Hi Oleg, all,

I haven't dug into any of the code yet, but I've read through the  
document you were working on. It seems positive and makes sense. I did  
get a bit lost on the meaning of the "Tree Builder" section as it  
doesn't seem to describe the current tree or graph technique, but  
maybe illustrate the possible combinations?

Anyway, a few things caught my attention...

You mentioned about the inconsistency of whether 3.8.1 means "must be  
3.8.1" vs "I'm using 3.8.1 right now but I'm not really sure which  
versions it works with". Pretty much everyone putting POMs together  
does the latter, as they are not trained in specifying ranges, and  
because projects do not always follow the guidelines on versioning  
such that compatibility can be measured. You also mentioned that some  
change to the way ranges are specified might be needed. I'm wondering  
what thoughts you have on how we specify dependencies need to be  
different from today?

I do think the compatibility question is an interesting one. We could  
theoretically build up a compatibility database in the central  
repository, even using clirr to make initial assessment on java  
artifacts. However this is unfortunately never a binary decision  
either, as you may not be using the incompatible parts, and  
compatibility can break in non-API ways.

I'm curious about how these work in terms of remote retrieval (ie,  
where consulting metadatasource is a costly operation). When I looked  
at p2 in Sept last year, they stored all the repository artifact  
metadata in a single, large file. Are we expecting to need some  
partial or full resolution of the repository content?

Do you think depth resolution is still relevant if we have a better  
method? I believe the only depth we really should care about is "1" -  
those immediately specified (and particularly those managed by  
depMgmt). With that in mind, how can the use of depMgmt help in  
reducing the problem space during resolution?

You also mention OSGi resolution at the end. Is it your intent that  
one of the goals of the mechanism is to be able to be a complete OSGi  
resolver?

I'm also interested in seeing explicit listing of the problems we aim  
to solve to ensure we have objectives/scope. For example:
- lack of alternate conflict resolution in current artifact mechanism
- reduction in amount of metadata and artifacts dragged in (ie, stuff  
that could use maven 2.0.9 still pulls down whatever version of maven  
it was built against, even when it's not used)
- deterministic building over time

Just my initial thoughts - I'll follow your progress as you continue  
investigating :)

Cheers,
Brett

--
Brett Porter
brett@apache.org
http://blogs.exist.com/bporter/


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Jason van Zyl <ja...@maven.org>.
On 22-Jun-08, at 12:41 AM, Ralph Goers wrote:

> Jason van Zyl wrote:
>> In the world where there is some rigour in that the said project  
>> doesn't change the API within a major release they know very well.  
>> In Eclipse a great deal of care is taken to make sure that APIs  
>> don't change within a major release of the platform and ranges in  
>> dependencies are usually specified as ranges that allow the  
>> consumption of new versions within a major release version. We're  
>> not accustom to this here at Apache because there just isn't that  
>> level of rigour yet.
> There are at least hundreds of various software projects that could  
> possibly become a dependency to a given software development  
> project. While it is great that Eclipse takes great care to maintain  
> some measure of compatibility between releases but the same can't be  
> said of the vast majority of things a project could be dependent on.  
> While it would be great to live in a Utopian world where API  
> compatibility is rarely, if ever, broken, that isn't the world we  
> will be living in for the forseeable future.

You are used to Apache, Eclipse is not a Utopia and has managed to do  
it pretty well. It's a practical upshot of dire need, it's not a "nice  
to have" when you have such a large ecosystem, it's a requirement.

>  Expecting a project to understand all the compatibility issues of  
> its dependencies is not only unreasonable and burdensome, it is  
> impossible when those dependencies can dynamically change due to  
> version ranges.
>

I disagree, there are lots of projects that have that notion  
engrained. I'm not saying that you are not free to lock down your  
version but lots of people use ranges in OSGi with commercial and  
Eclipse-based dependencies and they have success.

> Ironically, although Eclipse might take great care at maintaining  
> compatibility, none of its components have ever found their way into  
> one of my projects.
>
> While commercial vendors might be better I've encountered many of  
> the same issues with them. They will do a "major upgrade" once every  
> 18 months or so and break compatibility if it suits their needs.  
> Only point upgrades (purely bug fixes - no new features) are  
> guaranteed to be compatible. Remember, breaking compatibility  
> doesn't necessarily require an API change.

I fully understand the configuration and behavioral changes also need  
to be taken into account.

