Posted to dev@ofbiz.apache.org by Hans Bakker <ma...@antwebsystems.com> on 2007/12/20 06:49:15 UTC
Re: Task (WorkEffort) Statuses, any further comments?
Can I ask the community to check the last project Task status proposal?
If there are no further comments i will implement the proposal below in
a couple of days in the special component 'project manager'
The final proposal about the project task status was:
The status on a task is largely system controlled (1-4) and user controlled (5-6):
----------------------------------------------------------------------------------
1: unassigned -> the task has no performers and has not started.
2: assigned -> the task has one or more performers but has still not started
3. in-progress -> at least one performer has registered, the task is started
time on the task
4. completed -> all attached performers have set their assign
status to completed
5. onHold -> the projectmanager can set this status and
can be set back to status 1-3
6. cancelled -> again can be set by the projectmanager
The status of the assignment of a party to the task is manual
controlled:
-------------------------------------------------------------
1. assigned -> the task is assigned to the party with
from/thru dates to show when active
2. completed -> the party has done his part (work,approval,
test etc) on the task and has indicated he is ready.
--
http://Antwebsystems.com : OFBiz Quality support for competitive rates.