[DISCUSS] Planning Flink 2.3

Hi everyone,

I'd like to start the discussion of the next release, Flink 2.3.

- Release Managers

I'd like to volunteer as one of the release managers, along with Hao Li.
Rui Fan has offered to help us with the steps that require PMC permission.

It has been good practice to have a team of release managers from different
backgrounds, so please raise your hand if you'd like to volunteer and get
involved.

- Timeline

Flink 2.2 was released at the beginning of December 2025. With a target
release cycle of 4 months, we propose a feature freeze date of Feb 28,
2026, targeting a final release at the end of March 2026.

- Collecting Features

As usual, we've created a wiki page[1] for collecting new features in 2.3.

Once the release management team is finalized, we will setup the Jira
Boards and Sync meetings to make it easy for everyone to get an overview
and track progress.

Best,
David

[1] https://cwiki.apache.org/confluence/x/eYU8G

Re: [DISCUSS] Planning Flink 2.3

Posted by David Anderson <da...@apache.org>.
We will start having regular release sync meetings for Flink 2.3 right
after the Spring Festival.

The meetings will be on Tuesday afternoons/evenings in the US / Wednesday
mornings in China, with the first meeting at 4pm PST (UTC-8) on February
24, which is 8am CST (UTC+8) on February 25. As usual, we'll use Google
Meet [1].

[1] https://meet.google.com/trj-nuqx-vzv

David

On Thu, Jan 22, 2026 at 11:53 PM Jark Wu <im...@gmail.com> wrote:

> Thanks for kicking off the 2.3 release.
>
> +1 for the revised timeline and the RMs.
>
> Best,
> Jark
>
> On Fri, 23 Jan 2026 at 04:54, Ferenc Csaky <fe...@pm.me> wrote:
> >
> > Thanks for kicking this off David!
> >
> > +1 for the revised timeline and release managers.
> >
> > Best,
> > Ferenc
> >
> >
> >
> > On Thursday, January 22nd, 2026 at 16:17, David Anderson <
> danderson@apache.org> wrote:
> >
> > >
> > >
> > > I agree that it makes sense to extend the timeframe for this release,
> and
> > > I've updated the wiki [1] accordingly. This moves the feature freeze to
> > > March 31, 2026, and the final release to the end of April.
> > >
> > > Thank you, Yuepeng Pan, for offering to help. Happy to have you!
> > >
> > > [1] https://cwiki.apache.org/confluence/x/eYU8G
> > >
> > > On Thu, Jan 22, 2026 at 3:21 AM Yuepeng Pan hipanyuepeng@gmail.com
> wrote:
> > >
> > > > Thanks David for kicking off this version.
> > > >
> > > > I briefly reviewed the number of FLIPs mentioned in the mailing list
> since
> > > > the release of Flink 2.2,
> > > > and there appear to be about ten [1]. Although not all of these are
> > > > necessarily planned for the 2.3 release,
> > > > several FLIPs have already entered the development phase.
> > > > This may give a preliminary sense of the workload scope and the
> > > > developer/user communities involved.
> > > > So +1 for extending both the release timeline and the feature freeze
> > > > deadline