> It might involve a configuration change, a change in a database  
> schema, changes in its dependencies that impact your project in  
> other ways, etc.
>>
>>>
>>>
>>> Frankly, even if version ranges worked as above I'd still probably  
>>> not use them during a build simply because I want to specify  
>>> exactly what is used in the build.
>>
>> A lot of people probably do too, but that's not what you've been  
>> doing with the POMs you use now I'm willing to bet. Almost everyone  
>> with the mechanism we have now can be subject to exactly what you  
>> describe above without knowing it. Most people don't know the "1.0"  
>> in their POMs doesn't actually mean use "1.0" all the time.
> If that's what you think then you forget why I've been so slow in  
> actually converting my projects from Maven 1 to Maven 2 (which I  
> finally found the time to do by the way). We used the jar override  
> feature in Maven 1 to specify the version of EVERY dependency.  I  
> wasn't able to convert to Maven 2 until we could accomplish the same  
> thing - which we are now able to do in a much better way.
>
> However, if simply specifying a specific version in a managed  
> dependency doesn't guarantee that  the specified version of that  
> dependency is used then I see three problems:
> 1. The documentation isn't clear enough.
> 2. I need to modify my managed dependencies to specify the start and  
> end of the version range to the same version.
> 3. Since most people don't expect this behavior one would normally  
> consider it to be a bug. Certainly forcing people to have to do the  
> previous step is downright awful. It would be much better to provide  
> an option that forces only the specified version to be used.
>>
>>> However, it would be great to know that multiple projects have  
>>> dependencies on incompatible versions of the same thing. It would  
>>> also be great to have reports that indicate which dependencies  
>>> could be safely upgraded.
>>
>> It should be the exception that it changes in a major version.
>>
> That's all well and good but it completely misses the point. If you  
> really think that Maven can cause every possible project that a  
> project might list as a dependency to do things "correctly" you are  
> going to end up very frustrated. Maven needs to deal with the world  
> as it is.

Where did I say anything resembling the assumption that this happens  
everywhere? I'm simply stating it's not as rare as you might think.  
I'm also saying use ranges where it makes sense and there is a  
difference in how the ranges are used in development versus runtime  
and here I'm specifically talking about OSGi. After testing something  
and passing through QA it would obviously be not very useful to let  
the range calculate something differently after it had been tested.

>
>
> Again, I will reiterate. IMO, without projects declaring themselves  
> which prior versions they are compatible with no version ranging  
> scheme will ever be able to produce a build you can be even close to  
> 100% confident in. As always, you are free to disagree.

I'm not disagreeing with you, and if that is what you need then you  
just specify that known set in your dependency range. You were saying  
it's not supported in the POM, but all you need to do is state the  
values in the ranges that you know yourself to be valid for your  
project. As you update, leave the previous version in the range if you  
know it to be compatible and add the next one.

I wasn't in anyway implying the information is good enough anywhere  
but a few places to rely on the "within a major version this remains  
API (and behaviorally) compatible." rule. You learn pretty fast where  
this is possible or not.

>
>
> Ralph
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
> For additional commands, e-mail: dev-help@maven.apache.org
>

Thanks,

Jason

----------------------------------------------------------
Jason van Zyl
Founder,  Apache Maven
jason at sonatype dot com
----------------------------------------------------------

Selfish deeds are the shortest path to self destruction.

  -- The Seven Samuari, Akira Kirosawa


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Ralph Goers <Ra...@dslextreme.com>.
Jason van Zyl wrote:
> In the world where there is some rigour in that the said project 
> doesn't change the API within a major release they know very well. In 
> Eclipse a great deal of care is taken to make sure that APIs don't 
> change within a major release of the platform and ranges in 
> dependencies are usually specified as ranges that allow the 
> consumption of new versions within a major release version. We're not 
> accustom to this here at Apache because there just isn't that level of 
> rigour yet.
There are at least hundreds of various software projects that could 
possibly become a dependency to a given software development project. 
While it is great that Eclipse takes great care to maintain some measure 
of compatibility between releases but the same can't be said of the vast 
majority of things a project could be dependent on. While it would be 
great to live in a Utopian world where API compatibility is rarely, if 
ever, broken, that isn't the world we will be living in for the 
forseeable future.  Expecting a project to understand all the 
compatibility issues of its dependencies is not only unreasonable and 
burdensome, it is impossible when those dependencies can dynamically 
change due to version ranges.

Ironically, although Eclipse might take great care at maintaining 
compatibility, none of its components have ever found their way into one 
of my projects.

While commercial vendors might be better I've encountered many of the 
same issues with them. They will do a "major upgrade" once every 18 
months or so and break compatibility if it suits their needs. Only point 
upgrades (purely bug fixes - no new features) are guaranteed to be 
compatible. Remember, breaking compatibility doesn't necessarily require 
an API change. It might involve a configuration change, a change in a 
database schema, changes in its dependencies that impact your project in 
other ways, etc.
>
>>
>>
>> Frankly, even if version ranges worked as above I'd still probably 
>> not use them during a build simply because I want to specify exactly 
>> what is used in the build.
>
> A lot of people probably do too, but that's not what you've been doing 
> with the POMs you use now I'm willing to bet. Almost everyone with the 
> mechanism we have now can be subject to exactly what you describe 
> above without knowing it. Most people don't know the "1.0" in their 
> POMs doesn't actually mean use "1.0" all the time.
If that's what you think then you forget why I've been so slow in 
actually converting my projects from Maven 1 to Maven 2 (which I finally 
found the time to do by the way). We used the jar override feature in 
Maven 1 to specify the version of EVERY dependency.  I wasn't able to 
convert to Maven 2 until we could accomplish the same thing - which we 
are now able to do in a much better way.

