You are viewing a plain text version of this content. The canonical link for it is here.
Posted to commits@spamassassin.apache.org by Apache Wiki <wi...@apache.org> on 2005/07/02 05:32:20 UTC

[Spamassassin Wiki] Update of "Release310Schedule" by JustinMason

Dear Wiki user,

You have subscribed to a wiki page or wiki category on "Spamassassin Wiki" for change notification.

The following page has been changed by JustinMason:
http://wiki.apache.org/spamassassin/Release310Schedule

The comment on the change is:
updating schedule with brown-bag moment details and new proposal

------------------------------------------------------------------------------
  
   * IN PROGRESS: Mon, 2005-06-27 to Wed, 2005-07-06: start mass-checks; move to C-T-R: [http://article.gmane.org/gmane.mail.spam.spamassassin.devel/37991 3.1.0pre2 cut], [http://article.gmane.org/gmane.mail.spam.spamassassin.devel/37992 mass-checks started].
  
-  * Wed, 2005-07-06: (Monday is July 4, let's wait 'til a little after that weekend!  Also, Theo has suggested moving this date out a couple of days, this may indeed change slightly.): collate mass-check results, generate logs for all scoresets from those (Daniel, we can now get all scoresets from one mass-check run, right?) Start perceptron, check in results (will almost definitely need Henry's help here)
+  * Fri, 2005-07-01: mass-checks scratched, due to mass-check-affecting bug: bug 4450
  
-  * Wed, 2005-07-06 to Wed 2005-07-13: tweak those scores if necessary.
+  * Fri, 2005-07-01 to Mon 2005-07-11: '''proposed''' new duration of mass-checks, using 3.1.0-pre3.
  
-  * Wed 2005-07-13: decide whether to release or delay an (optional) additional week, to 2005-07-20.
+  * Wed, 2005-07-11: (Monday is July 4, let's wait 'til a little after that weekend!  Also, Theo has suggested moving this date out a couple of days, this may indeed change slightly.): collate mass-check results, generate logs for all scoresets from those (Daniel, we can now get all scoresets from one mass-check run, right?) Start perceptron, check in results (will almost definitely need Henry's help here)
  
+  * Wed, 2005-07-11 to Wed 2005-07-18: tweak those scores if necessary.
+ 
+  * Wed 2005-07-18: decide whether to release or delay an (optional) additional week.
+