> > > > to mitigate the potential time and workload risks posed by the
> upcoming
> > > > holidays.
> > > >
> > > > Additionally, I'd like to volunteer as one of the release managers
> this
> > > > time, too.
> > > >
> > > > [1] https://lists.apache.org/list?dev@flink.apache.org:lte=1M:FLIP-
> > > >
> > > > Best regards,
> > > > Yuepeng Pan
> > > >
> > > > Rui Fan 1996fanrui@gmail.com 于2026年1月22日周四 16:48写道:
> > > >
> > > > > Hey David and Hao,
> > > > >
> > > > > Thanks for driving the 2.3 release.
> > > > >
> > > > > Would it be feasible to push back both the feature freeze and the
> final
> > > > > release by one month? I’d like to propose this for two reasons:
> > > > >
> > > > > 1. Tight Schedule for FLIPs: The current one-month window until the
> > > > > feature
> > > > > freeze is quite tight for many of the ongoing FLIPs.
> > > > > 2. Holiday Impact on Community Availability: This release cycle
> coincides
> > > > > with several major holidays, including Christmas, New Year, and the
> > > > > Lunar(Chinese) New Year (Feb 17-23). These breaks will inevitably
> limit
> > > > > the
> > > > > bandwidth of many contributors and reviewers right before the
> freeze
> > > > > date.
> > > > >
> > > > > Given these factors, a one-month extension might help ensure a more
> > > > > stable
> > > > > and high-quality release.
> > > > >
> > > > > I would love to hear the community's thoughts on this.
> > > > >
> > > > > Best,
> > > > > Rui
> > > > >
> > > > > On Wed, Jan 21, 2026 at 10:43 PM David Anderson
> danderson@apache.org
> > > > > wrote:
> > > > >
> > > > > > Hi everyone,
> > > > > >
> > > > > > I'd like to start the discussion of the next release, Flink 2.3.
> > > > > >
> > > > > > - Release Managers
> > > > > >
> > > > > > I'd like to volunteer as one of the release managers, along with
> Hao
> > > > > > Li.
> > > > > > Rui Fan has offered to help us with the steps that require PMC
> > > > > > permission.
> > > > > >
> > > > > > It has been good practice to have a team of release managers from
> > > > > > different
> > > > > > backgrounds, so please raise your hand if you'd like to
> volunteer and
> > > > > > get
> > > > > > involved.
> > > > > >
> > > > > > - Timeline
> > > > > >
> > > > > > Flink 2.2 was released at the beginning of December 2025. With a
> target
> > > > > > release cycle of 4 months, we propose a feature freeze date of
> Feb 28,
> > > > > > 2026, targeting a final release at the end of March 2026.
> > > > > >
> > > > > > - Collecting Features
> > > > > >
> > > > > > As usual, we've created a wiki page[1] for collecting new
> features in
> > > > > > 2.3.
> > > > > >
> > > > > > Once the release management team is finalized, we will setup the
> Jira
> > > > > > Boards and Sync meetings to make it easy for everyone to get an
> > > > > > overview
> > > > > > and track progress.
> > > > > >
> > > > > > Best,
> > > > > > David
> > > > > >
> > > > > > [1] https://cwiki.apache.org/confluence/x/eYU8G
>