However, if simply specifying a specific version in a managed dependency 
doesn't guarantee that  the specified version of that dependency is used 
then I see three problems:
1. The documentation isn't clear enough.
2. I need to modify my managed dependencies to specify the start and end 
of the version range to the same version.
3. Since most people don't expect this behavior one would normally 
consider it to be a bug. Certainly forcing people to have to do the 
previous step is downright awful. It would be much better to provide an 
option that forces only the specified version to be used.
>
>> However, it would be great to know that multiple projects have 
>> dependencies on incompatible versions of the same thing. It would 
>> also be great to have reports that indicate which dependencies could 
>> be safely upgraded.
>
> It should be the exception that it changes in a major version.
>
That's all well and good but it completely misses the point. If you 
really think that Maven can cause every possible project that a project 
might list as a dependency to do things "correctly" you are going to end 
up very frustrated. Maven needs to deal with the world as it is.

Again, I will reiterate. IMO, without projects declaring themselves 
which prior versions they are compatible with no version ranging scheme 
will ever be able to produce a build you can be even close to 100% 
confident in. As always, you are free to disagree.

Ralph

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Jason van Zyl <ja...@maven.org>.
On 21-Jun-08, at 11:16 PM, Ralph Goers wrote:

> See below
>
> Brett Porter wrote:
>> Hi Oleg, all,
>>
>> I haven't dug into any of the code yet, but I've read through the  
>> document you were working on. It seems positive and makes sense. I  
>> did get a bit lost on the meaning of the "Tree Builder" section as  
>> it doesn't seem to describe the current tree or graph technique,  
>> but maybe illustrate the possible combinations?
>>
>> Anyway, a few things caught my attention...
>>
>> You mentioned about the inconsistency of whether 3.8.1 means "must  
>> be 3.8.1" vs "I'm using 3.8.1 right now but I'm not really sure  
>> which versions it works with". Pretty much everyone putting POMs  
>> together does the latter, as they are not trained in specifying  
>> ranges, and because projects do not always follow the guidelines on  
>> versioning such that compatibility can be measured. You also  
>> mentioned that some change to the way ranges are specified might be  
>> needed. I'm wondering what thoughts you have on how we specify  
>> dependencies need to be different from today?
> This is one of the problems that has bothered me for a while. It  
> makes no sense for a project to say I'm compatible with 3.8.x. How  
> in the world could they know that?

In the world where there is some rigour in that the said project  
doesn't change the API within a major release they know very well. In  
Eclipse a great deal of care is taken to make sure that APIs don't  
change within a major release of the platform and ranges in  
dependencies are usually specified as ranges that allow the  
consumption of new versions within a major release version. We're not  
accustom to this here at Apache because there just isn't that level of  
rigour yet.

> The dependent project might release a new 3.8.x release that isn't  
> compatible.

Commercial vendors take a lot more care because people complain  
wildly, and Eclipse takes a lot more care. It's not rocket science to  
use CLIRR, we along with a lot of other open source projects have just  
been lazy.

> Thus, for any kind of version range to have any meaning, projects  
> must declare what prior versions they are compatible with using a  
> declaration that isn't part of the current pom syntax.

I'm not sure it has to be, there generally isn't a very good reason to  
break API compatibility in a major release.

>  Then when a project specifies a dependency on 3.8.1 if there is a  
> 3.8.2 that specifies it is compatible with any prior 3.8.x release  
> it would be fine to use 3.8.2 in the project with the dependency.  
> Without such a specification, in my opinion version ranges aren't  
> particularly useful.

I disagree. There are generally accepted rules about changes in APIs  
in major and minor releases. Takes a conscious effort but tooling can  
help as well. There's a big set of tooling available in the eclipse  
platform to help with this coming in 3.4.

>
>
> Frankly, even if version ranges worked as above I'd still probably  
> not use them during a build simply because I want to specify exactly  
> what is used in the build.

A lot of people probably do too, but that's not what you've been doing  
with the POMs you use now I'm willing to bet. Almost everyone with the  
mechanism we have now can be subject to exactly what you describe  
above without knowing it. Most people don't know the "1.0" in their  
POMs doesn't actually mean use "1.0" all the time.

> However, it would be great to know that multiple projects have  
> dependencies on incompatible versions of the same thing. It would  
> also be great to have reports that indicate which dependencies could  
> be safely upgraded.

