[jira] [Created] (OFBIZ-7111) Total Actual cost of production run need to be passed on to produced stock's unit cost for completed production run

Swapnil Shah created OFBIZ-7111:
-----------------------------------

             Summary: Total Actual cost of production run need to be passed on to produced stock's unit cost for completed production run
                 Key: OFBIZ-7111
                 URL: https://issues.apache.org/jira/browse/OFBIZ-7111
             Project: OFBiz
          Issue Type: New Feature
            Reporter: Swapnil Shah


Currently as soon as item is produced into inventory once production run is completed then inventory get created with ZERO unit cost. 

We could pass on the total actual cost (Material+Labor+Resource etc.) to Produced Item's inventory item i.e. = Total Actual Cost/ Produced in Stock 