Re: [DISCUSS] Planning Flink 2.3

Posted by Jark Wu <im...@gmail.com>.
Thanks for kicking off the 2.3 release.

+1 for the revised timeline and the RMs.

Best,
Jark

On Fri, 23 Jan 2026 at 04:54, Ferenc Csaky <fe...@pm.me> wrote:
>
> Thanks for kicking this off David!
>
> +1 for the revised timeline and release managers.
>
> Best,
> Ferenc
>
>
>
> On Thursday, January 22nd, 2026 at 16:17, David Anderson <da...@apache.org> wrote:
>
> >
> >
> > I agree that it makes sense to extend the timeframe for this release, and
> > I've updated the wiki [1] accordingly. This moves the feature freeze to
> > March 31, 2026, and the final release to the end of April.
> >
> > Thank you, Yuepeng Pan, for offering to help. Happy to have you!
> >
> > [1] https://cwiki.apache.org/confluence/x/eYU8G
> >
> > On Thu, Jan 22, 2026 at 3:21 AM Yuepeng Pan hipanyuepeng@gmail.com wrote:
> >
> > > Thanks David for kicking off this version.
> > >
> > > I briefly reviewed the number of FLIPs mentioned in the mailing list since
> > > the release of Flink 2.2,
> > > and there appear to be about ten [1]. Although not all of these are
> > > necessarily planned for the 2.3 release,
> > > several FLIPs have already entered the development phase.
> > > This may give a preliminary sense of the workload scope and the
> > > developer/user communities involved.
> > > So +1 for extending both the release timeline and the feature freeze
> > > deadline
> > > to mitigate the potential time and workload risks posed by the upcoming
> > > holidays.
> > >
> > > Additionally, I'd like to volunteer as one of the release managers this
> > > time, too.
> > >
> > > [1] https://lists.apache.org/list?dev@flink.apache.org:lte=1M:FLIP-
> > >
> > > Best regards,
> > > Yuepeng Pan
> > >
> > > Rui Fan 1996fanrui@gmail.com 于2026年1月22日周四 16:48写道:
> > >
> > > > Hey David and Hao,
> > > >
> > > > Thanks for driving the 2.3 release.
> > > >
> > > > Would it be feasible to push back both the feature freeze and the final
> > > > release by one month? I’d like to propose this for two reasons:
> > > >
> > > > 1. Tight Schedule for FLIPs: The current one-month window until the
> > > > feature
> > > > freeze is quite tight for many of the ongoing FLIPs.
> > > > 2. Holiday Impact on Community Availability: This release cycle coincides
> > > > with several major holidays, including Christmas, New Year, and the
> > > > Lunar(Chinese) New Year (Feb 17-23). These breaks will inevitably limit
> > > > the
> > > > bandwidth of many contributors and reviewers right before the freeze
> > > > date.
> > > >
> > > > Given these factors, a one-month extension might help ensure a more
> > > > stable
> > > > and high-quality release.
> > > >
> > > > I would love to hear the community's thoughts on this.
> > > >
> > > > Best,
> > > > Rui
> > > >
> > > > On Wed, Jan 21, 2026 at 10:43 PM David Anderson danderson@apache.org
> > > > wrote:
> > > >
> > > > > Hi everyone,
> > > > >
> > > > > I'd like to start the discussion of the next release, Flink 2.3.
> > > > >
> > > > > - Release Managers
> > > > >
> > > > > I'd like to volunteer as one of the release managers, along with Hao
> > > > > Li.
> > > > > Rui Fan has offered to help us with the steps that require PMC
> > > > > permission.
> > > > >
> > > > > It has been good practice to have a team of release managers from
> > > > > different
> > > > > backgrounds, so please raise your hand if you'd like to volunteer and
> > > > > get
> > > > > involved.
> > > > >
> > > > > - Timeline
> > > > >
> > > > > Flink 2.2 was released at the beginning of December 2025. With a target
> > > > > release cycle of 4 months, we propose a feature freeze date of Feb 28,
> > > > > 2026, targeting a final release at the end of March 2026.
> > > > >
> > > > > - Collecting Features
> > > > >
> > > > > As usual, we've created a wiki page[1] for collecting new features in
> > > > > 2.3.
> > > > >
> > > > > Once the release management team is finalized, we will setup the Jira
> > > > > Boards and Sync meetings to make it easy for everyone to get an
> > > > > overview
> > > > > and track progress.
> > > > >
> > > > > Best,
> > > > > David
> > > > >
> > > > > [1] https://cwiki.apache.org/confluence/x/eYU8G

Re: [DISCUSS] Planning Flink 2.3

Posted by Ferenc Csaky <fe...@pm.me>.
Thanks for kicking this off David!

+1 for the revised timeline and release managers.

Best,
Ferenc



On Thursday, January 22nd, 2026 at 16:17, David Anderson <da...@apache.org> wrote:

