Schedule for Board Reports

Hi all -

Our next FINERACT project to ASF Board Report is due in early July, three
weeks from now.

Generally, the PMC chair (currently me) asks for input here on list, and
puts a draft together. I have also created the wiki page so we can work on
that directly.

Our Reports are due on a schedule:  January, April, July, October

With over 200 Top Level Projects at ASF, the ASF Board, which meets
Monthly, only reviews individual projects on a staggered quarterly basis.

Our draft Report will be available here ==>.
https://cwiki.apache.org/confluence/display/FINERACT/2023-07+July+Fineract+Report+to+ASF+Board

Let's try to make progress on the things we have discussed on list here
around communications , website, wiki, documentation, and get a release out
or at least schedule as possible.

James Dailey
PMC Chair

Re: July Report Due Soon

Posted by James Dailey <ja...@gmail.com>.
I will be submitting the report in the next 24 hrs or so.
https://cwiki.apache.org/confluence/display/FINERACT/2023-07+July+Fineract+Report+to+ASF+Board


comments welcome

On Sat, Jul 1, 2023 at 12:09 AM Aleksandar Vidakovic <
cheetah@monkeysintown.com> wrote:

> July 10th would be very tight... so, no release.
> On 28/06/2023 23:19, James Dailey wrote:
>
> Ping
>
> Please comment on any progress or challenges you'd like to mention in the
> quarterly report.
>
> @Aleksandar Vidakovic <ch...@monkeysintown.com> - I will assume we
> won't have a release by July 10th.
>
>
>
>
> On Thu, Jun 15, 2023 at 5:42 PM James Dailey <ja...@gmail.com>
> wrote:
>
>> Hi all -
>>
>> Our next FINERACT project to ASF Board Report is due in early July, three
>> weeks from now.
>>
>> Generally, the PMC chair (currently me) asks for input here on list, and
>> puts a draft together. I have also created the wiki page so we can work on
>> that directly.
>>
>> Our Reports are due on a schedule:  January, April, July, October
>>
>> With over 200 Top Level Projects at ASF, the ASF Board, which meets
>> Monthly, only reviews individual projects on a staggered quarterly basis.
>>
>> Our draft Report will be available here ==>.
>> https://cwiki.apache.org/confluence/display/FINERACT/2023-07+July+Fineract+Report+to+ASF+Board
>>
>> Let's try to make progress on the things we have discussed on list here
>> around communications , website, wiki, documentation, and get a release out
>> or at least schedule as possible.
>>
>> James Dailey
>> PMC Chair
>>
>

Re: July Report Due Soon

Posted by Aleksandar Vidakovic <ch...@monkeysintown.com>.
July 10th would be very tight... so, no release.

On 28/06/2023 23:19, James Dailey wrote:
> Ping
>
> Please comment on any progress or challenges you'd like to mention in 
> the quarterly report.
>
> @Aleksandar Vidakovic <ma...@monkeysintown.com> - I will 
> assume we won't have a release by July 10th.
>
>
>
>
> On Thu, Jun 15, 2023 at 5:42 PM James Dailey <ja...@gmail.com> 
> wrote:
>
>     Hi all -
>
>     Our next FINERACT project to ASF Board Report is due in early
>     July, three weeks from now.
>
>     Generally, the PMC chair (currently me) asks for input here on
>     list, and puts a draft together. I have also created the wiki page
>     so we can work on that directly.
>
>     Our Reports are due on a schedule:  January, April, July, October
>
>     With over 200 Top Level Projects at ASF, the ASF Board, which
>     meets Monthly, only reviews individual projects on a staggered
>     quarterly basis.
>
>     Our draft Report will be available here ==>.
>     https://cwiki.apache.org/confluence/display/FINERACT/2023-07+July+Fineract+Report+to+ASF+Board
>
>     Let's try to make progress on the things we have discussed on list
>     here around communications , website, wiki, documentation, and get
>     a release out or at least schedule as possible.
>
>     James Dailey
>     PMC Chair
>

July Report Due Soon

Posted by James Dailey <ja...@gmail.com>.
Ping

Please comment on any progress or challenges you'd like to mention in the
quarterly report.

@Aleksandar Vidakovic <ch...@monkeysintown.com> - I will assume we won't
have a release by July 10th.




On Thu, Jun 15, 2023 at 5:42 PM James Dailey <ja...@gmail.com> wrote:

> Hi all -
>
> Our next FINERACT project to ASF Board Report is due in early July, three
> weeks from now.
>
> Generally, the PMC chair (currently me) asks for input here on list, and
> puts a draft together. I have also created the wiki page so we can work on
> that directly.
>
> Our Reports are due on a schedule:  January, April, July, October
>
> With over 200 Top Level Projects at ASF, the ASF Board, which meets
> Monthly, only reviews individual projects on a staggered quarterly basis.
>
> Our draft Report will be available here ==>.
> https://cwiki.apache.org/confluence/display/FINERACT/2023-07+July+Fineract+Report+to+ASF+Board
>
> Let's try to make progress on the things we have discussed on list here
> around communications , website, wiki, documentation, and get a release out
> or at least schedule as possible.
>
> James Dailey
> PMC Chair
>