>>> └──────┴──────────────────────────┴────────────────┘
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>> For some years, we would still cut it a little bit tight, but we
> > >> could
> > >>>>>>>>> also apply an exception to the rule, to compensate for it. If we
> > >> have
> > >>>>>>>>> enough buffer room from LYN, we can start the Q1 release train a
> > >> week
> > >>>>>>>>> earlier, reducing the Q3->Q1 timeline by one week.
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>> Curious to hear what people think about it. In the end, if we
> > >> can agree
> > >>>>>>>>> on high level rules like "start Q1 release with X buffer after
> > >> LYN", and
> > >>>>>>>>> "complete Q3 release with Y buffer before Christmas", and still
> > >> aim for
> > >>>>>>>>> an as balance week-allocation per release, we can just put
> > >> together a
> > >>>>>>>>> release plan for the next 10 years and be done with it.
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>> -Matthias
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> > >>>>>>>>>> Hello,
> > >>>>>>>>>>
> > >>>>>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
> > >> release
> > >>>>>>>>>> coincided with a reasonable amount of holidays, so I would
> > >> favour a
> > >>>>>>>>>> 3+2 schedule with releases in March, July and November.
> > >>>>>>>>>>
> > >>>>>>>>>> Best,
> > >>>>>>>>>> Christo
> > >>>>>>>>>>
> > >>>>>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
> > >> wrote:
> > >>>>>>>>>>>
> > >>>>>>>>>>> Hi,
> > >>>>>>>>>>>
> > >>>>>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
> > >> schofielaj@apache.org>
> > >>>>>>>>>>> wrote:
> > >>>>>>>>>>>
> > >>>>>>>>>>>> I would go for 3 releases of equal lengths in March, July and
> > >> November. I
> > >>>>>>>>>>>> favour the 3+2 schedule.
> > >>>>>>>>>>>>
> > >>>>>>>>>>>
> > >>>>>>>>>>> +1
> > >>>>>>>>>>>
> > >>>>>>>>>>> Thanks,
> > >>>>>>>>>>> Ismael
> > >>>>>>>>>
> > >>>>>>>>>
> > >>>>>
> > >>>>
> > >>>
> > >>
> >
> >
>
Re: [DISCUSS] Tightening time-based releases
Posted by Muralidhar Basani via dev <de...@kafka.apache.org>.
Hi all,
I'm not deeply involved in release management, so please take this as just
some data in case it's useful for the 4.5/4.6 discussion.
I compared the planned dates on the wiki release plans with what actually
happened in git for the last five releases:
Version Planned Feat Freeze Branch cut Planned target Released
Late RCs
4.0.0 2024-12-11 2024-12-16 2025-01-29
2025-03-18 48d 5
4.1.0 2025-06-04 2025-06-10 2025-07-09
2025-09-02 55d 4
4.2.0 2025-11-19 2025-11-21 2026-01-07
2026-02-16 40d 5
4.3.0 2026-03-18 2026-03-18 2026-05-06
2026-05-20 14d 3
4.4.0 2026-07-29 2026-07-27 2026-09-09
2026-10-12* 33d 5
(* expected)
Feature freeze is usually on time; the time between code freeze and the
release is where we tend to need more than planned (median ~40 days after
the target). With the current 4.5.0 plan, that would put the 4.5.0 release
around late April 2027, which may be worth keeping in mind when choosing
the 4.6.0 dates.
I put the small script in this PR, in case it's helpful for future
planning: https://github.com/apache/kafka/pull/23769
Added sample runs in the PR.
If this is not the direction we want, happy to close it.
Here is a short snippet from the scripts run
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
% python3 release/schedule.py
....
....
version KIP freeze derived from feature freeze code freeze
first RC target release realistic release
------- ---------- ----------------- --------------
----------- ---------- --------------
-----------------
4.5.0 2027-01-13 wiki release plan 2027-02-03 2027-02-17
2027-03-16 2027-03-17 2027-04-28
4.6.0 2027-05-19 history 2027-06-09 2027-06-23
2027-07-20 2027-07-21 2027-09-01
4.7.0 2027-09-22 history 2027-10-13 2027-10-27
2027-11-23 2027-11-24 2028-01-05
...
%python3 release/schedule.py --release-date 4.4.0=2026-10-12 status 4.6.0
....
....
Release 4.6.0 as of 2026-10-10 (dates: history)
KIP freeze 2027-05-19 (in 221 days)
feature freeze 2027-06-09 (in 242 days)
code freeze 2027-06-23 (in 256 days)
first RC 2027-07-20 (in 283 days)
target release 2027-07-21 (in 284 days)
realistic release 2027-09-01 (in 326 days)
...
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Thanks,
Murali
On Sat, Oct 10, 2026 at 3:33 PM Matthias J. Sax <mj...@apache.org> wrote:
> What's you rational for doing 4.6 in March already? If we so 4.5
> early/mid January, it would be a very small release. Given the overhead
> releases have, I am wondering if it would be worth doing?
>
> For 4.5, I am also ok to start a Jan/6 instead of Jan/13 with KIP
> freeze. If we do 4.6 in July (instead of March) I don't see a need to
> pull it forward by one a week though. But I am fine in any case.
>
> -Matthias
>
> On 9/28/26 11:49 PM, Dejan Stojadinović wrote:
> >> "Anyway, all I want to say is that the original schedule was hard to
> > follow. The codebase is large and CVEs are common these days."
> >
> > As an occasional contributor I can confirm this.
> > From my POV committers/maintainers are having a challenging task to keep
> > up, especially while trying to juggle around with multiple release
> > branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
> >
> > Best regards,
> > Dejan S.
> > https://github.com/dejan2609
> >
> >
> > On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org>
> wrote:
> >
> >> Hi Andrew,
> >>
> >> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
> >> since that puts the KIP freeze right after the holidays.
> >>
> >> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
> >> reaches code freeze. We had too many must-have changes in 4.4.0, which
> >> caused a serious delay. I try to review all backports but my tokens are
> >> limited :)
> >>
> >> Anyway, all I want to say is that the original schedule was hard to
> >> follow. The codebase is large and CVEs are common these days.
> >>
> >> Best,
> >> Chia-Ping
> >>
> >>
> >> On 2026/09/25 08:36:23 Andrew Schofield wrote:
> >>> Hi,
> >>> I'm starting to look at the release schedule for 4.5.0.
> >>>
> >>> In Chia-Ping's table from 29 May 2026, we have:
> >>>
> >>> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
> >>> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19,
> 2026
> >>> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
> >>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> >>>
> >>> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
> >> freeze of Jan 13, 2027 which gives this.
> >>>
> >>> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon
> now
> >>> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17,
> 2027
> >>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> >>>
> >>> I think we could even pull 4.5.0 a week earlier than that, but I don't
> >> think there's anything fundamentally wrong with a short 4.6.0 provided
> >> people know in advance.
> >>>
> >>> Are people happy with the 4.5.0 (revised) dates above? Would a week
> >> earlier be better given that it gives an extra week to 4.6.0 which is
> >> looking very squeezed?
> >>>
> >>> Thanks,
> >>> Andrew
> >>>
> >>> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> >>>> Hi all,
> >>>>
> >>>> +1 to the 4.5 schedule, given the delay of 4.4.0.
> >>>>
> >>>> I think having 4.5 land right on Lunar New Year should be fine this
> >> time, since "too close" is the real issue here.
> >>>>
> >>>> Best,
> >>>> Chia-Ping
> >>>>
> >>>>> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> >>>>>
> >>>>> I don't think we have for 4.5... I believe that there was a slight,
> >> high level agreement for the long term, that we want to follow the
> >> "calendar week proposal"?
> >>>>>
> >>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
> >> feature freeze
> >>>>>>>>>> +3 weeks, and code freeze +2 weeks.
> >>>>>
> >>>>> AK 4.4 KIP freeze was Jul/8.
> >>>>>
> >>>>> For 2026, week 41 would be Oct/7 which is way too close IMHO.
> >>>>> For 2027, week 9 would be Mar/3 which seems to be too far out?
> >>>>>
> >>>>> Second release (week 25) for 2027 would be Jun/23, which would be
> >> 4.6?
> >>>>>
> >>>>> So the question remains, where to put 4.5 so we can start to follow
> >> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
> >> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
> >> freeze dates. Of course, the release would overlap with Chinese New
> Year,
> >> but it would be the last time we have this overlap.
> >>>>>
> >>>>> Just my 2tc.
> >>>>>
> >>>>>
> >>>>> -Matthias
> >>>>>
> >>>>>> On 9/15/26 8:17 AM, David Jacot wrote:
> >>>>>> Hi all,
> >>>>>> Have we converged on the schedule that we want to use yet? Based on
> >>>>>> the last emails, it is not so clear to me. For your context, I am
> >>>>>> trying to figure out the timeline for 4.5.
> >>>>>> Best,
> >>>>>> David
> >>>>>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
> >> christololov@gmail.com> wrote:
> >>>>>>>
> >>>>>>> I think we could be a bit more lax with the KIP freeze of 6.7.0
> >> when
> >>>>>>> 2034 comes around to account for LNY :)
> >>>>>>>
> >>>>>>> Joking aside, my preference between "KIP freeze would be
> >> Wednesday's,
> >>>>>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> >>>>>>> weeks" and "start Q1 release with X buffer after LYN and complete
> >> Q3
> >>>>>>> release with Y buffer before Christmas" would be to start with the
> >>>>>>> first and adjust by shifting by 1 week on individual basis the ones
> >>>>>>> which are too close. I am okay with too close being defined as 2
> >>>>>>> weeks. Based on your very detailed tables we seem to have only a
> >> few
> >>>>>>> such outliers in the next decade.
> >>>>>>>
> >>>>>>> Best,
> >>>>>>> Christo
> >>>>>>>
> >>>>>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
> >> wrote:
> >>>>>>>>
> >>>>>>>> Matthias, you are definitely a master of scheduling! I'm +100 to
> >> your plans.
> >>>>>>>>
> >>>>>>>> Also, it is absolutely helpful to write down the exact release
> >> dates for the next few years at once. It will ease our anxiety a lot!
> I'd
> >> be more than happy to update the wiki with these dates once we all
> agree on
> >> this new schedule. For example:
> >>>>>>>>
> >>>>>>>> Version KIP Freeze Feature Freeze Code Freeze Target
> >> Release
> >>>>>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
> >> 2026
> >>>>>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
> >> 2026
> >>>>>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
> >> 2027
> >>>>>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
> >> 2027
> >>>>>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
> >> 2027
> >>>>>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
> >> 2028
> >>>>>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
> >> 2028
> >>>>>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
> >> 2028
> >>>>>>>>
> >>>>>>>> Furthermore, let's do our best to avoid fixing release blockers
> >> under the Christmas tree :)
> >>>>>>>>
> >>>>>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> >>>>>>>>> Thanks for the input.
> >>>>>>>>>
> >>>>>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> >>>>>>>>> windows gets a lot of support.
> >>>>>>>>>
> >>>>>>>>> However, the idea of dividing the release windows not into 3
> >> equally
> >>>>>>>>> long junks, but be more flexible to account for holiday seasons,
> >> seems
> >>>>>>>>> not to get a lot of support? Not sure why... I personally think
> >> it would
> >>>>>>>>> be good to take it into account, and I also think that Chia-Ping
> >> raises
> >>>>>>>>> a very good point.
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
> >> it. I
> >>>>>>>>> did actually briefly think about it, but it's difficult, and
> >> thus I just
> >>>>>>>>> started with something simple as proposal to kick off a
> >> discussion.
> >>>>>>>>>
> >>>>>>>>> I think, Diwali is short enough to not make it a concern
> >> (similar to
> >>>>>>>>> Thanksgiving)?
> >>>>>>>>>
> >>>>>>>>> For Lunar New Year, I agree that it would be good to plan for it.
> >>>>>>>>> However, it seems it's shifting quite a lot year-over-year what
> >> makes it
> >>>>>>>>> very difficult (w/o a huge window) to include?