> 
> 
> I agree that it makes sense to extend the timeframe for this release, and
> I've updated the wiki [1] accordingly. This moves the feature freeze to
> March 31, 2026, and the final release to the end of April.
> 
> Thank you, Yuepeng Pan, for offering to help. Happy to have you!
> 
> [1] https://cwiki.apache.org/confluence/x/eYU8G
> 
> On Thu, Jan 22, 2026 at 3:21 AM Yuepeng Pan hipanyuepeng@gmail.com wrote:
> 
> > Thanks David for kicking off this version.
> > 
> > I briefly reviewed the number of FLIPs mentioned in the mailing list since
> > the release of Flink 2.2,
> > and there appear to be about ten [1]. Although not all of these are
> > necessarily planned for the 2.3 release,
> > several FLIPs have already entered the development phase.
> > This may give a preliminary sense of the workload scope and the
> > developer/user communities involved.
> > So +1 for extending both the release timeline and the feature freeze
> > deadline
> > to mitigate the potential time and workload risks posed by the upcoming
> > holidays.
> > 
> > Additionally, I'd like to volunteer as one of the release managers this
> > time, too.
> > 
> > [1] https://lists.apache.org/list?dev@flink.apache.org:lte=1M:FLIP-
> > 
> > Best regards,
> > Yuepeng Pan
> > 
> > Rui Fan 1996fanrui@gmail.com 于2026年1月22日周四 16:48写道:
> > 
> > > Hey David and Hao,
> > > 
> > > Thanks for driving the 2.3 release.
> > > 
> > > Would it be feasible to push back both the feature freeze and the final
> > > release by one month? I’d like to propose this for two reasons:
> > > 
> > > 1. Tight Schedule for FLIPs: The current one-month window until the
> > > feature
> > > freeze is quite tight for many of the ongoing FLIPs.
> > > 2. Holiday Impact on Community Availability: This release cycle coincides
> > > with several major holidays, including Christmas, New Year, and the
> > > Lunar(Chinese) New Year (Feb 17-23). These breaks will inevitably limit
> > > the
> > > bandwidth of many contributors and reviewers right before the freeze
> > > date.
> > > 
> > > Given these factors, a one-month extension might help ensure a more
> > > stable
> > > and high-quality release.
> > > 
> > > I would love to hear the community's thoughts on this.
> > > 
> > > Best,
> > > Rui
> > > 
> > > On Wed, Jan 21, 2026 at 10:43 PM David Anderson danderson@apache.org
> > > wrote:
> > > 
> > > > Hi everyone,
> > > > 
> > > > I'd like to start the discussion of the next release, Flink 2.3.
> > > > 
> > > > - Release Managers
> > > > 
> > > > I'd like to volunteer as one of the release managers, along with Hao
> > > > Li.
> > > > Rui Fan has offered to help us with the steps that require PMC
> > > > permission.
> > > > 
> > > > It has been good practice to have a team of release managers from
> > > > different
> > > > backgrounds, so please raise your hand if you'd like to volunteer and
> > > > get
> > > > involved.
> > > > 
> > > > - Timeline
> > > > 
> > > > Flink 2.2 was released at the beginning of December 2025. With a target
> > > > release cycle of 4 months, we propose a feature freeze date of Feb 28,
> > > > 2026, targeting a final release at the end of March 2026.
> > > > 
> > > > - Collecting Features
> > > > 
> > > > As usual, we've created a wiki page[1] for collecting new features in
> > > > 2.3.
> > > > 
> > > > Once the release management team is finalized, we will setup the Jira
> > > > Boards and Sync meetings to make it easy for everyone to get an
> > > > overview
> > > > and track progress.
> > > > 
> > > > Best,
> > > > David
> > > > 
> > > > [1] https://cwiki.apache.org/confluence/x/eYU8G

Re: [DISCUSS] Planning Flink 2.3

Posted by David Anderson <da...@apache.org>.
I agree that it makes sense to extend the timeframe for this release, and
I've updated the wiki [1] accordingly. This moves the feature freeze to
March 31, 2026, and the final release to the end of April.

Thank you, Yuepeng Pan, for offering to help. Happy to have you!

[1] https://cwiki.apache.org/confluence/x/eYU8G

On Thu, Jan 22, 2026 at 3:21 AM Yuepeng Pan <hi...@gmail.com> wrote:

