JK 1.2.29 Plan

Any objections to the following plan about JK 1.2.29?

- 15.01.2009
   make snapshot available for testing feedback like we did
   for nearly all previous releases

- ~22.01.2009
   tag 1.2.29 (exact date depending whether there's bug feedback)

Regards,

Rainer


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org


Re: JK 1.2.29 Plan

Posted by Mladen Turk <mt...@apache.org>.
On 02/08/2010 08:32 AM, Rainer Jung wrote:
> After a couple of heavily loaded weeks, I'll have time to care about it
> this week. I'll review the changes done by Mladen and will then proceed
> with the usual snapshot for letting people do some tests before the
> final release. I guess I'll need 2 or 3 days before doing the snapshot.
>

I'll make a snapshot today together with widows binaries.
Hope we could have a real tag next week then.

Regards
-- 
^TM

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org


Re: JK 1.2.29 Plan

Posted by Mladen Turk <mt...@apache.org>.
On 02/08/2010 08:32 AM, Rainer Jung wrote:
> After a couple of heavily loaded weeks, I'll have time to care about it
> this week. I'll review the changes done by Mladen and will then proceed
> with the usual snapshot for letting people do some tests before the
> final release. I guess I'll need 2 or 3 days before doing the snapshot.
>

If you don't have a time, I can do some snapshot.


Regards
-- 
^TM

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org


Re: JK 1.2.29 Plan

Posted by Rainer Jung <ra...@kippdata.de>.
After a couple of heavily loaded weeks, I'll have time to care about it 
this week. I'll review the changes done by Mladen and will then proceed 
with the usual snapshot for letting people do some tests before the 
final release. I guess I'll need 2 or 3 days before doing the snapshot.

Regards,

Rainer

On 08.02.2010 08:23, Tim Whittington wrote:
> I guess we need to re-plan this since we missed the dates?
>
> I'll hold off on the IIS log rotation changes until 1.2.29 is tagged.
>
> cheers
> tim
>
>
> From: "Mladen Turk"<mt...@apache.org>
>> To: dev@tomcat.apache.org
>> Sent: Thursday, 7 January, 2010 12:42:07 AM GMT +12:00 New Zealand
>> Subject: Re: JK 1.2.29 Plan
>>
>> +1
>>
>> I've done majority of planned fixes.
>>
>> Let's tag and then play with IIS rotatelogs.
>> BTW, the IIS logging should be fixed now
>> (compiling with commode.obj that forces a real flush on fflush)
>>
>>
>> On 01/06/2010 11:07 AM, Rainer Jung wrote:
>>> Any objections to the following plan about JK 1.2.29?
>>>
>>> - 15.01.2009
>>> make snapshot available for testing feedback like we did
>>> for nearly all previous releases
>>>
>>> - ~22.01.2009
>>> tag 1.2.29 (exact date depending whether there's bug feedback)
>>>
>>>
>>
>> Regards
>> --
>> ^TM

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org


Re: JK 1.2.29 Plan

Posted by Tim Whittington <ti...@apache.org>.
I guess we need to re-plan this since we missed the dates?

I'll hold off on the IIS log rotation changes until 1.2.29 is tagged.

cheers
tim


From: "Mladen Turk" <mt...@apache.org>
> To: dev@tomcat.apache.org
> Sent: Thursday, 7 January, 2010 12:42:07 AM GMT +12:00 New Zealand
> Subject: Re: JK 1.2.29 Plan
>
> +1
>
> I've done majority of planned fixes.
>
> Let's tag and then play with IIS rotatelogs.
> BTW, the IIS logging should be fixed now
> (compiling with commode.obj that forces a real flush on fflush)
>
>
> On 01/06/2010 11:07 AM, Rainer Jung wrote:
> > Any objections to the following plan about JK 1.2.29?
> >
> > - 15.01.2009
> > make snapshot available for testing feedback like we did
> > for nearly all previous releases
> >
> > - ~22.01.2009
> > tag 1.2.29 (exact date depending whether there's bug feedback)
> >
> >
>
> Regards
> --
> ^TM
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
> For additional commands, e-mail: dev-help@tomcat.apache.org
>
>

Re: JK 1.2.29 Plan

Posted by Mladen Turk <mt...@apache.org>.
+1

I've done majority of planned fixes.

Let's tag and then play with IIS rotatelogs.
BTW, the IIS logging should be fixed now
(compiling with commode.obj that forces a real flush on fflush)


On 01/06/2010 11:07 AM, Rainer Jung wrote:
> Any objections to the following plan about JK 1.2.29?
>
> - 15.01.2009
> make snapshot available for testing feedback like we did
> for nearly all previous releases
>
> - ~22.01.2009
> tag 1.2.29 (exact date depending whether there's bug feedback)
>
>

Regards
-- 
^TM

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org


Re: JK 1.2.29 Plan

Posted by Peter Roßbach <pr...@objektpark.de>.
+1

Regards
Peter

Am 06.01.2010 um 11:07 schrieb Rainer Jung:

> Any objections to the following plan about JK 1.2.29?
>
> - 15.01.2009
>  make snapshot available for testing feedback like we did
>  for nearly all previous releases
>
> - ~22.01.2009
>  tag 1.2.29 (exact date depending whether there's bug feedback)
>
> Regards,
>
> Rainer
>
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
> For additional commands, e-mail: dev-help@tomcat.apache.org
>
>


---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org


Re: JK 1.2.29 Plan

Posted by Henri Gomez <he...@gmail.com>.
+1

2010/1/6 Rainer Jung <ra...@kippdata.de>:
> Any objections to the following plan about JK 1.2.29?
>
> - 15.01.2009
>  make snapshot available for testing feedback like we did
>  for nearly all previous releases
>
> - ~22.01.2009
>  tag 1.2.29 (exact date depending whether there's bug feedback)
>
> Regards,
>
> Rainer
>
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
> For additional commands, e-mail: dev-help@tomcat.apache.org
>
>

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscribe@tomcat.apache.org
For additional commands, e-mail: dev-help@tomcat.apache.org