> >>>>>>>>>
> >>>>>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
> >> (this
> >>>>>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
> >> month
> >>>>>>>>> releases does not sound very appealing?
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>> I was playing with it a little bit more. Overall we have 52
> >> weeks, so
> >>>>>>>>> roughly 17.3 weeks per release. So we can naturally split it into
> >>>>>>>>> 17/17/18 using the additional week for the holidays. But that's
> >> not good
> >>>>>>>>> enough to take both Christmas and Lunar New Year into account.
> >> However,
> >>>>>>>>> with a 16/16/20, we could make it work I believe, even if it
> >> does cut it
> >>>>>>>>> tight sometimes... To be able to phrase a "simple rule", we can
> >> use ISO
> >>>>>>>>> weeks:
> >>>>>>>>>
> >>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
> >> freeze
> >>>>>>>>> +3 weeks, and code freeze +2 weeks.
> >>>>>>>>>
> >>>>>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
> >> for most
> >>>>>>>>> years:
> >>>>>>>>>
> >>>>>>>>>>
> >>
> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> >>>>>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
> >> Buffer │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
> >> │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
> >> tightest with realistic LNY │
> >>>>>>>>>>
> >>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
> >> │
> >>>>>>>>>>
> >>
> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> >>>>>>>>>
> >>>>>>>>> Guess, we could also make it week-8 instead of 9, and accept
> >> that 2034
> >>>>>>>>> would cut it too short (or be even more flexible and keep week-9
> >> for
> >>>>>>>>> 2034 as an exception to the rule), but that's a single year...
> >> for 2029
> >>>>>>>>> and 2032 we still have one week buffer.
> >>>>>>>>>
> >>>>>>>>> For Christmas, we would still ensure that the release can go out
> >> on
> >>>>>>>>> time, too. The below Q3 target release date is 4 weeks after code
> >>>>>>>>> freeze. This is a little bit more tight, as we often need more
> >> than 4
> >>>>>>>>> weeks to get it done:
> >>>>>>>>>
> >>>>>>>>>> ┌──────┬──────────────────────────┬────────────────┐
> >>>>>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2026 │ Dec 9 │ 16 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2027 │ Dec 15 │ 10 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2028 │ Dec 13 │ 12 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2029 │ Dec 12 │ 13 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2030 │ Dec 11 │ 14 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2031 │ Dec 10 │ 15 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2032 │ Dec 8 │ 17 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2033 │ Dec 14 │ 11 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2034 │ Dec 13 │ 12 │
> >>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>>>>>> │ 2035 │ Dec 12 │ 13 │
> >>>>>>>>>> └──────┴──────────────────────────┴────────────────┘
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>> For some years, we would still cut it a little bit tight, but we
> >> could
> >>>>>>>>> also apply an exception to the rule, to compensate for it. If we
> >> have
> >>>>>>>>> enough buffer room from LYN, we can start the Q1 release train a
> >> week
> >>>>>>>>> earlier, reducing the Q3->Q1 timeline by one week.
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>> Curious to hear what people think about it. In the end, if we
> >> can agree
> >>>>>>>>> on high level rules like "start Q1 release with X buffer after
> >> LYN", and
> >>>>>>>>> "complete Q3 release with Y buffer before Christmas", and still
> >> aim for
> >>>>>>>>> an as balance week-allocation per release, we can just put
> >> together a
> >>>>>>>>> release plan for the next 10 years and be done with it.
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>> -Matthias
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>>
> >>>>>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> >>>>>>>>>> Hello,
> >>>>>>>>>>
> >>>>>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
> >> release
> >>>>>>>>>> coincided with a reasonable amount of holidays, so I would
> >> favour a
> >>>>>>>>>> 3+2 schedule with releases in March, July and November.
> >>>>>>>>>>
> >>>>>>>>>> Best,
> >>>>>>>>>> Christo
> >>>>>>>>>>
> >>>>>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
> >> wrote:
> >>>>>>>>>>>
> >>>>>>>>>>> Hi,
> >>>>>>>>>>>
> >>>>>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
> >> schofielaj@apache.org>
> >>>>>>>>>>> wrote:
> >>>>>>>>>>>
> >>>>>>>>>>>> I would go for 3 releases of equal lengths in March, July and
> >> November. I
> >>>>>>>>>>>> favour the 3+2 schedule.
> >>>>>>>>>>>>
> >>>>>>>>>>>
> >>>>>>>>>>> +1
> >>>>>>>>>>>
> >>>>>>>>>>> Thanks,
> >>>>>>>>>>> Ismael
> >>>>>>>>>
> >>>>>>>>>
> >>>>>
> >>>>
> >>>
> >>
>
>
Re: [DISCUSS] Tightening time-based releases
Posted by "Matthias J. Sax" <mj...@apache.org>.
What's you rational for doing 4.6 in March already? If we so 4.5
early/mid January, it would be a very small release. Given the overhead
releases have, I am wondering if it would be worth doing?
For 4.5, I am also ok to start a Jan/6 instead of Jan/13 with KIP
freeze. If we do 4.6 in July (instead of March) I don't see a need to
pull it forward by one a week though. But I am fine in any case.
-Matthias
On 9/28/26 11:49 PM, Dejan Stojadinović wrote:
>> "Anyway, all I want to say is that the original schedule was hard to
> follow. The codebase is large and CVEs are common these days."
>
> As an occasional contributor I can confirm this.
> From my POV committers/maintainers are having a challenging task to keep
> up, especially while trying to juggle around with multiple release
> branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
>
> Best regards,
> Dejan S.
> https://github.com/dejan2609
>
>
> On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org> wrote:
>
>> Hi Andrew,
>>
>> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
>> since that puts the KIP freeze right after the holidays.
>>
>> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
>> reaches code freeze. We had too many must-have changes in 4.4.0, which
>> caused a serious delay. I try to review all backports but my tokens are
>> limited :)
>>
>> Anyway, all I want to say is that the original schedule was hard to
>> follow. The codebase is large and CVEs are common these days.
>>
>> Best,
>> Chia-Ping
>>
>>
>> On 2026/09/25 08:36:23 Andrew Schofield wrote:
>>> Hi,
>>> I'm starting to look at the release schedule for 4.5.0.
>>>
>>> In Chia-Ping's table from 29 May 2026, we have:
>>>
>>> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
>>> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19, 2026
>>> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
>>>
>>> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
>> freeze of Jan 13, 2027 which gives this.
>>>
>>> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon now
>>> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17, 2027
>>> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
>>>
>>> I think we could even pull 4.5.0 a week earlier than that, but I don't
>> think there's anything fundamentally wrong with a short 4.6.0 provided
>> people know in advance.
>>>
>>> Are people happy with the 4.5.0 (revised) dates above? Would a week
>> earlier be better given that it gives an extra week to 4.6.0 which is
>> looking very squeezed?
>>>
>>> Thanks,
>>> Andrew
>>>
>>> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
>>>> Hi all,
>>>>
>>>> +1 to the 4.5 schedule, given the delay of 4.4.0.
>>>>
>>>> I think having 4.5 land right on Lunar New Year should be fine this
>> time, since "too close" is the real issue here.
>>>>
>>>> Best,
>>>> Chia-Ping
>>>>
>>>>> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
>>>>>
>>>>> I don't think we have for 4.5... I believe that there was a slight,
>> high level agreement for the long term, that we want to follow the
>> "calendar week proposal"?
>>>>>
>>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
>> feature freeze
>>>>>>>>>> +3 weeks, and code freeze +2 weeks.
>>>>>
>>>>> AK 4.4 KIP freeze was Jul/8.
>>>>>
>>>>> For 2026, week 41 would be Oct/7 which is way too close IMHO.
>>>>> For 2027, week 9 would be Mar/3 which seems to be too far out?
>>>>>
>>>>> Second release (week 25) for 2027 would be Jun/23, which would be
>> 4.6?
>>>>>
>>>>> So the question remains, where to put 4.5 so we can start to follow
>> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
>> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
>> freeze dates. Of course, the release would overlap with Chinese New Year,
>> but it would be the last time we have this overlap.
>>>>>
>>>>> Just my 2tc.
>>>>>
>>>>>
>>>>> -Matthias
>>>>>
>>>>>> On 9/15/26 8:17 AM, David Jacot wrote:
>>>>>> Hi all,
>>>>>> Have we converged on the schedule that we want to use yet? Based on
>>>>>> the last emails, it is not so clear to me. For your context, I am
>>>>>> trying to figure out the timeline for 4.5.
>>>>>> Best,
>>>>>> David
>>>>>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
>> christololov@gmail.com> wrote:
>>>>>>>
>>>>>>> I think we could be a bit more lax with the KIP freeze of 6.7.0
>> when
>>>>>>> 2034 comes around to account for LNY :)
>>>>>>>
>>>>>>> Joking aside, my preference between "KIP freeze would be
>> Wednesday's,
>>>>>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
>>>>>>> weeks" and "start Q1 release with X buffer after LYN and complete
>> Q3
>>>>>>> release with Y buffer before Christmas" would be to start with the
>>>>>>> first and adjust by shifting by 1 week on individual basis the ones
>>>>>>> which are too close. I am okay with too close being defined as 2
>>>>>>> weeks. Based on your very detailed tables we seem to have only a
>> few
>>>>>>> such outliers in the next decade.
>>>>>>>
>>>>>>> Best,
>>>>>>> Christo
>>>>>>>
>>>>>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
>> wrote:
>>>>>>>>
>>>>>>>> Matthias, you are definitely a master of scheduling! I'm +100 to
>> your plans.
>>>>>>>>
>>>>>>>> Also, it is absolutely helpful to write down the exact release
>> dates for the next few years at once. It will ease our anxiety a lot! I'd
>> be more than happy to update the wiki with these dates once we all agree on
>> this new schedule. For example:
>>>>>>>>
>>>>>>>> Version KIP Freeze Feature Freeze Code Freeze Target
>> Release
>>>>>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
>> 2026
>>>>>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
>> 2026
>>>>>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
>> 2027
>>>>>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
>> 2027
>>>>>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
>> 2027
>>>>>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
>> 2028
>>>>>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
>> 2028
>>>>>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
>> 2028
>>>>>>>>
>>>>>>>> Furthermore, let's do our best to avoid fixing release blockers
>> under the Christmas tree :)
>>>>>>>>
>>>>>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
>>>>>>>>> Thanks for the input.
>>>>>>>>>
>>>>>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
>>>>>>>>> windows gets a lot of support.
>>>>>>>>>
>>>>>>>>> However, the idea of dividing the release windows not into 3
>> equally
>>>>>>>>> long junks, but be more flexible to account for holiday seasons,
>> seems
>>>>>>>>> not to get a lot of support? Not sure why... I personally think
>> it would
>>>>>>>>> be good to take it into account, and I also think that Chia-Ping
>> raises
>>>>>>>>> a very good point.
>>>>>>>>>
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
>> it. I
>>>>>>>>> did actually briefly think about it, but it's difficult, and
>> thus I just
>>>>>>>>> started with something simple as proposal to kick off a
>> discussion.
>>>>>>>>>
>>>>>>>>> I think, Diwali is short enough to not make it a concern
>> (similar to
>>>>>>>>> Thanksgiving)?
>>>>>>>>>
>>>>>>>>> For Lunar New Year, I agree that it would be good to plan for it.
>>>>>>>>> However, it seems it's shifting quite a lot year-over-year what
>> makes it
>>>>>>>>> very difficult (w/o a huge window) to include?
>>>>>>>>>
>>>>>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
>> (this
>>>>>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
>> month
>>>>>>>>> releases does not sound very appealing?
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> I was playing with it a little bit more. Overall we have 52
>> weeks, so
>>>>>>>>> roughly 17.3 weeks per release. So we can naturally split it into
>>>>>>>>> 17/17/18 using the additional week for the holidays. But that's
>> not good
>>>>>>>>> enough to take both Christmas and Lunar New Year into account.
