[jira] [Commented] (OFBIZ-5604) Add nextTask field to production
run declaration form dependent on time entry additions
[ https://issues.apache.org/jira/browse/OFBIZ-5604?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13978013#comment-13978013 ]
Pierre Smits commented on OFBIZ-5604:
-------------------------------------
This is related to the manufacturing component.
> Add nextTask field to production run declaration form dependent on time entry additions
> ---------------------------------------------------------------------------------------
>
> Key: OFBIZ-5604
> URL: https://issues.apache.org/jira/browse/OFBIZ-5604
> Project: OFBiz
> Issue Type: Improvement
> Affects Versions: SVN trunk
> Reporter: Christian Carlow
>
> I'm faced with the challenge of recreating a company's WIP report using OFBiz manufacturing data. The purpose of the WIP report in OFBiz terms is to indicate how many pieces have moved to fixed assets by a previous task declaration based on the time entry functionality added in OFBIZ-5532. I propose adding an additional nextTaskId field dependent on the added time entry functionality to generate an inventory list for production run task fixed assets.
> For example:
> Given a production run with 3 tasks all with differing fixed assets and able to be performed in any order, if a user creates a timeEntry declaration for task1 and sets the nextTaskId to task3 then I could generate a WIP report indicating that the quantityProduced exists at the fixedAsset of task3.
--
This message was sent by Atlassian JIRA
(v6.2#6252)