Linking Purchase Orders with Requirements

Hello everyone,
I was exploring the issue OFBIZ-7128
<https://issues.apache.org/jira/browse/OFBIZ-7128> which is regarding the
listing of the Purchase Orders generated using approved requirements.

Currently, the  system doesn't keep track of POs with respect to
requirements. In the case of sales orders, *OrderRequirementCommitment
*records are
being generated once the order status changes from *Created to Approved*.

Should we create *OrderRequirementCommitment *records for Purchase orders
at the time of placing the PO, so that the POs can be tracked corresponding
to the particular Requirement.

As of now the approved requirements are only used for initializing PO cart
& then the requirement is being marked as *ordered *once the PO is created.
This work flow should also be improved, as we are always free to edit the
cart items & how can we mark a requirement as *ordered* if we reduced the
quantity of the item corresponding to the requirement while placing the PO.

In short there are two major concerns:

   - Need of *OrderRequirementCommitment records* for PO
   - Proper validation while Marking Requirements *Ordered *when placing
   POs using Requirements

I would like to invite you all for discussing these requirements,  so that
we can conclude this work flow properly.


Thanks and Regards
*Rahul Bhooteshwar*
Enterprise Software Engineer
HotWax Systems <http://www.hotwaxsystems.com/> - *Global leader in
innovative enterprise commerce solutions **powered by Apache OFBiz.*

Re: Linking Purchase Orders with Requirements

Posted by Rahul Bhooteshwar <ra...@hotwaxsystems.com>.
Thank you, Swapnil for the detailed explanation.
Considering only the ordered quantity of an item for a specific
requirement, we can create OrderRequirementCommitment while placing the PO.
I have uploaded the patch for the same.

Thanks and Regards
*Rahul Bhooteshwar*
Enterprise Software Engineer
HotWax Systems <http://www.hotwaxsystems.com/> - *Global leader in
innovative enterprise commerce solutions **powered by Apache OFBiz.*

On Sat, Jun 18, 2016 at 6:03 PM, Swapnil Shah <
swapnil.shah@hotwaxsystems.com> wrote:

> Yes I do agree on suggested usage of OrderRequirementCommitment to link
> Order and Requirement. Apart from this for following thought...
> " Also out of 10 requirements if PO is created and approved for 5
> requirements then this particular requirement should be marked as "Ordered"
> and for remaining 5 requirements we should create new requirement so that
> we
> don't lose those requirements in system."
>
> IMO, Let's leave the requirement in Ordered state and don't forcefully
> create requirement for remaining qty. Requirement (via any systemic
> workflow
> like MRP or Manually) are suggested quantity based on state of affair at
> the
> time when that requirement came into existence in system and it's up to
> buyer to take call and hence reduce/increase this suggested quantity while
> placing the orders. In the next systemic run (of MRP or manually by user)
> the requirement could be regenerate based on the then demand/supply gap.
>
> Thanks & Regards,
> Swapnil
>
> -----Original Message-----
> From: Divesh Dutta [mailto:divesh.dutta@hotwaxsystems.com]
> Sent: Saturday, June 18, 2016 5:47 PM
> To: dev@ofbiz.apache.org
> Cc: Rahul Bhooteshwar <ra...@hotwaxsystems.com>
> Subject: Re: Linking Purchase Orders with Requirements
>
> In my opinion we are good to use OrderRequirementCommitment table for
> associating POs created with respect to requirements. This way we will be
> able to track what POs are wrt which SOs. This can help us in future to see
> PO lined up wrt SOs.
>
> Also similar to SO, we should mark Requirement "Ordered" only when PO is
> "approved". Also out of 10 requirements if PO is created and approved for 5
> requirements then this particular requirement should be marked as "Ordered"
> and for remaining 5 requirements we should create new requirement so that
> we
> don't loose those requirements in system.
>
> Thanks
> --
> Divesh Dutta.
>
> On Sat, Jun 18, 2016 at 5:00 PM, Rahul Bhooteshwar <
> rahul.bhooteshwar@hotwaxsystems.com> wrote:
>
> > Hello everyone,
> > I was exploring the issue OFBIZ-7128
> > <https://issues.apache.org/jira/browse/OFBIZ-7128> which is regarding
> > the listing of the Purchase Orders generated using approved requirements.
> >
> > Currently, the  system doesn't keep track of POs with respect to
> > requirements. In the case of sales orders, *OrderRequirementCommitment
> > *records are being generated once the order status changes from
> > *Created to Approved*.
> >
> > Should we create *OrderRequirementCommitment *records for Purchase
> > orders at the time of placing the PO, so that the POs can be tracked
> > corresponding to the particular Requirement.
> >
> > As of now the approved requirements are only used for initializing PO
> > cart & then the requirement is being marked as *ordered *once the PO is
> > created.
> > This work flow should also be improved, as we are always free to edit
> > the cart items & how can we mark a requirement as *ordered* if we
> > reduced the quantity of the item corresponding to the requirement while
> > placing the PO.
> >
> > In short there are two major concerns:
> >
> >    - Need of *OrderRequirementCommitment records* for PO
> >    - Proper validation while Marking Requirements *Ordered *when placing
> >    POs using Requirements
> >
> > I would like to invite you all for discussing these requirements,  so
> > that we can conclude this work flow properly.
> >
> >
> > Thanks and Regards
> > *Rahul Bhooteshwar*
> > Enterprise Software Engineer
> > HotWax Systems <http://www.hotwaxsystems.com/> - *Global leader in
> > innovative enterprise commerce solutions **powered by Apache OFBiz.*
> >
>

RE: Linking Purchase Orders with Requirements

Posted by Swapnil Shah <sw...@hotwaxsystems.com>.
Yes I do agree on suggested usage of OrderRequirementCommitment to link
Order and Requirement. Apart from this for following thought...
" Also out of 10 requirements if PO is created and approved for 5
requirements then this particular requirement should be marked as "Ordered"
and for remaining 5 requirements we should create new requirement so that we
don't lose those requirements in system."