>> However,
>>>>>>>>> with a 16/16/20, we could make it work I believe, even if it
>> does cut it
>>>>>>>>> tight sometimes... To be able to phrase a "simple rule", we can
>> use ISO
>>>>>>>>> weeks:
>>>>>>>>>
>>>>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
>> freeze
>>>>>>>>> +3 weeks, and code freeze +2 weeks.
>>>>>>>>>
>>>>>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
>> for most
>>>>>>>>> years:
>>>>>>>>>
>>>>>>>>>>
>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
>>>>>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
>> Buffer │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
>> │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
>> tightest with realistic LNY │
>>>>>>>>>>
>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
>> │
>>>>>>>>>>
>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
>>>>>>>>>
>>>>>>>>> Guess, we could also make it week-8 instead of 9, and accept
>> that 2034
>>>>>>>>> would cut it too short (or be even more flexible and keep week-9
>> for
>>>>>>>>> 2034 as an exception to the rule), but that's a single year...
>> for 2029
>>>>>>>>> and 2032 we still have one week buffer.
>>>>>>>>>
>>>>>>>>> For Christmas, we would still ensure that the release can go out
>> on
>>>>>>>>> time, too. The below Q3 target release date is 4 weeks after code
>>>>>>>>> freeze. This is a little bit more tight, as we often need more
>> than 4
>>>>>>>>> weeks to get it done:
>>>>>>>>>
>>>>>>>>>> ┌──────┬──────────────────────────┬────────────────┐
>>>>>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2026 │ Dec 9 │ 16 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2027 │ Dec 15 │ 10 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2028 │ Dec 13 │ 12 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2029 │ Dec 12 │ 13 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2030 │ Dec 11 │ 14 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2031 │ Dec 10 │ 15 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2032 │ Dec 8 │ 17 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2033 │ Dec 14 │ 11 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2034 │ Dec 13 │ 12 │
>>>>>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>>>>>> │ 2035 │ Dec 12 │ 13 │
>>>>>>>>>> └──────┴──────────────────────────┴────────────────┘
>>>>>>>>>
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> For some years, we would still cut it a little bit tight, but we
>> could
>>>>>>>>> also apply an exception to the rule, to compensate for it. If we
>> have
>>>>>>>>> enough buffer room from LYN, we can start the Q1 release train a
>> week
>>>>>>>>> earlier, reducing the Q3->Q1 timeline by one week.
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> Curious to hear what people think about it. In the end, if we
>> can agree
>>>>>>>>> on high level rules like "start Q1 release with X buffer after
>> LYN", and
>>>>>>>>> "complete Q3 release with Y buffer before Christmas", and still
>> aim for
>>>>>>>>> an as balance week-allocation per release, we can just put
>> together a
>>>>>>>>> release plan for the next 10 years and be done with it.
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> -Matthias
>>>>>>>>>
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
>>>>>>>>>> Hello,
>>>>>>>>>>
>>>>>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
>> release
>>>>>>>>>> coincided with a reasonable amount of holidays, so I would
>> favour a
>>>>>>>>>> 3+2 schedule with releases in March, July and November.
>>>>>>>>>>
>>>>>>>>>> Best,
>>>>>>>>>> Christo
>>>>>>>>>>
>>>>>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
>> wrote:
>>>>>>>>>>>
>>>>>>>>>>> Hi,
>>>>>>>>>>>
>>>>>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
>> schofielaj@apache.org>
>>>>>>>>>>> wrote:
>>>>>>>>>>>
>>>>>>>>>>>> I would go for 3 releases of equal lengths in March, July and
>> November. I
>>>>>>>>>>>> favour the 3+2 schedule.
>>>>>>>>>>>>
>>>>>>>>>>>
>>>>>>>>>>> +1
>>>>>>>>>>>
>>>>>>>>>>> Thanks,
>>>>>>>>>>> Ismael
>>>>>>>>>
>>>>>>>>>
>>>>>
>>>>
>>>
>>
Re: [DISCUSS] Tightening time-based releases
Posted by Dejan Stojadinović <de...@gmail.com>.
> "Anyway, all I want to say is that the original schedule was hard to
follow. The codebase is large and CVEs are common these days."
As an occasional contributor I can confirm this.
From my POV committers/maintainers are having a challenging task to keep
up, especially while trying to juggle around with multiple release
branches/versions (trunk/4.5.0, 4.4.0, 4.3.2, 4.2.2).
Best regards,
Dejan S.
https://github.com/dejan2609
On Tue, Sep 29, 2026 at 7:55 AM Chia-Ping Tsai <ch...@apache.org> wrote:
> Hi Andrew,
>
> +1 to the revised 4.5.0 schedule. I would not pull it a week earlier,
> since that puts the KIP freeze right after the holidays.
>
> Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0
> reaches code freeze. We had too many must-have changes in 4.4.0, which
> caused a serious delay. I try to review all backports but my tokens are
> limited :)
>
> Anyway, all I want to say is that the original schedule was hard to
> follow. The codebase is large and CVEs are common these days.
>
> Best,
> Chia-Ping
>
>
> On 2026/09/25 08:36:23 Andrew Schofield wrote:
> > Hi,
> > I'm starting to look at the release schedule for 4.5.0.
> >
> > In Chia-Ping's table from 29 May 2026, we have:
> >
> > Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
> > 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19, 2026
> > 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
> > 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> >
> > In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP
> freeze of Jan 13, 2027 which gives this.
> >
> > 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon now
> > 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17, 2027
> > 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
> >
> > I think we could even pull 4.5.0 a week earlier than that, but I don't
> think there's anything fundamentally wrong with a short 4.6.0 provided
> people know in advance.
> >
> > Are people happy with the 4.5.0 (revised) dates above? Would a week
> earlier be better given that it gives an extra week to 4.6.0 which is
> looking very squeezed?
> >
> > Thanks,
> > Andrew
> >
> > On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> > > Hi all,
> > >
> > > +1 to the 4.5 schedule, given the delay of 4.4.0.
> > >
> > > I think having 4.5 land right on Lunar New Year should be fine this
> time, since "too close" is the real issue here.
> > >
> > > Best,
> > > Chia-Ping
> > >
> > > > Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> > > >
> > > > I don't think we have for 4.5... I believe that there was a slight,
> high level agreement for the long term, that we want to follow the
> "calendar week proposal"?
> > > >
> > > >>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with
> feature freeze
> > > >>>>>> +3 weeks, and code freeze +2 weeks.
> > > >
> > > > AK 4.4 KIP freeze was Jul/8.
> > > >
> > > > For 2026, week 41 would be Oct/7 which is way too close IMHO.
> > > > For 2027, week 9 would be Mar/3 which seems to be too far out?
> > > >
> > > > Second release (week 25) for 2027 would be Jun/23, which would be
> 4.6?
> > > >
> > > > So the question remains, where to put 4.5 so we can start to follow
> the new schedule starting with 4.6. It seems KIP freeze between Jan 13
> might be a good compromise putting it roughly between 4.4 and 4.6 KIP
> freeze dates. Of course, the release would overlap with Chinese New Year,
> but it would be the last time we have this overlap.
> > > >
> > > > Just my 2tc.
> > > >
> > > >
> > > > -Matthias
> > > >
> > > >> On 9/15/26 8:17 AM, David Jacot wrote:
> > > >> Hi all,
> > > >> Have we converged on the schedule that we want to use yet? Based on
> > > >> the last emails, it is not so clear to me. For your context, I am
> > > >> trying to figure out the timeline for 4.5.
> > > >> Best,
> > > >> David
> > > >>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <
> christololov@gmail.com> wrote:
> > > >>>
> > > >>> I think we could be a bit more lax with the KIP freeze of 6.7.0
> when
> > > >>> 2034 comes around to account for LNY :)
> > > >>>
> > > >>> Joking aside, my preference between "KIP freeze would be
> Wednesday's,
> > > >>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> > > >>> weeks" and "start Q1 release with X buffer after LYN and complete
> Q3
> > > >>> release with Y buffer before Christmas" would be to start with the
> > > >>> first and adjust by shifting by 1 week on individual basis the ones
> > > >>> which are too close. I am okay with too close being defined as 2
> > > >>> weeks. Based on your very detailed tables we seem to have only a
> few
> > > >>> such outliers in the next decade.
> > > >>>
> > > >>> Best,
> > > >>> Christo
> > > >>>
> > > >>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org>
> wrote:
> > > >>>>
> > > >>>> Matthias, you are definitely a master of scheduling! I'm +100 to
> your plans.
> > > >>>>
> > > >>>> Also, it is absolutely helpful to write down the exact release
> dates for the next few years at once. It will ease our anxiety a lot! I'd
> be more than happy to update the wiki with these dates once we all agree on
> this new schedule. For example:
> > > >>>>
> > > >>>> Version KIP Freeze Feature Freeze Code Freeze Target
> Release
> > > >>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19,
> 2026
> > > >>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9,
> 2026
> > > >>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5,
> 2027
> > > >>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25,
> 2027
> > > >>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15,
> 2027
> > > >>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3,
> 2028
> > > >>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23,
> 2028
> > > >>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13,
> 2028
> > > >>>>
> > > >>>> Furthermore, let's do our best to avoid fixing release blockers
> under the Christmas tree :)
> > > >>>>
> > > >>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> > > >>>>> Thanks for the input.
> > > >>>>>
> > > >>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> > > >>>>> windows gets a lot of support.
> > > >>>>>
> > > >>>>> However, the idea of dividing the release windows not into 3
> equally
> > > >>>>> long junks, but be more flexible to account for holiday seasons,
> seems
> > > >>>>> not to get a lot of support? Not sure why... I personally think
> it would
> > > >>>>> be good to take it into account, and I also think that Chia-Ping
> raises
> > > >>>>> a very good point.
> > > >>>>>
> > > >>>>>
> > > >>>>>
> > > >>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising
> it. I
> > > >>>>> did actually briefly think about it, but it's difficult, and
> thus I just
> > > >>>>> started with something simple as proposal to kick off a
> discussion.
> > > >>>>>
> > > >>>>> I think, Diwali is short enough to not make it a concern
> (similar to
> > > >>>>> Thanksgiving)?
> > > >>>>>
> > > >>>>> For Lunar New Year, I agree that it would be good to plan for it.
> > > >>>>> However, it seems it's shifting quite a lot year-over-year what
> makes it
> > > >>>>> very difficult (w/o a huge window) to include?
> > > >>>>>
> > > >>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced
> (this
> > > >>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5
> month
> > > >>>>> releases does not sound very appealing?
> > > >>>>>
> > > >>>>>
> > > >>>>> I was playing with it a little bit more. Overall we have 52
> weeks, so
> > > >>>>> roughly 17.3 weeks per release. So we can naturally split it into
> > > >>>>> 17/17/18 using the additional week for the holidays. But that's
> not good
> > > >>>>> enough to take both Christmas and Lunar New Year into account.
> However,
> > > >>>>> with a 16/16/20, we could make it work I believe, even if it
> does cut it
> > > >>>>> tight sometimes... To be able to phrase a "simple rule", we can
> use ISO
> > > >>>>> weeks:
> > > >>>>>
> > > >>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature
> freeze
> > > >>>>> +3 weeks, and code freeze +2 weeks.
> > > >>>>>
> > > >>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer
> for most
> > > >>>>> years:
> > > >>>>>
> > > >>>>>>
> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > > >>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │
> Buffer │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days
> │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ←
> tightest with realistic LNY │
> > > >>>>>>
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > >>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days
> │
> > > >>>>>>
> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> > > >>>>>
> > > >>>>> Guess, we could also make it week-8 instead of 9, and accept
> that 2034
> > > >>>>> would cut it too short (or be even more flexible and keep week-9
> for
> > > >>>>> 2034 as an exception to the rule), but that's a single year...
> for 2029
> > > >>>>> and 2032 we still have one week buffer.
