Dashboard for the Composite Application based on status changes

Hi all,

Can we have $subject?

When having more than one group/cartridges in an application, it is really
hard to predict the flow by going through the logs, since there are lot of
logs in the single JVM. We are unable to cut down the logs as we may need
it when deploying stratos as a distributed setup.

If there is dashboard which would explain the execution flow of the
components in the application, then we can easily debug/get more
information regarding the execution of the application based on the given
behaviours such as start order and termination behaviour. Specially when
there is a faulty member detection, all the dependent groups/clusters will
be terminated and coming up again. We are unable to validate the flow by
going through the logs, since there are more than 100 lines for this case.
It would be nice for a user/developer to go through the dashboard and
confirm on the execution flow. Or can we have any other approach where
users can validate their execution of the application rather than going
through the logs?


Thanks,
Reka


-- 
Reka Thirunavukkarasu
Senior Software Engineer,
WSO2, Inc.:http://wso2.com,
Mobile: +94776442007

Re: Dashboard for the Composite Application based on status changes

Posted by Dakshika Jayathilaka <da...@wso2.com>.
Hi All,

I'm working on this. seems we need graphical tree representation. I'm
checking on *Tree Drawing Algorithms* which can be apply for above
scenario.

Also we need to identify factors that we want to show on each node.

I'll update the status soon.

Thank you,

*Dakshika Jayathilaka*
Software Engineer
WSO2, Inc.
lean.enterprise.middleware
0771100911

On Mon, Nov 17, 2014 at 10:37 AM, Reka Thirunavukkarasu <re...@wso2.com>
wrote:

> Hi Chamila,
>
> On Mon, Nov 17, 2014 at 3:30 AM, Chamila De Alwis <ch...@wso2.com>
> wrote:
>
>> Hi Reka,
>>
>> Would this dashboard reflect the status of a particular application in
>> real time or is it an analysis of a (say) certain set of lines of logs
>> entries?
>>
>
> This application will reflect the status of an application and its
> components in the real time..
>
> Thanks,
> Reka
>
>>
>>
>> Regards,
>> Chamila de Alwis
>> Software Engineer | WSO2 | +94772207163
>> Blog: code.chamiladealwis.com
>>
>>
>>
>> On Sun, Nov 16, 2014 at 2:35 PM, Reka Thirunavukkarasu <re...@wso2.com>
>> wrote:
>>
>>> Hi all,
>>>
>>> Can we have $subject?
>>>
>>> When having more than one group/cartridges in an application, it is
>>> really hard to predict the flow by going through the logs, since there are
>>> lot of logs in the single JVM. We are unable to cut down the logs as we may
>>> need it when deploying stratos as a distributed setup.
>>>
>>> If there is dashboard which would explain the execution flow of the
>>> components in the application, then we can easily debug/get more
>>> information regarding the execution of the application based on the given
>>> behaviours such as start order and termination behaviour. Specially when
>>> there is a faulty member detection, all the dependent groups/clusters will
>>> be terminated and coming up again. We are unable to validate the flow by
>>> going through the logs, since there are more than 100 lines for this case.
>>> It would be nice for a user/developer to go through the dashboard and
>>> confirm on the execution flow. Or can we have any other approach where
>>> users can validate their execution of the application rather than going
>>> through the logs?
>>>
>>>
>>> Thanks,
>>> Reka
>>>
>>>
>>> --
>>> Reka Thirunavukkarasu
>>> Senior Software Engineer,
>>> WSO2, Inc.:http://wso2.com,
>>> Mobile: +94776442007
>>>
>>>
>>>
>>
>
>
> --
> Reka Thirunavukkarasu
> Senior Software Engineer,
> WSO2, Inc.:http://wso2.com,
> Mobile: +94776442007
>
>
>

Re: Dashboard for the Composite Application based on status changes

Posted by Reka Thirunavukkarasu <re...@wso2.com>.
Hi Chamila,

On Mon, Nov 17, 2014 at 3:30 AM, Chamila De Alwis <ch...@wso2.com> wrote:

> Hi Reka,
>
> Would this dashboard reflect the status of a particular application in
> real time or is it an analysis of a (say) certain set of lines of logs
> entries?
>

This application will reflect the status of an application and its
components in the real time..

Thanks,
Reka

>
>
> Regards,
> Chamila de Alwis
> Software Engineer | WSO2 | +94772207163
> Blog: code.chamiladealwis.com
>
>
>
> On Sun, Nov 16, 2014 at 2:35 PM, Reka Thirunavukkarasu <re...@wso2.com>
> wrote:
>
>> Hi all,
>>
>> Can we have $subject?
>>
>> When having more than one group/cartridges in an application, it is
>> really hard to predict the flow by going through the logs, since there are
>> lot of logs in the single JVM. We are unable to cut down the logs as we may
>> need it when deploying stratos as a distributed setup.
>>
>> If there is dashboard which would explain the execution flow of the
>> components in the application, then we can easily debug/get more
>> information regarding the execution of the application based on the given
>> behaviours such as start order and termination behaviour. Specially when
>> there is a faulty member detection, all the dependent groups/clusters will
>> be terminated and coming up again. We are unable to validate the flow by
>> going through the logs, since there are more than 100 lines for this case.
>> It would be nice for a user/developer to go through the dashboard and
>> confirm on the execution flow. Or can we have any other approach where
>> users can validate their execution of the application rather than going
>> through the logs?
>>
>>
>> Thanks,
>> Reka
>>
>>
>> --
>> Reka Thirunavukkarasu
>> Senior Software Engineer,
>> WSO2, Inc.:http://wso2.com,
>> Mobile: +94776442007
>>
>>
>>
>


-- 
Reka Thirunavukkarasu
Senior Software Engineer,
WSO2, Inc.:http://wso2.com,
Mobile: +94776442007

Re: Dashboard for the Composite Application based on status changes

Posted by Chamila De Alwis <ch...@wso2.com>.
Hi Reka,

Would this dashboard reflect the status of a particular application in real
time or is it an analysis of a (say) certain set of lines of logs entries?


Regards,
Chamila de Alwis
Software Engineer | WSO2 | +94772207163
Blog: code.chamiladealwis.com



On Sun, Nov 16, 2014 at 2:35 PM, Reka Thirunavukkarasu <re...@wso2.com>
wrote:

> Hi all,
>
> Can we have $subject?
>
> When having more than one group/cartridges in an application, it is really
> hard to predict the flow by going through the logs, since there are lot of
> logs in the single JVM. We are unable to cut down the logs as we may need
> it when deploying stratos as a distributed setup.
>
> If there is dashboard which would explain the execution flow of the
> components in the application, then we can easily debug/get more
> information regarding the execution of the application based on the given
> behaviours such as start order and termination behaviour. Specially when
> there is a faulty member detection, all the dependent groups/clusters will
> be terminated and coming up again. We are unable to validate the flow by
> going through the logs, since there are more than 100 lines for this case.
> It would be nice for a user/developer to go through the dashboard and
> confirm on the execution flow. Or can we have any other approach where
> users can validate their execution of the application rather than going
> through the logs?
>
>
> Thanks,
> Reka
>
>
> --
> Reka Thirunavukkarasu
> Senior Software Engineer,
> WSO2, Inc.:http://wso2.com,
> Mobile: +94776442007
>
>
>