It should be the exception that it changes in a major version.

>
>
> Ralph
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
> For additional commands, e-mail: dev-help@maven.apache.org
>

Thanks,

Jason

----------------------------------------------------------
Jason van Zyl
Founder,  Apache Maven
jason at sonatype dot com
----------------------------------------------------------

People develop abstractions by generalizing from concrete examples.
Every attempt to determine the correct abstraction on paper without
actually developing a running system is doomed to failure. No one
is that smart. A framework is a resuable design, so you develop it by
looking at the things it is supposed to be a design of. The more  
examples
you look at, the more general your framework will be.

   -- Ralph Johnson & Don Roberts, Patterns for Evolving Frameworks


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Michael McCallum <gh...@apache.org>.
On Mon, 23 Jun 2008 14:26:38 Michael McCallum wrote:
> have a meeting will explain in more detail later...
have not forgotten just been really busy and want to give this a proper 
treatment...


-- 
Michael McCallum
Enterprise Engineer
mailto:gholam@apache.org

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Michael McCallum <gh...@apache.org>.
On Mon, 23 Jun 2008 14:18:24 Ralph Goers wrote:
> > 2) because and i might be wrong but dependencyManagement messes with the
> > version defined up the chain when what I want is a localised enforcement,
> > its important to isolate the dependency and apply exclusions and version
> > restrictions to guarantee that I get consistent resolution.
>
> What do you mean "up the chain"? dependencyManagement should behave as
> if you specified the version wherever it is encountered in an actual
> dependency. So managed dependencies specified in one part of a
> dependency tree should only affect other parts of the tree in the same
> way they would with the fully specified dependency.
thats my concern...

> As far as I know version ranges should work just fine. I haven't tried
> it because I don't use them. I don't know what you mean by defining
> dependencies "in terms of each other". Do you mean versions 1.1-1.1.5 of
> Project A can use versions 1.0-1.x of Project B? This works until you
> start throwing in Project C, D, E, F, etc which also have dependencies.
> At some point understanding what is really compatible with what is
> extremely difficult.
have a meeting will explain in more detail later...



-- 
Michael McCallum
Enterprise Engineer
mailto:gholam@apache.org

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Ralph Goers <Ra...@dslextreme.com>.

Michael McCallum wrote:
> On Mon, 23 Jun 2008 11:20:40 Ralph Goers wrote:
>   
>> Why aren't you using dependencyManagement instead of the technique shown
>> below?
>>     
> Good question, please refute/correct/flame if/where possible
>
> 1) there was no way to use dependencyManagement with deps  when I adopted the 
> technique. This works now with pom depedencies i think but I'm not certain it 
> provides all the benefits.
>   
I believe it should work now.
> 2) because and i might be wrong but dependencyManagement messes with the 
> version defined up the chain when what I want is a localised enforcement, its 
> important to isolate the dependency and apply exclusions and version 
> restrictions to guarantee that I get consistent resolution.
>   
What do you mean "up the chain"? dependencyManagement should behave as 
if you specified the version wherever it is encountered in an actual 
dependency. So managed dependencies specified in one part of a 
dependency tree should only affect other parts of the tree in the same 
way they would with the fully specified dependency.
> 3) also because i actually use jars for the composites/constraints so that the 
> poms and pom properties end up in my aggregations - they are single merged 
> together... reasons are OT - so i can unravel what actually ended up in the 
> jar if needed. 
>   
I have no idea how this is a benefit. Probably just me not understanding 
something.
> 4) is it possible to use version ranges in dependencyManagement? I was 
> thinking not but have not tried recently. Once you get a reasonable set of 
> constrained external depdencies you naturally want to define them in terms of 
> each other to reduce overhead and to ensure better consistency
>   
As far as I know version ranges should work just fine. I haven't tried 
it because I don't use them. I don't know what you mean by defining 
dependencies "in terms of each other". Do you mean versions 1.1-1.1.5 of 
Project A can use versions 1.0-1.x of Project B? This works until you 
start throwing in Project C, D, E, F, etc which also have dependencies. 
At some point understanding what is really compatible with what is 
extremely difficult.

Ralph

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Michael McCallum <gh...@apache.org>.
On Mon, 23 Jun 2008 11:20:40 Ralph Goers wrote:
> Why aren't you using dependencyManagement instead of the technique shown
> below?
Good question, please refute/correct/flame if/where possible

1) there was no way to use dependencyManagement with deps  when I adopted the 
technique. This works now with pom depedencies i think but I'm not certain it 
provides all the benefits.

2) because and i might be wrong but dependencyManagement messes with the 
version defined up the chain when what I want is a localised enforcement, its 
important to isolate the dependency and apply exclusions and version 
restrictions to guarantee that I get consistent resolution.