> > > >>>>>
> > > >>>>> For Christmas, we would still ensure that the release can go out
> on
> > > >>>>> time, too. The below Q3 target release date is 4 weeks after code
> > > >>>>> freeze. This is a little bit more tight, as we often need more
> than 4
> > > >>>>> weeks to get it done:
> > > >>>>>
> > > >>>>>> ┌──────┬──────────────────────────┬────────────────┐
> > > >>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2026 │ Dec 9 │ 16 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2027 │ Dec 15 │ 10 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2028 │ Dec 13 │ 12 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2029 │ Dec 12 │ 13 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2030 │ Dec 11 │ 14 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2031 │ Dec 10 │ 15 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2032 │ Dec 8 │ 17 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2033 │ Dec 14 │ 11 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2034 │ Dec 13 │ 12 │
> > > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > > >>>>>> │ 2035 │ Dec 12 │ 13 │
> > > >>>>>> └──────┴──────────────────────────┴────────────────┘
> > > >>>>>
> > > >>>>>
> > > >>>>>
> > > >>>>> For some years, we would still cut it a little bit tight, but we
> could
> > > >>>>> also apply an exception to the rule, to compensate for it. If we
> have
> > > >>>>> enough buffer room from LYN, we can start the Q1 release train a
> week
> > > >>>>> earlier, reducing the Q3->Q1 timeline by one week.
> > > >>>>>
> > > >>>>>
> > > >>>>> Curious to hear what people think about it. In the end, if we
> can agree
> > > >>>>> on high level rules like "start Q1 release with X buffer after
> LYN", and
> > > >>>>> "complete Q3 release with Y buffer before Christmas", and still
> aim for
> > > >>>>> an as balance week-allocation per release, we can just put
> together a
> > > >>>>> release plan for the next 10 years and be done with it.
> > > >>>>>
> > > >>>>>
> > > >>>>> -Matthias
> > > >>>>>
> > > >>>>>
> > > >>>>>
> > > >>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> > > >>>>>> Hello,
> > > >>>>>>
> > > >>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's
> release
> > > >>>>>> coincided with a reasonable amount of holidays, so I would
> favour a
> > > >>>>>> 3+2 schedule with releases in March, July and November.
> > > >>>>>>
> > > >>>>>> Best,
> > > >>>>>> Christo
> > > >>>>>>
> > > >>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com>
> wrote:
> > > >>>>>>>
> > > >>>>>>> Hi,
> > > >>>>>>>
> > > >>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <
> schofielaj@apache.org>
> > > >>>>>>> wrote:
> > > >>>>>>>
> > > >>>>>>>> I would go for 3 releases of equal lengths in March, July and
> November. I
> > > >>>>>>>> favour the 3+2 schedule.
> > > >>>>>>>>
> > > >>>>>>>
> > > >>>>>>> +1
> > > >>>>>>>
> > > >>>>>>> Thanks,
> > > >>>>>>> Ismael
> > > >>>>>
> > > >>>>>
> > > >
> > >
> >
>
Re: [DISCUSS] Tightening time-based releases
Posted by Chia-Ping Tsai <ch...@apache.org>.
Hi Andrew,
+1 to the revised 4.5.0 schedule. I would not pull it a week earlier, since that puts the KIP freeze right after the holidays.
Regarding the 4.6.0 schedule, I think we could discuss it once 4.5.0 reaches code freeze. We had too many must-have changes in 4.4.0, which caused a serious delay. I try to review all backports but my tokens are limited :)
Anyway, all I want to say is that the original schedule was hard to follow. The codebase is large and CVEs are common these days.
Best,
Chia-Ping
On 2026/09/25 08:36:23 Andrew Schofield wrote:
> Hi,
> I'm starting to look at the release schedule for 4.5.0.
>
> In Chia-Ping's table from 29 May 2026, we have:
>
> Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
> 4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19, 2026
> 4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
>
> In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP freeze of Jan 13, 2027 which gives this.
>
> 4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon now
> 4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17, 2027
> 4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
>
> I think we could even pull 4.5.0 a week earlier than that, but I don't think there's anything fundamentally wrong with a short 4.6.0 provided people know in advance.
>
> Are people happy with the 4.5.0 (revised) dates above? Would a week earlier be better given that it gives an extra week to 4.6.0 which is looking very squeezed?
>
> Thanks,
> Andrew
>
> On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> > Hi all,
> >
> > +1 to the 4.5 schedule, given the delay of 4.4.0.
> >
> > I think having 4.5 land right on Lunar New Year should be fine this time, since "too close" is the real issue here.
> >
> > Best,
> > Chia-Ping
> >
> > > Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> > >
> > > I don't think we have for 4.5... I believe that there was a slight, high level agreement for the long term, that we want to follow the "calendar week proposal"?
> > >
> > >>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> > >>>>>> +3 weeks, and code freeze +2 weeks.
> > >
> > > AK 4.4 KIP freeze was Jul/8.
> > >
> > > For 2026, week 41 would be Oct/7 which is way too close IMHO.
> > > For 2027, week 9 would be Mar/3 which seems to be too far out?
> > >
> > > Second release (week 25) for 2027 would be Jun/23, which would be 4.6?
> > >
> > > So the question remains, where to put 4.5 so we can start to follow the new schedule starting with 4.6. It seems KIP freeze between Jan 13 might be a good compromise putting it roughly between 4.4 and 4.6 KIP freeze dates. Of course, the release would overlap with Chinese New Year, but it would be the last time we have this overlap.
> > >
> > > Just my 2tc.
> > >
> > >
> > > -Matthias
> > >
> > >> On 9/15/26 8:17 AM, David Jacot wrote:
> > >> Hi all,
> > >> Have we converged on the schedule that we want to use yet? Based on
> > >> the last emails, it is not so clear to me. For your context, I am
> > >> trying to figure out the timeline for 4.5.
> > >> Best,
> > >> David
> > >>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <ch...@gmail.com> wrote:
> > >>>
> > >>> I think we could be a bit more lax with the KIP freeze of 6.7.0 when
> > >>> 2034 comes around to account for LNY :)
> > >>>
> > >>> Joking aside, my preference between "KIP freeze would be Wednesday's,
> > >>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> > >>> weeks" and "start Q1 release with X buffer after LYN and complete Q3
> > >>> release with Y buffer before Christmas" would be to start with the
> > >>> first and adjust by shifting by 1 week on individual basis the ones
> > >>> which are too close. I am okay with too close being defined as 2
> > >>> weeks. Based on your very detailed tables we seem to have only a few
> > >>> such outliers in the next decade.
> > >>>
> > >>> Best,
> > >>> Christo
> > >>>
> > >>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org> wrote:
> > >>>>
> > >>>> Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
> > >>>>
> > >>>> Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
> > >>>>
> > >>>> Version KIP Freeze Feature Freeze Code Freeze Target Release
> > >>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
> > >>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
> > >>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
> > >>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
> > >>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
> > >>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
> > >>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
> > >>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
> > >>>>
> > >>>> Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
> > >>>>
> > >>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> > >>>>> Thanks for the input.
> > >>>>>
> > >>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> > >>>>> windows gets a lot of support.
> > >>>>>
> > >>>>> However, the idea of dividing the release windows not into 3 equally
> > >>>>> long junks, but be more flexible to account for holiday seasons, seems
> > >>>>> not to get a lot of support? Not sure why... I personally think it would
> > >>>>> be good to take it into account, and I also think that Chia-Ping raises
> > >>>>> a very good point.
> > >>>>>
> > >>>>>
> > >>>>>
> > >>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
> > >>>>> did actually briefly think about it, but it's difficult, and thus I just
> > >>>>> started with something simple as proposal to kick off a discussion.
> > >>>>>
> > >>>>> I think, Diwali is short enough to not make it a concern (similar to
> > >>>>> Thanksgiving)?
> > >>>>>
> > >>>>> For Lunar New Year, I agree that it would be good to plan for it.
> > >>>>> However, it seems it's shifting quite a lot year-over-year what makes it
> > >>>>> very difficult (w/o a huge window) to include?
> > >>>>>
> > >>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
> > >>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
> > >>>>> releases does not sound very appealing?
> > >>>>>
> > >>>>>
> > >>>>> I was playing with it a little bit more. Overall we have 52 weeks, so
> > >>>>> roughly 17.3 weeks per release. So we can naturally split it into
> > >>>>> 17/17/18 using the additional week for the holidays. But that's not good
> > >>>>> enough to take both Christmas and Lunar New Year into account. However,
> > >>>>> with a 16/16/20, we could make it work I believe, even if it does cut it
> > >>>>> tight sometimes... To be able to phrase a "simple rule", we can use ISO
> > >>>>> weeks:
> > >>>>>
> > >>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> > >>>>> +3 weeks, and code freeze +2 weeks.
> > >>>>>
> > >>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer for most
> > >>>>> years:
> > >>>>>
> > >>>>>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > >>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
> > >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > >>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
> > >>>>>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> > >>>>>
> > >>>>> Guess, we could also make it week-8 instead of 9, and accept that 2034
> > >>>>> would cut it too short (or be even more flexible and keep week-9 for
> > >>>>> 2034 as an exception to the rule), but that's a single year... for 2029
> > >>>>> and 2032 we still have one week buffer.
> > >>>>>
> > >>>>> For Christmas, we would still ensure that the release can go out on
> > >>>>> time, too. The below Q3 target release date is 4 weeks after code
> > >>>>> freeze. This is a little bit more tight, as we often need more than 4
> > >>>>> weeks to get it done:
> > >>>>>
> > >>>>>> ┌──────┬──────────────────────────┬────────────────┐
> > >>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2026 │ Dec 9 │ 16 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2027 │ Dec 15 │ 10 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2028 │ Dec 13 │ 12 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2029 │ Dec 12 │ 13 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2030 │ Dec 11 │ 14 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2031 │ Dec 10 │ 15 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2032 │ Dec 8 │ 17 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2033 │ Dec 14 │ 11 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2034 │ Dec 13 │ 12 │
> > >>>>>> ├──────┼──────────────────────────┼────────────────┤
> > >>>>>> │ 2035 │ Dec 12 │ 13 │
> > >>>>>> └──────┴──────────────────────────┴────────────────┘
> > >>>>>
> > >>>>>
> > >>>>>
> > >>>>> For some years, we would still cut it a little bit tight, but we could
> > >>>>> also apply an exception to the rule, to compensate for it. If we have
> > >>>>> enough buffer room from LYN, we can start the Q1 release train a week
> > >>>>> earlier, reducing the Q3->Q1 timeline by one week.
> > >>>>>
> > >>>>>
> > >>>>> Curious to hear what people think about it. In the end, if we can agree
> > >>>>> on high level rules like "start Q1 release with X buffer after LYN", and
> > >>>>> "complete Q3 release with Y buffer before Christmas", and still aim for
> > >>>>> an as balance week-allocation per release, we can just put together a
> > >>>>> release plan for the next 10 years and be done with it.
> > >>>>>
> > >>>>>
> > >>>>> -Matthias
> > >>>>>
> > >>>>>
> > >>>>>
> > >>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> > >>>>>> Hello,
> > >>>>>>
> > >>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's release
> > >>>>>> coincided with a reasonable amount of holidays, so I would favour a
> > >>>>>> 3+2 schedule with releases in March, July and November.
> > >>>>>>
> > >>>>>> Best,
> > >>>>>> Christo
> > >>>>>>
> > >>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
> > >>>>>>>
> > >>>>>>> Hi,
> > >>>>>>>
> > >>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
> > >>>>>>> wrote:
> > >>>>>>>
> > >>>>>>>> I would go for 3 releases of equal lengths in March, July and November. I
> > >>>>>>>> favour the 3+2 schedule.
> > >>>>>>>>
> > >>>>>>>
> > >>>>>>> +1
> > >>>>>>>
> > >>>>>>> Thanks,
> > >>>>>>> Ismael
> > >>>>>
> > >>>>>
> > >
> >
>
Re: [DISCUSS] Tightening time-based releases
Posted by Andrew Schofield <sc...@apache.org>.