> Thanks David for kicking off this version.
>
> I briefly reviewed the number of FLIPs mentioned in the mailing list since
> the release of Flink 2.2,
> and there appear to be about ten [1]. Although not all of these are
> necessarily planned for the 2.3 release,
> several FLIPs have already entered the development phase.
> This may give a preliminary sense of the workload scope and the
> developer/user communities involved.
> So +1 for extending both the release timeline and the feature freeze
> deadline
> to mitigate the potential time and workload risks posed by the upcoming
> holidays.
>
> Additionally, I'd like to volunteer as one of the release managers this
> time, too.
>
> [1] https://lists.apache.org/list?dev@flink.apache.org:lte=1M:FLIP-
>
> Best regards,
> Yuepeng Pan
>
> Rui Fan <19...@gmail.com> 于2026年1月22日周四 16:48写道:
>
> > Hey David and Hao,
> >
> > Thanks for driving the 2.3 release.
> >
> > Would it be feasible to push back both the feature freeze and the final
> > release by one month? I’d like to propose this for two reasons:
> >
> > 1. Tight Schedule for FLIPs: The current one-month window until the
> feature
> > freeze is quite tight for many of the ongoing FLIPs.
> > 2. Holiday Impact on Community Availability: This release cycle coincides
> > with several major holidays, including Christmas, New Year, and the
> > Lunar(Chinese) New Year (Feb 17-23). These breaks will inevitably limit
> the
> > bandwidth of many contributors and reviewers right before the freeze
> date.
> >
> > Given these factors, a one-month extension might help ensure a more
> stable
> > and high-quality release.
> >
> > I would love to hear the community's thoughts on this.
> >
> > Best,
> > Rui
> >
> > On Wed, Jan 21, 2026 at 10:43 PM David Anderson <da...@apache.org>
> > wrote:
> >
> > > Hi everyone,
> > >
> > > I'd like to start the discussion of the next release, Flink 2.3.
> > >
> > > - Release Managers
> > >
> > > I'd like to volunteer as one of the release managers, along with Hao
> Li.
> > > Rui Fan has offered to help us with the steps that require PMC
> > permission.
> > >
> > > It has been good practice to have a team of release managers from
> > different
> > > backgrounds, so please raise your hand if you'd like to volunteer and
> get
> > > involved.
> > >
> > > - Timeline
> > >
> > > Flink 2.2 was released at the beginning of December 2025. With a target
> > > release cycle of 4 months, we propose a feature freeze date of Feb 28,
> > > 2026, targeting a final release at the end of March 2026.
> > >
> > > - Collecting Features
> > >
> > > As usual, we've created a wiki page[1] for collecting new features in
> > 2.3.
> > >
> > > Once the release management team is finalized, we will setup the Jira
> > > Boards and Sync meetings to make it easy for everyone to get an
> overview
> > > and track progress.
> > >
> > > Best,
> > > David
> > >
> > > [1] https://cwiki.apache.org/confluence/x/eYU8G
> > >
> >
>

Re: [DISCUSS] Planning Flink 2.3

Posted by Yuepeng Pan <hi...@gmail.com>.
Thanks David for kicking off this version.

I briefly reviewed the number of FLIPs mentioned in the mailing list since
the release of Flink 2.2,
and there appear to be about ten [1]. Although not all of these are
necessarily planned for the 2.3 release,
several FLIPs have already entered the development phase.
This may give a preliminary sense of the workload scope and the
developer/user communities involved.
So +1 for extending both the release timeline and the feature freeze
deadline
to mitigate the potential time and workload risks posed by the upcoming
holidays.

Additionally, I'd like to volunteer as one of the release managers this
time, too.

[1] https://lists.apache.org/list?dev@flink.apache.org:lte=1M:FLIP-

Best regards,
Yuepeng Pan

Rui Fan <19...@gmail.com> 于2026年1月22日周四 16:48写道:

> Hey David and Hao,
>
> Thanks for driving the 2.3 release.
>
> Would it be feasible to push back both the feature freeze and the final
> release by one month? I’d like to propose this for two reasons:
>
> 1. Tight Schedule for FLIPs: The current one-month window until the feature
> freeze is quite tight for many of the ongoing FLIPs.
> 2. Holiday Impact on Community Availability: This release cycle coincides
> with several major holidays, including Christmas, New Year, and the
> Lunar(Chinese) New Year (Feb 17-23). These breaks will inevitably limit the
> bandwidth of many contributors and reviewers right before the freeze date.
>
> Given these factors, a one-month extension might help ensure a more stable
> and high-quality release.
>
> I would love to hear the community's thoughts on this.
>
> Best,
> Rui
>
> On Wed, Jan 21, 2026 at 10:43 PM David Anderson <da...@apache.org>
> wrote:
>
> > Hi everyone,
> >
> > I'd like to start the discussion of the next release, Flink 2.3.
> >
> > - Release Managers
> >
> > I'd like to volunteer as one of the release managers, along with Hao Li.
> > Rui Fan has offered to help us with the steps that require PMC
> permission.
> >
> > It has been good practice to have a team of release managers from
> different
> > backgrounds, so please raise your hand if you'd like to volunteer and get
> > involved.
> >
> > - Timeline
> >
> > Flink 2.2 was released at the beginning of December 2025. With a target
> > release cycle of 4 months, we propose a feature freeze date of Feb 28,
> > 2026, targeting a final release at the end of March 2026.
> >
> > - Collecting Features
> >
> > As usual, we've created a wiki page[1] for collecting new features in
> 2.3.
> >
> > Once the release management team is finalized, we will setup the Jira
> > Boards and Sync meetings to make it easy for everyone to get an overview
> > and track progress.
> >
> > Best,
> > David
> >
> > [1] https://cwiki.apache.org/confluence/x/eYU8G
> >
>