3) also because i actually use jars for the composites/constraints so that the 
poms and pom properties end up in my aggregations - they are single merged 
together... reasons are OT - so i can unravel what actually ended up in the 
jar if needed. 

4) is it possible to use version ranges in dependencyManagement? I was 
thinking not but have not tried recently. Once you get a reasonable set of 
constrained external depdencies you naturally want to define them in terms of 
each other to reduce overhead and to ensure better consistency

 

-- 
Michael McCallum
Enterprise Engineer
mailto:gholam@apache.org

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Ralph Goers <Ra...@dslextreme.com>.
Why aren't you using dependencyManagement instead of the technique shown 
below?

Michael McCallum wrote:
> On Sun, 22 Jun 2008 18:16:37 Ralph Goers wrote:
>   
>> This is one of the problems that has bothered me for a while. It makes
>> no sense for a project to say I'm compatible with 3.8.x. How in the
>> world could they know that? The dependent project might release a new
>> 3.8.x release that isn't compatible. Thus, for any kind of version range
>> to have any meaning, projects must declare what prior versions they are
>> compatible with using a declaration that isn't part of the current pom
>> syntax.  Then when a project specifies a dependency on 3.8.1 if there is
>> a 3.8.2 that specifies it is compatible with any prior 3.8.x release it
>> would be fine to use 3.8.2 in the project with the dependency. Without
>> such a specification, in my opinion version ranges aren't particularly
>> useful.
>>     
> I get around this by wrapping a well defined version around a strict range 
> e.g.
>
> i have a special pom project that holds the version of spring that all my 
> projects should use currently at 7.1 which says use 2.0.7
>
> so all my projects use a range of 
> <dependency>
> <version>[7,8-!)</version>
> <groupId>my.domain.constraint</groupId>
> <artifactId>my.domain.constraint.spring</artifactId>
> </dependency>
>
> and my.domain.constraint.spring is defined in brief as
>
> <project ...>
> ...
> <dependency>
> <version>[2.0.7]</version>
> <groupId>org.springframework</groupId>
> <artifactId>context</artifactId>
> </dependency>
> ...
> </project>
>
> the only overhead to this is a few extra artifacts with no code...  hardly a 
> major... there is also the added bonus that you have a convenient place to 
> control exclusions like... commons-logging
>
> having read more of the thread... most of the apache projects are small and 
> have fairly simple trees you can get away with locking vrsion down simply. In 
> my case the trees are fairly horendous and using various pattern and 
> refactoring techiniques was necessary to get clean consistent trees. 
>
> It does mean that I encapsulate the the third party version as shown above and 
> it also lets me guarantee that dependency graph produced by spring, 
> hibernate, jmx, etc etc is the same when used in all my other projects. Each 
> time there is a new release I can just do depedency:resolve and/or 
> depedency:tree and make sure the trees look the same and then run tests on 
> all my projects against the new version to ensure nothing breaks. If 
> something does I can decide to bump the major version of the 'constraint' 
> project or fix the problem in the broken project...
> i don't think that you can ever make a generic solution to this problem you 
> always need a flexible solution close to home, because ultimately you need to 
> manage when and where things change if you ever hope to produce stable 
> software in a timely fashion.
>
>
>   

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Michael McCallum <gh...@apache.org>.
On Sun, 22 Jun 2008 18:16:37 Ralph Goers wrote:
> This is one of the problems that has bothered me for a while. It makes
> no sense for a project to say I'm compatible with 3.8.x. How in the
> world could they know that? The dependent project might release a new
> 3.8.x release that isn't compatible. Thus, for any kind of version range
> to have any meaning, projects must declare what prior versions they are
> compatible with using a declaration that isn't part of the current pom
> syntax.  Then when a project specifies a dependency on 3.8.1 if there is
> a 3.8.2 that specifies it is compatible with any prior 3.8.x release it
> would be fine to use 3.8.2 in the project with the dependency. Without
> such a specification, in my opinion version ranges aren't particularly
> useful.
I get around this by wrapping a well defined version around a strict range 
e.g.

i have a special pom project that holds the version of spring that all my 
projects should use currently at 7.1 which says use 2.0.7

so all my projects use a range of 
<dependency>
<version>[7,8-!)</version>
<groupId>my.domain.constraint</groupId>
<artifactId>my.domain.constraint.spring</artifactId>
</dependency>

and my.domain.constraint.spring is defined in brief as

<project ...>
...
<dependency>
<version>[2.0.7]</version>
<groupId>org.springframework</groupId>
<artifactId>context</artifactId>
</dependency>
...
</project>

the only overhead to this is a few extra artifacts with no code...  hardly a 
major... there is also the added bonus that you have a convenient place to 
control exclusions like... commons-logging

having read more of the thread... most of the apache projects are small and 
have fairly simple trees you can get away with locking vrsion down simply. In 
my case the trees are fairly horendous and using various pattern and 
refactoring techiniques was necessary to get clean consistent trees. 