Hi,
I'm starting to look at the release schedule for 4.5.0.
In Chia-Ping's table from 29 May 2026, we have:
Version : KIP Freeze : Feature Freeze : Code Freeze : Target Release
4.4.0 (planned) : Jun 17, 2026: Jul 8, 2026 : Jul 22, 2026 : Aug 19, 2026
4.5.0 : Oct 7, 2026 : Oct 28, 2026 : Nov 11, 2026 : Dec 9, 2026
4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
In reality, 4.4.0 ran 3 weeks later than this. Matthias suggested a KIP freeze of Jan 13, 2027 which gives this.
4.4.0 (actual) : Jul 8, 2026: Jul 29, 2026 : Aug 12, 2026 : Real soon now
4.5.0 (revised): Jan 13, 2027 : Feb 3, 2027 : Feb 17, 2027 : Mar 17, 2027
4.6.0 : Mar 3, 2027 : Mar 24, 2027 : Apr 7, 2027 : May 5, 2027
I think we could even pull 4.5.0 a week earlier than that, but I don't think there's anything fundamentally wrong with a short 4.6.0 provided people know in advance.
Are people happy with the 4.5.0 (revised) dates above? Would a week earlier be better given that it gives an extra week to 4.6.0 which is looking very squeezed?
Thanks,
Andrew
On 2026/09/16 04:01:41 Chia-Ping Tsai wrote:
> Hi all,
>
> +1 to the 4.5 schedule, given the delay of 4.4.0.
>
> I think having 4.5 land right on Lunar New Year should be fine this time, since "too close" is the real issue here.
>
> Best,
> Chia-Ping
>
> > Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
> >
> > I don't think we have for 4.5... I believe that there was a slight, high level agreement for the long term, that we want to follow the "calendar week proposal"?
> >
> >>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> >>>>>> +3 weeks, and code freeze +2 weeks.
> >
> > AK 4.4 KIP freeze was Jul/8.
> >
> > For 2026, week 41 would be Oct/7 which is way too close IMHO.
> > For 2027, week 9 would be Mar/3 which seems to be too far out?
> >
> > Second release (week 25) for 2027 would be Jun/23, which would be 4.6?
> >
> > So the question remains, where to put 4.5 so we can start to follow the new schedule starting with 4.6. It seems KIP freeze between Jan 13 might be a good compromise putting it roughly between 4.4 and 4.6 KIP freeze dates. Of course, the release would overlap with Chinese New Year, but it would be the last time we have this overlap.
> >
> > Just my 2tc.
> >
> >
> > -Matthias
> >
> >> On 9/15/26 8:17 AM, David Jacot wrote:
> >> Hi all,
> >> Have we converged on the schedule that we want to use yet? Based on
> >> the last emails, it is not so clear to me. For your context, I am
> >> trying to figure out the timeline for 4.5.
> >> Best,
> >> David
> >>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <ch...@gmail.com> wrote:
> >>>
> >>> I think we could be a bit more lax with the KIP freeze of 6.7.0 when
> >>> 2034 comes around to account for LNY :)
> >>>
> >>> Joking aside, my preference between "KIP freeze would be Wednesday's,
> >>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> >>> weeks" and "start Q1 release with X buffer after LYN and complete Q3
> >>> release with Y buffer before Christmas" would be to start with the
> >>> first and adjust by shifting by 1 week on individual basis the ones
> >>> which are too close. I am okay with too close being defined as 2
> >>> weeks. Based on your very detailed tables we seem to have only a few
> >>> such outliers in the next decade.
> >>>
> >>> Best,
> >>> Christo
> >>>
> >>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org> wrote:
> >>>>
> >>>> Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
> >>>>
> >>>> Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
> >>>>
> >>>> Version KIP Freeze Feature Freeze Code Freeze Target Release
> >>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
> >>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
> >>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
> >>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
> >>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
> >>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
> >>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
> >>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
> >>>>
> >>>> Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
> >>>>
> >>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> >>>>> Thanks for the input.
> >>>>>
> >>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> >>>>> windows gets a lot of support.
> >>>>>
> >>>>> However, the idea of dividing the release windows not into 3 equally
> >>>>> long junks, but be more flexible to account for holiday seasons, seems
> >>>>> not to get a lot of support? Not sure why... I personally think it would
> >>>>> be good to take it into account, and I also think that Chia-Ping raises
> >>>>> a very good point.
> >>>>>
> >>>>>
> >>>>>
> >>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
> >>>>> did actually briefly think about it, but it's difficult, and thus I just
> >>>>> started with something simple as proposal to kick off a discussion.
> >>>>>
> >>>>> I think, Diwali is short enough to not make it a concern (similar to
> >>>>> Thanksgiving)?
> >>>>>
> >>>>> For Lunar New Year, I agree that it would be good to plan for it.
> >>>>> However, it seems it's shifting quite a lot year-over-year what makes it
> >>>>> very difficult (w/o a huge window) to include?
> >>>>>
> >>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
> >>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
> >>>>> releases does not sound very appealing?
> >>>>>
> >>>>>
> >>>>> I was playing with it a little bit more. Overall we have 52 weeks, so
> >>>>> roughly 17.3 weeks per release. So we can naturally split it into
> >>>>> 17/17/18 using the additional week for the holidays. But that's not good
> >>>>> enough to take both Christmas and Lunar New Year into account. However,
> >>>>> with a 16/16/20, we could make it work I believe, even if it does cut it
> >>>>> tight sometimes... To be able to phrase a "simple rule", we can use ISO
> >>>>> weeks:
> >>>>>
> >>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> >>>>> +3 weeks, and code freeze +2 weeks.
> >>>>>
> >>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer for most
> >>>>> years:
> >>>>>
> >>>>>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> >>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
> >>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> >>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
> >>>>>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> >>>>>
> >>>>> Guess, we could also make it week-8 instead of 9, and accept that 2034
> >>>>> would cut it too short (or be even more flexible and keep week-9 for
> >>>>> 2034 as an exception to the rule), but that's a single year... for 2029
> >>>>> and 2032 we still have one week buffer.
> >>>>>
> >>>>> For Christmas, we would still ensure that the release can go out on
> >>>>> time, too. The below Q3 target release date is 4 weeks after code
> >>>>> freeze. This is a little bit more tight, as we often need more than 4
> >>>>> weeks to get it done:
> >>>>>
> >>>>>> ┌──────┬──────────────────────────┬────────────────┐
> >>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2026 │ Dec 9 │ 16 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2027 │ Dec 15 │ 10 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2028 │ Dec 13 │ 12 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2029 │ Dec 12 │ 13 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2030 │ Dec 11 │ 14 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2031 │ Dec 10 │ 15 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2032 │ Dec 8 │ 17 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2033 │ Dec 14 │ 11 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2034 │ Dec 13 │ 12 │
> >>>>>> ├──────┼──────────────────────────┼────────────────┤
> >>>>>> │ 2035 │ Dec 12 │ 13 │
> >>>>>> └──────┴──────────────────────────┴────────────────┘
> >>>>>
> >>>>>
> >>>>>
> >>>>> For some years, we would still cut it a little bit tight, but we could
> >>>>> also apply an exception to the rule, to compensate for it. If we have
> >>>>> enough buffer room from LYN, we can start the Q1 release train a week
> >>>>> earlier, reducing the Q3->Q1 timeline by one week.
> >>>>>
> >>>>>
> >>>>> Curious to hear what people think about it. In the end, if we can agree
> >>>>> on high level rules like "start Q1 release with X buffer after LYN", and
> >>>>> "complete Q3 release with Y buffer before Christmas", and still aim for
> >>>>> an as balance week-allocation per release, we can just put together a
> >>>>> release plan for the next 10 years and be done with it.
> >>>>>
> >>>>>
> >>>>> -Matthias
> >>>>>
> >>>>>
> >>>>>
> >>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
> >>>>>> Hello,
> >>>>>>
> >>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's release
> >>>>>> coincided with a reasonable amount of holidays, so I would favour a
> >>>>>> 3+2 schedule with releases in March, July and November.
> >>>>>>
> >>>>>> Best,
> >>>>>> Christo
> >>>>>>
> >>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
> >>>>>>>
> >>>>>>> Hi,
> >>>>>>>
> >>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
> >>>>>>> wrote:
> >>>>>>>
> >>>>>>>> I would go for 3 releases of equal lengths in March, July and November. I
> >>>>>>>> favour the 3+2 schedule.
> >>>>>>>>
> >>>>>>>
> >>>>>>> +1
> >>>>>>>
> >>>>>>> Thanks,
> >>>>>>> Ismael
> >>>>>
> >>>>>
> >
>
Re: [DISCUSS] Tightening time-based releases
Posted by Chia-Ping Tsai <ch...@gmail.com>.
Hi all,
+1 to the 4.5 schedule, given the delay of 4.4.0.
I think having 4.5 land right on Lunar New Year should be fine this time, since "too close" is the real issue here.
Best,
Chia-Ping
> Matthias J. Sax <mj...@apache.org> 於 2026年9月16日 清晨7:05 寫道:
>
> I don't think we have for 4.5... I believe that there was a slight, high level agreement for the long term, that we want to follow the "calendar week proposal"?
>
>>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
>>>>>> +3 weeks, and code freeze +2 weeks.
>
> AK 4.4 KIP freeze was Jul/8.
>
> For 2026, week 41 would be Oct/7 which is way too close IMHO.
> For 2027, week 9 would be Mar/3 which seems to be too far out?
>
> Second release (week 25) for 2027 would be Jun/23, which would be 4.6?
>
> So the question remains, where to put 4.5 so we can start to follow the new schedule starting with 4.6. It seems KIP freeze between Jan 13 might be a good compromise putting it roughly between 4.4 and 4.6 KIP freeze dates. Of course, the release would overlap with Chinese New Year, but it would be the last time we have this overlap.
>
> Just my 2tc.
>
>
> -Matthias
>
>> On 9/15/26 8:17 AM, David Jacot wrote:
>> Hi all,
>> Have we converged on the schedule that we want to use yet? Based on
>> the last emails, it is not so clear to me. For your context, I am
>> trying to figure out the timeline for 4.5.
>> Best,
>> David
>>> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <ch...@gmail.com> wrote:
>>>
>>> I think we could be a bit more lax with the KIP freeze of 6.7.0 when
>>> 2034 comes around to account for LNY :)
>>>
>>> Joking aside, my preference between "KIP freeze would be Wednesday's,
>>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
>>> weeks" and "start Q1 release with X buffer after LYN and complete Q3
>>> release with Y buffer before Christmas" would be to start with the
>>> first and adjust by shifting by 1 week on individual basis the ones
>>> which are too close. I am okay with too close being defined as 2
>>> weeks. Based on your very detailed tables we seem to have only a few
>>> such outliers in the next decade.
>>>
>>> Best,
>>> Christo
>>>
>>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org> wrote:
>>>>
>>>> Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
>>>>
>>>> Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
>>>>
>>>> Version KIP Freeze Feature Freeze Code Freeze Target Release
>>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
>>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
>>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
>>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
>>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
>>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
>>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
>>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
>>>>
>>>> Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
>>>>
>>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
>>>>> Thanks for the input.
>>>>>
>>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
>>>>> windows gets a lot of support.
>>>>>
>>>>> However, the idea of dividing the release windows not into 3 equally
>>>>> long junks, but be more flexible to account for holiday seasons, seems
>>>>> not to get a lot of support? Not sure why... I personally think it would
>>>>> be good to take it into account, and I also think that Chia-Ping raises
>>>>> a very good point.
>>>>>
>>>>>
>>>>>
>>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
>>>>> did actually briefly think about it, but it's difficult, and thus I just
>>>>> started with something simple as proposal to kick off a discussion.
>>>>>
>>>>> I think, Diwali is short enough to not make it a concern (similar to
>>>>> Thanksgiving)?
>>>>>
>>>>> For Lunar New Year, I agree that it would be good to plan for it.
