[jira] [Created] (HBASE-10019) PerfEval mapreduce percentage
complete is inaccurate
Nick Dimiduk created HBASE-10019:
------------------------------------
Summary: PerfEval mapreduce percentage complete is inaccurate
Key: HBASE-10019
URL: https://issues.apache.org/jira/browse/HBASE-10019
Project: HBase
Issue Type: Test
Components: mapreduce, test
Affects Versions: 0.94.6.1
Reporter: Nick Dimiduk
Priority: Minor
Just noticed this while testing 0.94.14RC1. The status is tracked, updating start/n/end counts, but the complete % is 100% for the entire job. This is probably just a minor thing in the testing tool, but making a note for myself to check the MapReduce implementation to make sure it's not a deeper bug.
--