It does mean that I encapsulate the the third party version as shown above and 
it also lets me guarantee that dependency graph produced by spring, 
hibernate, jmx, etc etc is the same when used in all my other projects. Each 
time there is a new release I can just do depedency:resolve and/or 
depedency:tree and make sure the trees look the same and then run tests on 
all my projects against the new version to ensure nothing breaks. If 
something does I can decide to bump the major version of the 'constraint' 
project or fix the problem in the broken project...
i don't think that you can ever make a generic solution to this problem you 
always need a flexible solution close to home, because ultimately you need to 
manage when and where things change if you ever hope to produce stable 
software in a timely fashion.


-- 
Michael McCallum
Enterprise Engineer
mailto:gholam@apache.org

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Ralph Goers <Ra...@dslextreme.com>.
Jason van Zyl wrote:
>>
>>>
>>> Frankly, even if version ranges worked as above I'd still probably 
>>> not use them during a build simply because I want to specify exactly 
>>> what is used in the build. However, it would be great to know that 
>>> multiple projects have dependencies on incompatible versions of the 
>>> same thing. It would also be great to have reports that indicate 
>>> which dependencies could be safely upgraded.
>> The approach above goes in this direction - it might give some 
>> guarantees. But not too strong - we cannot test behavioral 
>> compatibility.
>
> Not without some decent integration tests no. But you have a pretty 
> good chance with good ITs. We catch lots of shit that compiles, but 
> bombs in our ITs.
>
I believe Oleg meant behavior incompatibilities of third party 
artifacts, not Maven. Maven's ITs can't be expected to detect problems 
with other projects.

Ralph

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Jason van Zyl <ja...@maven.org>.
On 22-Jun-08, at 12:03 AM, Oleg Gusakov wrote:

>
>
> Ralph Goers wrote:
>> See below
>>
>> Brett Porter wrote:
>>> Hi Oleg, all,
>>>
>>> I haven't dug into any of the code yet, but I've read through the  
>>> document you were working on. It seems positive and makes sense. I  
>>> did get a bit lost on the meaning of the "Tree Builder" section as  
>>> it doesn't seem to describe the current tree or graph technique,  
>>> but maybe illustrate the possible combinations?
>>>
>>> Anyway, a few things caught my attention...
>>>
>>> You mentioned about the inconsistency of whether 3.8.1 means "must  
>>> be 3.8.1" vs "I'm using 3.8.1 right now but I'm not really sure  
>>> which versions it works with". Pretty much everyone putting POMs  
>>> together does the latter, as they are not trained in specifying  
>>> ranges, and because projects do not always follow the guidelines  
>>> on versioning such that compatibility can be measured. You also  
>>> mentioned that some change to the way ranges are specified might  
>>> be needed. I'm wondering what thoughts you have on how we specify  
>>> dependencies need to be different from today?
>> This is one of the problems that has bothered me for a while. It  
>> makes no sense for a project to say I'm compatible with 3.8.x. How  
>> in the world could they know that? The dependent project might  
>> release a new 3.8.x release that isn't compatible. Thus, for any  
>> kind of version range to have any meaning, projects must declare  
>> what prior versions they are compatible with using a declaration  
>> that isn't part of the current pom syntax.  Then when a project  
>> specifies a dependency on 3.8.1 if there is a 3.8.2 that specifies  
>> it is compatible with any prior 3.8.x release it would be fine to  
>> use 3.8.2 in the project with the dependency. Without such a  
>> specification, in my opinion version ranges aren't particularly  
>> useful.
> In my personal opinion - wild versioning should go away. We need to  
> impose stardards on versions: at least major.minor.build-[etc]. So -  
> any additive changes increment minir version, any incompatible  
> changes increment major. Build - for developer/QA test/release  
> iterations. We can enforce those rules for binary compatibility, but  
> behavioral compatibility will still be volatile :(
>>
>> Frankly, even if version ranges worked as above I'd still probably  
>> not use them during a build simply because I want to specify  
>> exactly what is used in the build. However, it would be great to  
>> know that multiple projects have dependencies on incompatible  
>> versions of the same thing. It would also be great to have reports  
>> that indicate which dependencies could be safely upgraded.
> The approach above goes in this direction - it might give some  
> guarantees. But not too strong - we cannot test behavioral  
> compatibility.

Not without some decent integration tests no. But you have a pretty  
good chance with good ITs. We catch lots of shit that compiles, but  
bombs in our ITs.