>>>>> However, it seems it's shifting quite a lot year-over-year what makes it
>>>>> very difficult (w/o a huge window) to include?
>>>>>
>>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
>>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
>>>>> releases does not sound very appealing?
>>>>>
>>>>>
>>>>> I was playing with it a little bit more. Overall we have 52 weeks, so
>>>>> roughly 17.3 weeks per release. So we can naturally split it into
>>>>> 17/17/18 using the additional week for the holidays. But that's not good
>>>>> enough to take both Christmas and Lunar New Year into account. However,
>>>>> with a 16/16/20, we could make it work I believe, even if it does cut it
>>>>> tight sometimes... To be able to phrase a "simple rule", we can use ISO
>>>>> weeks:
>>>>>
>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
>>>>> +3 weeks, and code freeze +2 weeks.
>>>>>
>>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer for most
>>>>> years:
>>>>>
>>>>>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
>>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
>>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
>>>>>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
>>>>>
>>>>> Guess, we could also make it week-8 instead of 9, and accept that 2034
>>>>> would cut it too short (or be even more flexible and keep week-9 for
>>>>> 2034 as an exception to the rule), but that's a single year... for 2029
>>>>> and 2032 we still have one week buffer.
>>>>>
>>>>> For Christmas, we would still ensure that the release can go out on
>>>>> time, too. The below Q3 target release date is 4 weeks after code
>>>>> freeze. This is a little bit more tight, as we often need more than 4
>>>>> weeks to get it done:
>>>>>
>>>>>> ┌──────┬──────────────────────────┬────────────────┐
>>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2026 │ Dec 9 │ 16 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2027 │ Dec 15 │ 10 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2028 │ Dec 13 │ 12 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2029 │ Dec 12 │ 13 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2030 │ Dec 11 │ 14 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2031 │ Dec 10 │ 15 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2032 │ Dec 8 │ 17 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2033 │ Dec 14 │ 11 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2034 │ Dec 13 │ 12 │
>>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>>> │ 2035 │ Dec 12 │ 13 │
>>>>>> └──────┴──────────────────────────┴────────────────┘
>>>>>
>>>>>
>>>>>
>>>>> For some years, we would still cut it a little bit tight, but we could
>>>>> also apply an exception to the rule, to compensate for it. If we have
>>>>> enough buffer room from LYN, we can start the Q1 release train a week
>>>>> earlier, reducing the Q3->Q1 timeline by one week.
>>>>>
>>>>>
>>>>> Curious to hear what people think about it. In the end, if we can agree
>>>>> on high level rules like "start Q1 release with X buffer after LYN", and
>>>>> "complete Q3 release with Y buffer before Christmas", and still aim for
>>>>> an as balance week-allocation per release, we can just put together a
>>>>> release plan for the next 10 years and be done with it.
>>>>>
>>>>>
>>>>> -Matthias
>>>>>
>>>>>
>>>>>
>>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
>>>>>> Hello,
>>>>>>
>>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's release
>>>>>> coincided with a reasonable amount of holidays, so I would favour a
>>>>>> 3+2 schedule with releases in March, July and November.
>>>>>>
>>>>>> Best,
>>>>>> Christo
>>>>>>
>>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
>>>>>>>
>>>>>>> Hi,
>>>>>>>
>>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
>>>>>>> wrote:
>>>>>>>
>>>>>>>> I would go for 3 releases of equal lengths in March, July and November. I
>>>>>>>> favour the 3+2 schedule.
>>>>>>>>
>>>>>>>
>>>>>>> +1
>>>>>>>
>>>>>>> Thanks,
>>>>>>> Ismael
>>>>>
>>>>>
>
Re: [DISCUSS] Tightening time-based releases
Posted by "Matthias J. Sax" <mj...@apache.org>.
I don't think we have for 4.5... I believe that there was a slight, high
level agreement for the long term, that we want to follow the "calendar
week proposal"?
>>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
>>>>> +3 weeks, and code freeze +2 weeks.
AK 4.4 KIP freeze was Jul/8.
For 2026, week 41 would be Oct/7 which is way too close IMHO.
For 2027, week 9 would be Mar/3 which seems to be too far out?
Second release (week 25) for 2027 would be Jun/23, which would be 4.6?
So the question remains, where to put 4.5 so we can start to follow the
new schedule starting with 4.6. It seems KIP freeze between Jan 13 might
be a good compromise putting it roughly between 4.4 and 4.6 KIP freeze
dates. Of course, the release would overlap with Chinese New Year, but
it would be the last time we have this overlap.
Just my 2tc.
-Matthias
On 9/15/26 8:17 AM, David Jacot wrote:
> Hi all,
>
> Have we converged on the schedule that we want to use yet? Based on
> the last emails, it is not so clear to me. For your context, I am
> trying to figure out the timeline for 4.5.
>
> Best,
> David
>
> On Fri, May 29, 2026 at 1:03 PM Christo Lolov <ch...@gmail.com> wrote:
>>
>> I think we could be a bit more lax with the KIP freeze of 6.7.0 when
>> 2034 comes around to account for LNY :)
>>
>> Joking aside, my preference between "KIP freeze would be Wednesday's,
>> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
>> weeks" and "start Q1 release with X buffer after LYN and complete Q3
>> release with Y buffer before Christmas" would be to start with the
>> first and adjust by shifting by 1 week on individual basis the ones
>> which are too close. I am okay with too close being defined as 2
>> weeks. Based on your very detailed tables we seem to have only a few
>> such outliers in the next decade.
>>
>> Best,
>> Christo
>>
>> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org> wrote:
>>>
>>> Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
>>>
>>> Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
>>>
>>> Version KIP Freeze Feature Freeze Code Freeze Target Release
>>> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
>>> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
>>> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
>>> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
>>> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
>>> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
>>> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
>>> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
>>>
>>> Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
>>>
>>> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
>>>> Thanks for the input.
>>>>
>>>> Overall, it seems that 3+2 weeks for feature freeze / code freeze
>>>> windows gets a lot of support.
>>>>
>>>> However, the idea of dividing the release windows not into 3 equally
>>>> long junks, but be more flexible to account for holiday seasons, seems
>>>> not to get a lot of support? Not sure why... I personally think it would
>>>> be good to take it into account, and I also think that Chia-Ping raises
>>>> a very good point.
>>>>
>>>>
>>>>
>>>> @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
>>>> did actually briefly think about it, but it's difficult, and thus I just
>>>> started with something simple as proposal to kick off a discussion.
>>>>
>>>> I think, Diwali is short enough to not make it a concern (similar to
>>>> Thanksgiving)?
>>>>
>>>> For Lunar New Year, I agree that it would be good to plan for it.
>>>> However, it seems it's shifting quite a lot year-over-year what makes it
>>>> very difficult (w/o a huge window) to include?
>>>>
>>>> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
>>>> would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
>>>> releases does not sound very appealing?
>>>>
>>>>
>>>> I was playing with it a little bit more. Overall we have 52 weeks, so
>>>> roughly 17.3 weeks per release. So we can naturally split it into
>>>> 17/17/18 using the additional week for the holidays. But that's not good
>>>> enough to take both Christmas and Lunar New Year into account. However,
>>>> with a 16/16/20, we could make it work I believe, even if it does cut it
>>>> tight sometimes... To be able to phrase a "simple rule", we can use ISO
>>>> weeks:
>>>>
>>>> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
>>>> +3 weeks, and code freeze +2 weeks.
>>>>
>>>> Ie, we put the first KIP freeze after LNY with plenty of buffer for most
>>>> years:
>>>>
>>>>> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
>>>>> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
>>>>> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
>>>>> │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
>>>>> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
>>>>
>>>> Guess, we could also make it week-8 instead of 9, and accept that 2034
>>>> would cut it too short (or be even more flexible and keep week-9 for
>>>> 2034 as an exception to the rule), but that's a single year... for 2029
>>>> and 2032 we still have one week buffer.
>>>>
>>>> For Christmas, we would still ensure that the release can go out on
>>>> time, too. The below Q3 target release date is 4 weeks after code
>>>> freeze. This is a little bit more tight, as we often need more than 4
>>>> weeks to get it done:
>>>>
>>>>> ┌──────┬──────────────────────────┬────────────────┐
>>>>> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2026 │ Dec 9 │ 16 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2027 │ Dec 15 │ 10 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2028 │ Dec 13 │ 12 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2029 │ Dec 12 │ 13 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2030 │ Dec 11 │ 14 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2031 │ Dec 10 │ 15 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2032 │ Dec 8 │ 17 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2033 │ Dec 14 │ 11 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2034 │ Dec 13 │ 12 │
>>>>> ├──────┼──────────────────────────┼────────────────┤
>>>>> │ 2035 │ Dec 12 │ 13 │
>>>>> └──────┴──────────────────────────┴────────────────┘
>>>>
>>>>
>>>>
>>>> For some years, we would still cut it a little bit tight, but we could
>>>> also apply an exception to the rule, to compensate for it. If we have
>>>> enough buffer room from LYN, we can start the Q1 release train a week
>>>> earlier, reducing the Q3->Q1 timeline by one week.
>>>>
>>>>
>>>> Curious to hear what people think about it. In the end, if we can agree
>>>> on high level rules like "start Q1 release with X buffer after LYN", and
>>>> "complete Q3 release with Y buffer before Christmas", and still aim for
>>>> an as balance week-allocation per release, we can just put together a
>>>> release plan for the next 10 years and be done with it.
>>>>
>>>>
>>>> -Matthias
>>>>
>>>>
>>>>
>>>> On 5/28/26 3:51 AM, Christo Lolov wrote:
>>>>> Hello,
>>>>>
>>>>> Thanks for pushing for this! I can confirm that the 4.2.0's release
>>>>> coincided with a reasonable amount of holidays, so I would favour a
>>>>> 3+2 schedule with releases in March, July and November.
>>>>>
>>>>> Best,
>>>>> Christo
>>>>>
>>>>> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
>>>>>>
>>>>>> Hi,
>>>>>>
>>>>>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
>>>>>> wrote:
>>>>>>
>>>>>>> I would go for 3 releases of equal lengths in March, July and November. I
>>>>>>> favour the 3+2 schedule.
>>>>>>>
>>>>>>
>>>>>> +1
>>>>>>
>>>>>> Thanks,
>>>>>> Ismael
>>>>
>>>>
Re: [DISCUSS] Tightening time-based releases
Posted by David Jacot <da...@apache.org>.
Hi all,
Have we converged on the schedule that we want to use yet? Based on
the last emails, it is not so clear to me. For your context, I am
trying to figure out the timeline for 4.5.
Best,
David
On Fri, May 29, 2026 at 1:03 PM Christo Lolov <ch...@gmail.com> wrote:
>
> I think we could be a bit more lax with the KIP freeze of 6.7.0 when
> 2034 comes around to account for LNY :)
>
> Joking aside, my preference between "KIP freeze would be Wednesday's,
> weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
> weeks" and "start Q1 release with X buffer after LYN and complete Q3
> release with Y buffer before Christmas" would be to start with the
> first and adjust by shifting by 1 week on individual basis the ones
> which are too close. I am okay with too close being defined as 2
> weeks. Based on your very detailed tables we seem to have only a few
> such outliers in the next decade.
>
> Best,
> Christo
>
> On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org> wrote:
> >
> > Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
> >
> > Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
> >
> > Version KIP Freeze Feature Freeze Code Freeze Target Release
> > 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
> > 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
> > 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
> > 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
> > 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
> > 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
> > 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
> > 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
> >
> > Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
> >
> > On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> > > Thanks for the input.
> > >
> > > Overall, it seems that 3+2 weeks for feature freeze / code freeze
> > > windows gets a lot of support.
> > >
> > > However, the idea of dividing the release windows not into 3 equally
> > > long junks, but be more flexible to account for holiday seasons, seems
> > > not to get a lot of support? Not sure why... I personally think it would
> > > be good to take it into account, and I also think that Chia-Ping raises
> > > a very good point.
