You are viewing a plain text version of this content. The canonical link for it is here.
Posted to users@maven.apache.org by Veit Guna <Ve...@gmx.de> on 2017/10/02 10:12:25 UTC
failsafe: proper shutdown on failure
Hi.
I'm using maven failsafe 2.20.1 to setup my test environment (redis, via fabric8/docker-maven-plugin) before ITs using pre-integration-test and shut it down on post-integration-test. It works just fine when tests are succeeding or failing "normally". But when failing "hard" like this:
[ERROR] Failed to execute goal org.apache.maven.plugins:maven-failsafe-plugin:2.18.1:integration-test (default) on project crs-it: Execution default of goal org.apache.maven.plugins:maven-failsafe-plugin:2.18.1:integration-test failed: There was an error in the forked process
[ERROR] org.testng.TestNGException:
Due to some class not found exceptions,
or just executing:
mvn clean verify -Dit.test=nonExistingTest
It seems that post-integration-test phase isn't executed properly then, leaving my docker container still running.
Is this expected behavior? If so, how can I make sure that my services startup in pre-integration-test phase are properly shutdown?
I setup my pom.xml according to failsafe documentation:
<build>
<plugins>
<plugin>
<artifactId>maven-failsafe-plugin</artifactId>
<version>2.20.1</version>
<executions>
<execution>
<goals>
<goal>integration-test</goal>
<goal>verify</goal>
</goals>
</execution>
</executions>
</plugin>
<!-- local redis -->
<plugin>
<groupId>io.fabric8</groupId>
<artifactId>docker-maven-plugin</artifactId>
<version>0.22.1</version>
<configuration>
<skip>${skipITs}</skip>
<images>
<image>
<name>redis</name>
<alias>redis</alias>
<run>
<ports>
<port>${redis.port}:6379</port>
</ports>
<wait>
<tcp>
<host>127.0.0.1</host>
<ports>
<port>${redis.port}</port>
</ports>
</tcp>
</wait>
</run>
</image>
</images>
</configuration>
<executions>
<execution>
<id>start</id>
<phase>pre-integration-test</phase>
<goals>
<goal>build</goal>
<goal>start</goal>
</goals>
</execution>
<execution>
<id>stop</id>
<phase>post-integration-test</phase>
<goals>
<goal>stop</goal>
</goals>
</execution>
</executions>
</plugin>
</plugins>
</build>
---------------------------------------------------------------------
To unsubscribe, e-mail: users-unsubscribe@maven.apache.org
For additional commands, e-mail: users-help@maven.apache.org
Aw: Re: failsafe: proper shutdown on failure
Posted by Veit Guna <Ve...@gmx.de>.
Hi Mark.
I've tried -fae but without luck.
When the build system is halted, shouldn't at least the post-integration-test phase properly executed in order to be consistent?
I also have a cargo container running during ITs which gets "shutdown" during halt - but most likely due to the fact that
the JVM is killed. Docker runs in a separate process so it isn't affected by the JVM shutdown. Hence it is still running.
> Gesendet: Montag, 02. Oktober 2017 um 17:04 Uhr
> Von: "Mark Prins" <mc...@gmail.com>
> An: users@maven.apache.org
> Betreff: Re: failsafe: proper shutdown on failure
>
> On 02-10-17 12:12, Veit Guna wrote:
> > Hi.
> >
> > I'm using maven failsafe 2.20.1 to setup my test environment (redis, via fabric8/docker-maven-plugin) before ITs using pre-integration-test and shut it down on post-integration-test. It works just fine when tests are succeeding or failing "normally". But when failing "hard" like this:
> >
> > [ERROR] Failed to execute goal org.apache.maven.plugins:maven-failsafe-plugin:2.18.1:integration-test (default) on project crs-it: Execution default of goal org.apache.maven.plugins:maven-failsafe-plugin:2.18.1:integration-test failed: There was an error in the forked process
> > [ERROR] org.testng.TestNGException:
> >
> > Due to some class not found exceptions,
> >
> > or just executing:
> >
> > mvn clean verify -Dit.test=nonExistingTest
> >
> > It seems that post-integration-test phase isn't executed properly then, leaving my docker container still running.
>
> I think the build is halted after the failure, so no further phases are
> processed. Using "-fae" (fail-at-end) may help, but I may be wrong.
>
> Mark
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: users-unsubscribe@maven.apache.org
> For additional commands, e-mail: users-help@maven.apache.org
>
>
---------------------------------------------------------------------
To unsubscribe, e-mail: users-unsubscribe@maven.apache.org
For additional commands, e-mail: users-help@maven.apache.org
Re: failsafe: proper shutdown on failure
Posted by Mark Prins <mc...@gmail.com>.
On 02-10-17 12:12, Veit Guna wrote:
> Hi.
>
> I'm using maven failsafe 2.20.1 to setup my test environment (redis, via fabric8/docker-maven-plugin) before ITs using pre-integration-test and shut it down on post-integration-test. It works just fine when tests are succeeding or failing "normally". But when failing "hard" like this:
>
> [ERROR] Failed to execute goal org.apache.maven.plugins:maven-failsafe-plugin:2.18.1:integration-test (default) on project crs-it: Execution default of goal org.apache.maven.plugins:maven-failsafe-plugin:2.18.1:integration-test failed: There was an error in the forked process
> [ERROR] org.testng.TestNGException:
>
> Due to some class not found exceptions,
>
> or just executing:
>
> mvn clean verify -Dit.test=nonExistingTest
>
> It seems that post-integration-test phase isn't executed properly then, leaving my docker container still running.
I think the build is halted after the failure, so no further phases are
processed. Using "-fae" (fail-at-end) may help, but I may be wrong.
Mark
---------------------------------------------------------------------
To unsubscribe, e-mail: users-unsubscribe@maven.apache.org