>
>
> Thanks,
> Oleg
>>
>> Ralph
>>
>> ---------------------------------------------------------------------
>> To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
>> For additional commands, e-mail: dev-help@maven.apache.org
>>
>>
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
> For additional commands, e-mail: dev-help@maven.apache.org
>

Thanks,

Jason

----------------------------------------------------------
Jason van Zyl
Founder,  Apache Maven
jason at sonatype dot com
----------------------------------------------------------

You are never dedicated to something you have complete confidence in.
No one is fanatically shouting that the sun is going to rise tomorrow.
They know it is going to rise tomorrow. When people are fanatically
dedicated to political or religious faiths or any other kind of
dogmas or goals, it's always because these dogmas or
goals are in doubt.

   -- Robert Pirzig, Zen and the Art of Motorcycle Maintenance


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Oleg Gusakov <ol...@gmail.com>.

Ralph Goers wrote:
> See below
>
> Brett Porter wrote:
>> Hi Oleg, all,
>>
>> I haven't dug into any of the code yet, but I've read through the 
>> document you were working on. It seems positive and makes sense. I 
>> did get a bit lost on the meaning of the "Tree Builder" section as it 
>> doesn't seem to describe the current tree or graph technique, but 
>> maybe illustrate the possible combinations?
>>
>> Anyway, a few things caught my attention...
>>
>> You mentioned about the inconsistency of whether 3.8.1 means "must be 
>> 3.8.1" vs "I'm using 3.8.1 right now but I'm not really sure which 
>> versions it works with". Pretty much everyone putting POMs together 
>> does the latter, as they are not trained in specifying ranges, and 
>> because projects do not always follow the guidelines on versioning 
>> such that compatibility can be measured. You also mentioned that some 
>> change to the way ranges are specified might be needed. I'm wondering 
>> what thoughts you have on how we specify dependencies need to be 
>> different from today?
> This is one of the problems that has bothered me for a while. It makes 
> no sense for a project to say I'm compatible with 3.8.x. How in the 
> world could they know that? The dependent project might release a new 
> 3.8.x release that isn't compatible. Thus, for any kind of version 
> range to have any meaning, projects must declare what prior versions 
> they are compatible with using a declaration that isn't part of the 
> current pom syntax.  Then when a project specifies a dependency on 
> 3.8.1 if there is a 3.8.2 that specifies it is compatible with any 
> prior 3.8.x release it would be fine to use 3.8.2 in the project with 
> the dependency. Without such a specification, in my opinion version 
> ranges aren't particularly useful.
In my personal opinion - wild versioning should go away. We need to 
impose stardards on versions: at least major.minor.build-[etc]. So - any 
additive changes increment minir version, any incompatible changes 
increment major. Build - for developer/QA test/release iterations. We 
can enforce those rules for binary compatibility, but behavioral 
compatibility will still be volatile :(
>
> Frankly, even if version ranges worked as above I'd still probably not 
> use them during a build simply because I want to specify exactly what 
> is used in the build. However, it would be great to know that multiple 
> projects have dependencies on incompatible versions of the same thing. 
> It would also be great to have reports that indicate which 
> dependencies could be safely upgraded.
The approach above goes in this direction - it might give some 
guarantees. But not too strong - we cannot test behavioral compatibility.

Thanks,
Oleg
>
> Ralph
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
> For additional commands, e-mail: dev-help@maven.apache.org
>
>

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Ralph Goers <Ra...@dslextreme.com>.
See below

Brett Porter wrote:
> Hi Oleg, all,
>
> I haven't dug into any of the code yet, but I've read through the 
> document you were working on. It seems positive and makes sense. I did 
> get a bit lost on the meaning of the "Tree Builder" section as it 
> doesn't seem to describe the current tree or graph technique, but 
> maybe illustrate the possible combinations?
>
> Anyway, a few things caught my attention...
>
> You mentioned about the inconsistency of whether 3.8.1 means "must be 
> 3.8.1" vs "I'm using 3.8.1 right now but I'm not really sure which 
> versions it works with". Pretty much everyone putting POMs together 
> does the latter, as they are not trained in specifying ranges, and 
> because projects do not always follow the guidelines on versioning 
> such that compatibility can be measured. You also mentioned that some 
> change to the way ranges are specified might be needed. I'm wondering 
> what thoughts you have on how we specify dependencies need to be 
> different from today?
This is one of the problems that has bothered me for a while. It makes 
no sense for a project to say I'm compatible with 3.8.x. How in the 
world could they know that? The dependent project might release a new 
3.8.x release that isn't compatible. Thus, for any kind of version range 
to have any meaning, projects must declare what prior versions they are 
compatible with using a declaration that isn't part of the current pom 
syntax.  Then when a project specifies a dependency on 3.8.1 if there is 
a 3.8.2 that specifies it is compatible with any prior 3.8.x release it 
would be fine to use 3.8.2 in the project with the dependency. Without 
such a specification, in my opinion version ranges aren't particularly 
useful.