> > >
> > >
> > >
> > > @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
> > > did actually briefly think about it, but it's difficult, and thus I just
> > > started with something simple as proposal to kick off a discussion.
> > >
> > > I think, Diwali is short enough to not make it a concern (similar to
> > > Thanksgiving)?
> > >
> > > For Lunar New Year, I agree that it would be good to plan for it.
> > > However, it seems it's shifting quite a lot year-over-year what makes it
> > > very difficult (w/o a huge window) to include?
> > >
> > > Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
> > > would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
> > > releases does not sound very appealing?
> > >
> > >
> > > I was playing with it a little bit more. Overall we have 52 weeks, so
> > > roughly 17.3 weeks per release. So we can naturally split it into
> > > 17/17/18 using the additional week for the holidays. But that's not good
> > > enough to take both Christmas and Lunar New Year into account. However,
> > > with a 16/16/20, we could make it work I believe, even if it does cut it
> > > tight sometimes... To be able to phrase a "simple rule", we can use ISO
> > > weeks:
> > >
> > > KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> > > +3 weeks, and code freeze +2 weeks.
> > >
> > > Ie, we put the first KIP freeze after LNY with plenty of buffer for most
> > > years:
> > >
> > > > ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > > > │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
> > > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > > │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
> > > > └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> > >
> > > Guess, we could also make it week-8 instead of 9, and accept that 2034
> > > would cut it too short (or be even more flexible and keep week-9 for
> > > 2034 as an exception to the rule), but that's a single year... for 2029
> > > and 2032 we still have one week buffer.
> > >
> > > For Christmas, we would still ensure that the release can go out on
> > > time, too. The below Q3 target release date is 4 weeks after code
> > > freeze. This is a little bit more tight, as we often need more than 4
> > > weeks to get it done:
> > >
> > > > ┌──────┬──────────────────────────┬────────────────┐
> > > > │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2026 │ Dec 9 │ 16 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2027 │ Dec 15 │ 10 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2028 │ Dec 13 │ 12 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2029 │ Dec 12 │ 13 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2030 │ Dec 11 │ 14 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2031 │ Dec 10 │ 15 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2032 │ Dec 8 │ 17 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2033 │ Dec 14 │ 11 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2034 │ Dec 13 │ 12 │
> > > > ├──────┼──────────────────────────┼────────────────┤
> > > > │ 2035 │ Dec 12 │ 13 │
> > > > └──────┴──────────────────────────┴────────────────┘
> > >
> > >
> > >
> > > For some years, we would still cut it a little bit tight, but we could
> > > also apply an exception to the rule, to compensate for it. If we have
> > > enough buffer room from LYN, we can start the Q1 release train a week
> > > earlier, reducing the Q3->Q1 timeline by one week.
> > >
> > >
> > > Curious to hear what people think about it. In the end, if we can agree
> > > on high level rules like "start Q1 release with X buffer after LYN", and
> > > "complete Q3 release with Y buffer before Christmas", and still aim for
> > > an as balance week-allocation per release, we can just put together a
> > > release plan for the next 10 years and be done with it.
> > >
> > >
> > > -Matthias
> > >
> > >
> > >
> > > On 5/28/26 3:51 AM, Christo Lolov wrote:
> > > > Hello,
> > > >
> > > > Thanks for pushing for this! I can confirm that the 4.2.0's release
> > > > coincided with a reasonable amount of holidays, so I would favour a
> > > > 3+2 schedule with releases in March, July and November.
> > > >
> > > > Best,
> > > > Christo
> > > >
> > > > On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
> > > >>
> > > >> Hi,
> > > >>
> > > >> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
> > > >> wrote:
> > > >>
> > > >>> I would go for 3 releases of equal lengths in March, July and November. I
> > > >>> favour the 3+2 schedule.
> > > >>>
> > > >>
> > > >> +1
> > > >>
> > > >> Thanks,
> > > >> Ismael
> > >
> > >
Re: [DISCUSS] Tightening time-based releases
Posted by Christo Lolov <ch...@gmail.com>.
I think we could be a bit more lax with the KIP freeze of 6.7.0 when
2034 comes around to account for LNY :)
Joking aside, my preference between "KIP freeze would be Wednesday's,
weeks 9 / 25 / 41, with feature freeze +3 weeks, and code freeze +2
weeks" and "start Q1 release with X buffer after LYN and complete Q3
release with Y buffer before Christmas" would be to start with the
first and adjust by shifting by 1 week on individual basis the ones
which are too close. I am okay with too close being defined as 2
weeks. Based on your very detailed tables we seem to have only a few
such outliers in the next decade.
Best,
Christo
On Fri, 29 May 2026 at 08:35, Chia-Ping Tsai <ch...@apache.org> wrote:
>
> Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
>
> Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
>
> Version KIP Freeze Feature Freeze Code Freeze Target Release
> 4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
> 4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
> 4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
> 4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
> 4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
> 4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
> 5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
> 5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
>
> Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
>
> On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> > Thanks for the input.
> >
> > Overall, it seems that 3+2 weeks for feature freeze / code freeze
> > windows gets a lot of support.
> >
> > However, the idea of dividing the release windows not into 3 equally
> > long junks, but be more flexible to account for holiday seasons, seems
> > not to get a lot of support? Not sure why... I personally think it would
> > be good to take it into account, and I also think that Chia-Ping raises
> > a very good point.
> >
> >
> >
> > @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
> > did actually briefly think about it, but it's difficult, and thus I just
> > started with something simple as proposal to kick off a discussion.
> >
> > I think, Diwali is short enough to not make it a concern (similar to
> > Thanksgiving)?
> >
> > For Lunar New Year, I agree that it would be good to plan for it.
> > However, it seems it's shifting quite a lot year-over-year what makes it
> > very difficult (w/o a huge window) to include?
> >
> > Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
> > would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
> > releases does not sound very appealing?
> >
> >
> > I was playing with it a little bit more. Overall we have 52 weeks, so
> > roughly 17.3 weeks per release. So we can naturally split it into
> > 17/17/18 using the additional week for the holidays. But that's not good
> > enough to take both Christmas and Lunar New Year into account. However,
> > with a 16/16/20, we could make it work I believe, even if it does cut it
> > tight sometimes... To be able to phrase a "simple rule", we can use ISO
> > weeks:
> >
> > KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> > +3 weeks, and code freeze +2 weeks.
> >
> > Ie, we put the first KIP freeze after LNY with plenty of buffer for most
> > years:
> >
> > > ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > > │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
> > > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > > │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
> > > └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
> >
> > Guess, we could also make it week-8 instead of 9, and accept that 2034
> > would cut it too short (or be even more flexible and keep week-9 for
> > 2034 as an exception to the rule), but that's a single year... for 2029
> > and 2032 we still have one week buffer.
> >
> > For Christmas, we would still ensure that the release can go out on
> > time, too. The below Q3 target release date is 4 weeks after code
> > freeze. This is a little bit more tight, as we often need more than 4
> > weeks to get it done:
> >
> > > ┌──────┬──────────────────────────┬────────────────┐
> > > │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2026 │ Dec 9 │ 16 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2027 │ Dec 15 │ 10 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2028 │ Dec 13 │ 12 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2029 │ Dec 12 │ 13 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2030 │ Dec 11 │ 14 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2031 │ Dec 10 │ 15 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2032 │ Dec 8 │ 17 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2033 │ Dec 14 │ 11 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2034 │ Dec 13 │ 12 │
> > > ├──────┼──────────────────────────┼────────────────┤
> > > │ 2035 │ Dec 12 │ 13 │
> > > └──────┴──────────────────────────┴────────────────┘
> >
> >
> >
> > For some years, we would still cut it a little bit tight, but we could
> > also apply an exception to the rule, to compensate for it. If we have
> > enough buffer room from LYN, we can start the Q1 release train a week
> > earlier, reducing the Q3->Q1 timeline by one week.
> >
> >
> > Curious to hear what people think about it. In the end, if we can agree
> > on high level rules like "start Q1 release with X buffer after LYN", and
> > "complete Q3 release with Y buffer before Christmas", and still aim for
> > an as balance week-allocation per release, we can just put together a
> > release plan for the next 10 years and be done with it.
> >
> >
> > -Matthias
> >
> >
> >
> > On 5/28/26 3:51 AM, Christo Lolov wrote:
> > > Hello,
> > >
> > > Thanks for pushing for this! I can confirm that the 4.2.0's release
> > > coincided with a reasonable amount of holidays, so I would favour a
> > > 3+2 schedule with releases in March, July and November.
> > >
> > > Best,
> > > Christo
> > >
> > > On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
> > >>
> > >> Hi,
> > >>
> > >> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
> > >> wrote:
> > >>
> > >>> I would go for 3 releases of equal lengths in March, July and November. I
> > >>> favour the 3+2 schedule.
> > >>>
> > >>
> > >> +1
> > >>
> > >> Thanks,
> > >> Ismael
> >
> >
Re: [DISCUSS] Tightening time-based releases
Posted by Chia-Ping Tsai <ch...@apache.org>.
Matthias, you are definitely a master of scheduling! I'm +100 to your plans.
Also, it is absolutely helpful to write down the exact release dates for the next few years at once. It will ease our anxiety a lot! I'd be more than happy to update the wiki with these dates once we all agree on this new schedule. For example:
Version KIP Freeze Feature Freeze Code Freeze Target Release
4.4.0 Jun 17, 2026 Jul 8, 2026 Jul 22, 2026 Aug 19, 2026
4.5.0 Oct 7, 2026 Oct 28, 2026 Nov 11, 2026 Dec 9, 2026
4.6.0 Mar 3, 2027 Mar 24, 2027 Apr 7, 2027 May 5, 2027
4.7.0 Jun 23, 2027 Jul 14, 2027 Jul 28, 2027 Aug 25, 2027
4.8.0 Oct 13, 2027 Nov 3, 2027 Nov 17, 2027 Dec 15, 2027
4.9.0 Mar 1, 2028 Mar 22, 2028 Apr 5, 2028 May 3, 2028
5.0.0 Jun 21, 2028 Jul 12, 2028 Jul 26, 2028 Aug 23, 2028
5.1.0 Oct 11, 2028 Nov 1, 2028 Nov 15, 2028 Dec 13, 2028
Furthermore, let's do our best to avoid fixing release blockers under the Christmas tree :)
On 2026/05/28 21:22:51 "Matthias J. Sax" wrote:
> Thanks for the input.
>
> Overall, it seems that 3+2 weeks for feature freeze / code freeze
> windows gets a lot of support.
>
> However, the idea of dividing the release windows not into 3 equally
> long junks, but be more flexible to account for holiday seasons, seems
> not to get a lot of support? Not sure why... I personally think it would
> be good to take it into account, and I also think that Chia-Ping raises
> a very good point.
>
>
>
> @Chia-Ping: Other holidays are a great point. Thanks for raising it. I
> did actually briefly think about it, but it's difficult, and thus I just
> started with something simple as proposal to kick off a discussion.
>
> I think, Diwali is short enough to not make it a concern (similar to
> Thanksgiving)?
>
> For Lunar New Year, I agree that it would be good to plan for it.
> However, it seems it's shifting quite a lot year-over-year what makes it
> very difficult (w/o a huge window) to include?
>
> Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
> would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
> releases does not sound very appealing?
>
>
> I was playing with it a little bit more. Overall we have 52 weeks, so
> roughly 17.3 weeks per release. So we can naturally split it into
> 17/17/18 using the additional week for the holidays. But that's not good
> enough to take both Christmas and Lunar New Year into account. However,
> with a 16/16/20, we could make it work I believe, even if it does cut it
> tight sometimes... To be able to phrase a "simple rule", we can use ISO
> weeks:
>
> KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
> +3 weeks, and code freeze +2 weeks.