Re: [DISCUSS] Planning Flink 2.3

Posted by Rui Fan <19...@gmail.com>.
Hey David and Hao,

Thanks for driving the 2.3 release.

Would it be feasible to push back both the feature freeze and the final
release by one month? I’d like to propose this for two reasons:

1. Tight Schedule for FLIPs: The current one-month window until the feature
freeze is quite tight for many of the ongoing FLIPs.
2. Holiday Impact on Community Availability: This release cycle coincides
with several major holidays, including Christmas, New Year, and the
Lunar(Chinese) New Year (Feb 17-23). These breaks will inevitably limit the
bandwidth of many contributors and reviewers right before the freeze date.

Given these factors, a one-month extension might help ensure a more stable
and high-quality release.

I would love to hear the community's thoughts on this.

Best,
Rui

On Wed, Jan 21, 2026 at 10:43 PM David Anderson <da...@apache.org>
wrote:

> Hi everyone,
>
> I'd like to start the discussion of the next release, Flink 2.3.
>
> - Release Managers
>
> I'd like to volunteer as one of the release managers, along with Hao Li.
> Rui Fan has offered to help us with the steps that require PMC permission.
>
> It has been good practice to have a team of release managers from different
> backgrounds, so please raise your hand if you'd like to volunteer and get
> involved.
>
> - Timeline
>
> Flink 2.2 was released at the beginning of December 2025. With a target
> release cycle of 4 months, we propose a feature freeze date of Feb 28,
> 2026, targeting a final release at the end of March 2026.
>
> - Collecting Features
>
> As usual, we've created a wiki page[1] for collecting new features in 2.3.
>
> Once the release management team is finalized, we will setup the Jira
> Boards and Sync meetings to make it easy for everyone to get an overview
> and track progress.
>
> Best,
> David
>
> [1] https://cwiki.apache.org/confluence/x/eYU8G
>

Re: [DISCUSS] Planning Flink 2.3

Posted by Leonard Xu <xb...@gmail.com>.
Thanks David for kicking off this version. +1 for the proposed release manager candidates.

Considering that this version's development cycle includes several long holidays—Christmas, New Year's, and Spring Festival—I'm considering whether we could extend the development time by an extra month?

Best,
Leonard



> 2026 1月 22 05:43,David Anderson <da...@apache.org> 写道:
> 
> Hi everyone,
> 
> I'd like to start the discussion of the next release, Flink 2.3.
> 
> - Release Managers
> 
> I'd like to volunteer as one of the release managers, along with Hao Li.
> Rui Fan has offered to help us with the steps that require PMC permission.
> 
> It has been good practice to have a team of release managers from different
> backgrounds, so please raise your hand if you'd like to volunteer and get
> involved.
> 
> - Timeline
> 
> Flink 2.2 was released at the beginning of December 2025. With a target
> release cycle of 4 months, we propose a feature freeze date of Feb 28,
> 2026, targeting a final release at the end of March 2026.
> 
> - Collecting Features
> 
> As usual, we've created a wiki page[1] for collecting new features in 2.3.
> 
> Once the release management team is finalized, we will setup the Jira
> Boards and Sync meetings to make it easy for everyone to get an overview
> and track progress.
> 
> Best,
> David
> 
> [1] https://cwiki.apache.org/confluence/x/eYU8G