Frankly, even if version ranges worked as above I'd still probably not 
use them during a build simply because I want to specify exactly what is 
used in the build. However, it would be great to know that multiple 
projects have dependencies on incompatible versions of the same thing. 
It would also be great to have reports that indicate which dependencies 
could be safely upgraded.

Ralph

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org


Re: initial comments on SAT solver document

Posted by Jason van Zyl <ja...@maven.org>.
On 21-Jun-08, at 9:37 PM, Brett Porter wrote:

> Hi Oleg, all,
>
> I haven't dug into any of the code yet, but I've read through the  
> document you were working on. It seems positive and makes sense. I  
> did get a bit lost on the meaning of the "Tree Builder" section as  
> it doesn't seem to describe the current tree or graph technique, but  
> maybe illustrate the possible combinations?
>
> Anyway, a few things caught my attention...
>
> You mentioned about the inconsistency of whether 3.8.1 means "must  
> be 3.8.1" vs "I'm using 3.8.1 right now but I'm not really sure  
> which versions it works with". Pretty much everyone putting POMs  
> together does the latter, as they are not trained in specifying  
> ranges, and because projects do not always follow the guidelines on  
> versioning such that compatibility can be measured. You also  
> mentioned that some change to the way ranges are specified might be  
> needed. I'm wondering what thoughts you have on how we specify  
> dependencies need to be different from today?
>
> I do think the compatibility question is an interesting one. We  
> could theoretically build up a compatibility database in the central  
> repository, even using clirr to make initial assessment on java  
> artifacts. However this is unfortunately never a binary decision  
> either, as you may not be using the incompatible parts, and  
> compatibility can break in non-API ways.
>

There will never be a heuristic that can replace people just taking  
some care with the APIs and their testing. Without that combination on  
the part of the project an external party trying to collect these  
metrics to use is probably not going to be of great value. Retaining  
API compatibility along with a high degree of coverage and you  
probably have a useful metric and really if it's not a conscious  
effort the API will be broken even if inadvertently. The mechanical  
turk is not going to help us much there.

> I'm curious about how these work in terms of remote retrieval (ie,  
> where consulting metadatasource is a costly operation). When I  
> looked at p2 in Sept last year, they stored all the repository  
> artifact metadata in a single, large file.

This is just one implementation of the MetadataRepository API, it's  
not very costly because they only deal with dependencies. Our  
currently because of the POM swizzling we do.

> Are we expecting to need some partial or full resolution of the  
> repository content?
>

When you deal with ranges the number of possible paths grows very  
quickly, and the SAT solver is very fast. You could predigest  
dependency information but pre-calculated subgraphs are probably not  
useful as one change in a range in a path and you're recalculating  
anyway.

> Do you think depth resolution is still relevant if we have a better  
> method? I believe the only depth we really should care about is "1"  
> - those immediately specified (and particularly those managed by  
> depMgmt). With that in mind, how can the use of depMgmt help in  
> reducing the problem space during resolution?

It will boil down to something far simpler. The SAT solver is  
guaranteed to find you a working solution. All ranges are a set where  
that set can be one, or fixed. If you want it weighted to what you say  
in your POM then fix the version. The depMan should not change the  
calculation like it does now, again if you want it fixed then fix it.  
We will let the SAT solver find the solution and we take the magic out.

>
>
> You also mention OSGi resolution at the end. Is it your intent that  
> one of the goals of the mechanism is to be able to be a complete  
> OSGi resolver?

We already have an OSGi resolver in Tycho, this is not the same thing.  
What is in p2 uses SAT, but this is not what's OSGi. No one has made  
it clear if that's what OSGi proper will use but right now the OSGi  
resolver is a simple state machine. What's in p2 is not an OSGi  
resolver even though what it retrieves is ultimately fed into an OSGi  
state machine.

>
>
> I'm also interested in seeing explicit listing of the problems we  
> aim to solve to ensure we have objectives/scope. For example:
> - lack of alternate conflict resolution in current artifact mechanism
> - reduction in amount of metadata and artifacts dragged in (ie,  
> stuff that could use maven 2.0.9 still pulls down whatever version  
> of maven it was built against, even when it's not used)
> - deterministic building over time
>
> Just my initial thoughts - I'll follow your progress as you continue  
> investigating :)
>
> Cheers,
> Brett
>
> --
> Brett Porter
> brett@apache.org
> http://blogs.exist.com/bporter/
>
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
> For additional commands, e-mail: dev-help@maven.apache.org
>

Thanks,

Jason

----------------------------------------------------------
Jason van Zyl
Founder,  Apache Maven
jason at sonatype dot com
----------------------------------------------------------

Three people can keep a secret provided two of them are dead.

  -- Unknown


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@maven.apache.org
For additional commands, e-mail: dev-help@maven.apache.org