>
> Ie, we put the first KIP freeze after LNY with plenty of buffer for most
> years:
>
> > ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> > │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
> > ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> > │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
> > └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
>
> Guess, we could also make it week-8 instead of 9, and accept that 2034
> would cut it too short (or be even more flexible and keep week-9 for
> 2034 as an exception to the rule), but that's a single year... for 2029
> and 2032 we still have one week buffer.
>
> For Christmas, we would still ensure that the release can go out on
> time, too. The below Q3 target release date is 4 weeks after code
> freeze. This is a little bit more tight, as we often need more than 4
> weeks to get it done:
>
> > ┌──────┬──────────────────────────┬────────────────┐
> > │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2026 │ Dec 9 │ 16 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2027 │ Dec 15 │ 10 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2028 │ Dec 13 │ 12 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2029 │ Dec 12 │ 13 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2030 │ Dec 11 │ 14 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2031 │ Dec 10 │ 15 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2032 │ Dec 8 │ 17 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2033 │ Dec 14 │ 11 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2034 │ Dec 13 │ 12 │
> > ├──────┼──────────────────────────┼────────────────┤
> > │ 2035 │ Dec 12 │ 13 │
> > └──────┴──────────────────────────┴────────────────┘
>
>
>
> For some years, we would still cut it a little bit tight, but we could
> also apply an exception to the rule, to compensate for it. If we have
> enough buffer room from LYN, we can start the Q1 release train a week
> earlier, reducing the Q3->Q1 timeline by one week.
>
>
> Curious to hear what people think about it. In the end, if we can agree
> on high level rules like "start Q1 release with X buffer after LYN", and
> "complete Q3 release with Y buffer before Christmas", and still aim for
> an as balance week-allocation per release, we can just put together a
> release plan for the next 10 years and be done with it.
>
>
> -Matthias
>
>
>
> On 5/28/26 3:51 AM, Christo Lolov wrote:
> > Hello,
> >
> > Thanks for pushing for this! I can confirm that the 4.2.0's release
> > coincided with a reasonable amount of holidays, so I would favour a
> > 3+2 schedule with releases in March, July and November.
> >
> > Best,
> > Christo
> >
> > On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
> >>
> >> Hi,
> >>
> >> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
> >> wrote:
> >>
> >>> I would go for 3 releases of equal lengths in March, July and November. I
> >>> favour the 3+2 schedule.
> >>>
> >>
> >> +1
> >>
> >> Thanks,
> >> Ismael
>
>
Re: [DISCUSS] Tightening time-based releases
Posted by "Matthias J. Sax" <mj...@apache.org>.
Thanks for the input.
Overall, it seems that 3+2 weeks for feature freeze / code freeze
windows gets a lot of support.
However, the idea of dividing the release windows not into 3 equally
long junks, but be more flexible to account for holiday seasons, seems
not to get a lot of support? Not sure why... I personally think it would
be good to take it into account, and I also think that Chia-Ping raises
a very good point.
@Chia-Ping: Other holidays are a great point. Thanks for raising it. I
did actually briefly think about it, but it's difficult, and thus I just
started with something simple as proposal to kick off a discussion.
I think, Diwali is short enough to not make it a concern (similar to
Thanksgiving)?
For Lunar New Year, I agree that it would be good to plan for it.
However, it seems it's shifting quite a lot year-over-year what makes it
very difficult (w/o a huge window) to include?
Overall, a 5 / 3.5 / 3.5 schedule seems to be quite unbalanced (this
would be 22 / 15 / 15 weeks per release? And two very short 3.5 month
releases does not sound very appealing?
I was playing with it a little bit more. Overall we have 52 weeks, so
roughly 17.3 weeks per release. So we can naturally split it into
17/17/18 using the additional week for the holidays. But that's not good
enough to take both Christmas and Lunar New Year into account. However,
with a 16/16/20, we could make it work I believe, even if it does cut it
tight sometimes... To be able to phrase a "simple rule", we can use ISO
weeks:
KIP freeze would be Wednesday's, weeks 9 / 25 / 41, with feature freeze
+3 weeks, and code freeze +2 weeks.
Ie, we put the first KIP freeze after LNY with plenty of buffer for most
years:
> ┌──────┬────────┬────────────────────────────┬───────────────────────────────────────┐
> │ Year │ LNY │ Q1 KIP freeze (week 9 Wed) │ Buffer │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2027 │ Feb 6 │ Mar 3 │ 25 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2028 │ Jan 26 │ Mar 1 │ 34 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2029 │ Feb 13 │ Feb 28 │ 15 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2030 │ Feb 3 │ Feb 27 │ 24 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2031 │ Jan 23 │ Feb 26 │ 34 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2032 │ Feb 11 │ Feb 25 │ 14 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2033 │ Jan 31 │ Mar 2 │ 30 days │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2034 │ Feb 19 │ Mar 1 │ 10 days ← tightest with realistic LNY │
> ├──────┼────────┼────────────────────────────┼───────────────────────────────────────┤
> │ 2035 │ Feb 8 │ Feb 28 │ 20 days │
> └──────┴────────┴────────────────────────────┴───────────────────────────────────────┘
Guess, we could also make it week-8 instead of 9, and accept that 2034
would cut it too short (or be even more flexible and keep week-9 for
2034 as an exception to the rule), but that's a single year... for 2029
and 2032 we still have one week buffer.
For Christmas, we would still ensure that the release can go out on
time, too. The below Q3 target release date is 4 weeks after code
freeze. This is a little bit more tight, as we often need more than 4
weeks to get it done:
> ┌──────┬──────────────────────────┬────────────────┐
> │ Year │ Q3 release (week 50 Wed) │ Days to Dec 25 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2026 │ Dec 9 │ 16 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2027 │ Dec 15 │ 10 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2028 │ Dec 13 │ 12 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2029 │ Dec 12 │ 13 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2030 │ Dec 11 │ 14 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2031 │ Dec 10 │ 15 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2032 │ Dec 8 │ 17 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2033 │ Dec 14 │ 11 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2034 │ Dec 13 │ 12 │
> ├──────┼──────────────────────────┼────────────────┤
> │ 2035 │ Dec 12 │ 13 │
> └──────┴──────────────────────────┴────────────────┘
For some years, we would still cut it a little bit tight, but we could
also apply an exception to the rule, to compensate for it. If we have
enough buffer room from LYN, we can start the Q1 release train a week
earlier, reducing the Q3->Q1 timeline by one week.
Curious to hear what people think about it. In the end, if we can agree
on high level rules like "start Q1 release with X buffer after LYN", and
"complete Q3 release with Y buffer before Christmas", and still aim for
an as balance week-allocation per release, we can just put together a
release plan for the next 10 years and be done with it.
-Matthias
On 5/28/26 3:51 AM, Christo Lolov wrote:
> Hello,
>
> Thanks for pushing for this! I can confirm that the 4.2.0's release
> coincided with a reasonable amount of holidays, so I would favour a
> 3+2 schedule with releases in March, July and November.
>
> Best,
> Christo
>
> On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
>>
>> Hi,
>>
>> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
>> wrote:
>>
>>> I would go for 3 releases of equal lengths in March, July and November. I
>>> favour the 3+2 schedule.
>>>
>>
>> +1
>>
>> Thanks,
>> Ismael
Re: [DISCUSS] Tightening time-based releases
Posted by Christo Lolov <cl...@apache.org>.
Hello,
Thanks for pushing for this! I can confirm that the 4.2.0's release
coincided with a reasonable amount of holidays, so I would favour a
3+2 schedule with releases in March, July and November.
Best,
Christo
On Thu, 28 May 2026 at 07:05, Ismael Juma <me...@ismaeljuma.com> wrote:
>
> Hi,
>
> On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
> wrote:
>
> > I would go for 3 releases of equal lengths in March, July and November. I
> > favour the 3+2 schedule.
> >
>
> +1
>
> Thanks,
> Ismael
Re: [DISCUSS] Tightening time-based releases
Posted by Ismael Juma <me...@ismaeljuma.com>.
Hi,
On Wed, May 27, 2026 at 12:44 AM Andrew Schofield <sc...@apache.org>
wrote:
> I would go for 3 releases of equal lengths in March, July and November. I
> favour the 3+2 schedule.
>
+1
Thanks,
Ismael
Re: [DISCUSS] Tightening time-based releases
Posted by Andrew Schofield <sc...@apache.org>.
Hi Matthias,
Thanks for driving this. I'm a bit less concerned about it than you, but stronger rules would eliminate the typical release schedule alignment discussions we've seen in all of the recent releases.
I would go for 3 releases of equal lengths in March, July and November. I favour the 3+2 schedule.
Thanks,
Andrew
On 2026/05/27 05:43:04 "Matthias J. Sax" wrote:
> Hello,
>
> I would like to start a discussion about our time-based release
> schedule. We have a discussion (that I personally find a little bit
> annoying and tedious) about release plan dates on every single release
> (the 4.4.0 discussion, is just another example). And we still often end
> up with none-optimal time-frames (4.4 might also be an example here --
> not by itself, but the impact on 4.5 release timeline -- cf my latest
> reply on the other thread).
>
> Given that we actually plan to have time-based releases, I think we
> should agree on a more fixed schedule, which allows us to project all
> release dates (including KIP/feature/code freeze) into the future and
> just be done with it. -- And even if we need an exception from the rule,
> we can easily get back on track on future release afterwards.
>
> I was also looking into historic data, and while we overall don't do too
> bad to stay on track for 3 release per year, we had to pay the price of
> a few short release cycles to "shift back" (the previous 4.3 release is
> a good example of it), while we still did shift somewhat forward
> overall. These short releases cause even more pain IMHO.
>
> To avoid problems with the holiday season end of the year, I would like
> to propose the following fixed release cadence (this is not my personal
> favorite, but let's start here):
>
> 1. KIP freeze is the second Wednesday of January, May, and September.
> 2. Feature freeze = KIP freeze + 3 weeks.
> 3. Code freeze = Feature freeze + 3 weeks.
> 4. Release target = Code freeze + 4 weeks.
>
> While we never officially formalized the 3+3 weeks between KIP/feature
> and feature/code freeze dates (and we used shorter time windows in the
> past, ie, 2+2 weeks), 3+3 established itself since 4.0 release -- I am
> totally open for other time frames, but believe we should not go shorter
> than 2+2 weeks. I would also not make them longer than 3+3, as it would
> just give us the subjective impression that releases are closer to each
> other.
>
> A 3+2 schedule would actually be my personal preference. For KIPs,
> giving only 2 weeks to complete them is tight, even for simple KIPs. And
> for bug-fixes, I would believe that 2 weeks are enough. Making it
> overall 5 week instead of 6, also helps to keep releases 1 week "further
> apart" from each other (not really, but we know how reality works, given
> our subjective nature).
>
> The above schedule implies that we would have target release dates late
> March, July, and November. Even if we need more than 4 weeks after code
> freeze, we still have some head room in the November release before the
> holidays (we might hit Thanksgiving, but I think that's ok). For the KIP
> freeze in January, it should also give enough time after the holidays to
> complete KIPs and get them accepted (w/o being too close to the
> holidays, eg, "first Wednesday in January" would effectively mean, that
> KIPs must get voted before the holiday break).
>
> If we want to take the holiday season into account even more, we could
> also make the timeline between "release 3" and "release 1 of the
> following year" two weeks longer, and the other two timelines 1 week
> shorter. This would give us the following KIP freeze deadlines:
>
> - third Wednesday of January
> - second Wednesday of May
> - first Wednesday of September
>
> It also implies, that Thanksgiving would be less of an issue for
> "release 3". This schedule is what I would personally prefer, instead of
> an 100% equal distribution of our 52 weeks across all three releases.
>
>
>
> For the upcoming 4.4 release, we should make it a 5-month cycle
> targeting October instead of September, and we would also have a
> slightly longer cycle for 4.6, which we should only start in January.
> However, starting with 4.6 we would enter the above proposed fixed
> timeline, putting us into a much better position going forward IMHO.
>
>
> Looking forward to your thoughts on this idea.
>
>
> -Matthias
>
>
>