You are viewing a plain text version of this content. The canonical link for it is here.
Posted to issues@ambari.apache.org by "Olivér Szabó (JIRA)" <ji...@apache.org> on 2018/08/20 20:22:00 UTC
[jira] [Updated] (AMBARI-24349) Rescheduled and canceled tasks stay
in progress forever
[ https://issues.apache.org/jira/browse/AMBARI-24349?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]
Olivér Szabó updated AMBARI-24349:
----------------------------------
Resolution: Fixed
Status: Resolved (was: Patch Available)
> Rescheduled and canceled tasks stay in progress forever
> -------------------------------------------------------
>
> Key: AMBARI-24349
> URL: https://issues.apache.org/jira/browse/AMBARI-24349
> Project: Ambari
> Issue Type: Bug
> Reporter: Andrew Onischuk
> Assignee: Andrew Onischuk
> Priority: Major
> Labels: pull-request-available
> Fix For: 2.7.1
>
> Attachments: AMBARI-24349.patch, AMBARI-24349.patch
>
> Time Spent: 3h
> Remaining Estimate: 0h
>
> 1\. Ambari-server reschedules task (timeout #1)
> 2\. Task did yet got rescheduled (due to something else being in queue)
> 3\. but, ambari-server cancels it (timeout #2)
> 4\. The tasks keeps reprorting that's it's in progess forever, however being
> canceled
--
This message was sent by Atlassian JIRA
(v7.6.3#76005)