IMO, Let's leave the requirement in Ordered state and don't forcefully
create requirement for remaining qty. Requirement (via any systemic workflow
like MRP or Manually) are suggested quantity based on state of affair at the
time when that requirement came into existence in system and it's up to
buyer to take call and hence reduce/increase this suggested quantity while
placing the orders. In the next systemic run (of MRP or manually by user)
the requirement could be regenerate based on the then demand/supply gap.

Thanks & Regards,
Swapnil

-----Original Message-----
From: Divesh Dutta [mailto:divesh.dutta@hotwaxsystems.com]
Sent: Saturday, June 18, 2016 5:47 PM
To: dev@ofbiz.apache.org
Cc: Rahul Bhooteshwar <ra...@hotwaxsystems.com>
Subject: Re: Linking Purchase Orders with Requirements

In my opinion we are good to use OrderRequirementCommitment table for
associating POs created with respect to requirements. This way we will be
able to track what POs are wrt which SOs. This can help us in future to see
PO lined up wrt SOs.

Also similar to SO, we should mark Requirement "Ordered" only when PO is
"approved". Also out of 10 requirements if PO is created and approved for 5
requirements then this particular requirement should be marked as "Ordered"
and for remaining 5 requirements we should create new requirement so that we
don't loose those requirements in system.

Thanks
--
Divesh Dutta.

On Sat, Jun 18, 2016 at 5:00 PM, Rahul Bhooteshwar <
rahul.bhooteshwar@hotwaxsystems.com> wrote:

> Hello everyone,
> I was exploring the issue OFBIZ-7128
> <https://issues.apache.org/jira/browse/OFBIZ-7128> which is regarding
> the listing of the Purchase Orders generated using approved requirements.
>
> Currently, the  system doesn't keep track of POs with respect to
> requirements. In the case of sales orders, *OrderRequirementCommitment
> *records are being generated once the order status changes from
> *Created to Approved*.
>
> Should we create *OrderRequirementCommitment *records for Purchase
> orders at the time of placing the PO, so that the POs can be tracked
> corresponding to the particular Requirement.
>
> As of now the approved requirements are only used for initializing PO
> cart & then the requirement is being marked as *ordered *once the PO is
> created.
> This work flow should also be improved, as we are always free to edit
> the cart items & how can we mark a requirement as *ordered* if we
> reduced the quantity of the item corresponding to the requirement while
> placing the PO.
>
> In short there are two major concerns:
>
>    - Need of *OrderRequirementCommitment records* for PO
>    - Proper validation while Marking Requirements *Ordered *when placing
>    POs using Requirements
>
> I would like to invite you all for discussing these requirements,  so
> that we can conclude this work flow properly.
>
>
> Thanks and Regards
> *Rahul Bhooteshwar*
> Enterprise Software Engineer
> HotWax Systems <http://www.hotwaxsystems.com/> - *Global leader in
> innovative enterprise commerce solutions **powered by Apache OFBiz.*
>

Re: Linking Purchase Orders with Requirements

Posted by Divesh Dutta <di...@hotwaxsystems.com>.
In my opinion we are good to use OrderRequirementCommitment table for
associating POs created with respect to requirements. This way we will be
able to track what POs are wrt which SOs. This can help us in future to see
PO lined up wrt SOs.

Also similar to SO, we should mark Requirement "Ordered" only when PO is
"approved". Also out of 10 requirements if PO is created and approved for 5
requirements then this particular requirement should be marked as "Ordered"
and for remaining 5 requirements we should create new requirement so that
we don't loose those requirements in system.

Thanks
--
Divesh Dutta.

On Sat, Jun 18, 2016 at 5:00 PM, Rahul Bhooteshwar <
rahul.bhooteshwar@hotwaxsystems.com> wrote:

> Hello everyone,
> I was exploring the issue OFBIZ-7128
> <https://issues.apache.org/jira/browse/OFBIZ-7128> which is regarding the
> listing of the Purchase Orders generated using approved requirements.
>
> Currently, the  system doesn't keep track of POs with respect to
> requirements. In the case of sales orders, *OrderRequirementCommitment
> *records are
> being generated once the order status changes from *Created to Approved*.
>
> Should we create *OrderRequirementCommitment *records for Purchase orders
> at the time of placing the PO, so that the POs can be tracked corresponding
> to the particular Requirement.
>
> As of now the approved requirements are only used for initializing PO cart
> & then the requirement is being marked as *ordered *once the PO is created.
> This work flow should also be improved, as we are always free to edit the
> cart items & how can we mark a requirement as *ordered* if we reduced the
> quantity of the item corresponding to the requirement while placing the PO.
>
> In short there are two major concerns:
>
>    - Need of *OrderRequirementCommitment records* for PO
>    - Proper validation while Marking Requirements *Ordered *when placing
>    POs using Requirements
>
> I would like to invite you all for discussing these requirements,  so that
> we can conclude this work flow properly.
>
>
> Thanks and Regards
> *Rahul Bhooteshwar*
> Enterprise Software Engineer
> HotWax Systems <http://www.hotwaxsystems.com/> - *Global leader in
> innovative enterprise commerce solutions **powered by Apache OFBiz.*
>